Permit: T22CM07302
Permit Details
Status:
Complete
Type:
Commercial Building
Address:
575 E CALLE ARIZONA UNIT 2
Address NEW:
575 E CALLE ARIZONA UNIT 2
Apply Date:
09/22/2022
Applicant:
Kristjan Laumets
Description:
Re-construction of burnt structure unit #2, #3, and #4
Permit Reviews
Permit Number - T22CM07302
Permit Status: Complete
Permit Description: Re-construction of burnt structure unit #2, #3, and #4
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 09/22/2022 | OTHER | 10/18/2022 | COMPLETED |
| 09/14/2023 | RESTAMP - COMMERCIAL v.1 | 09/18/2023 | APPROVED |
| 12/19/2022 | COMMERCIAL REVIEW - FULL v.2 | 01/27/2023 | REQUIRES RESUBMIT |
| 05/08/2023 | COMMERCIAL REVIEW - FULL v.5 | 05/25/2023 | REQUIRES RESUBMIT |
| 06/26/2023 | COMMERCIAL REVIEW - FULL v.6 | 06/26/2023 | REQUIRES RESUBMIT |
| 06/29/2023 | COMMERCIAL REVIEW - FULL v.7 | 06/29/2023 | REQUIRES RESUBMIT |
| 03/24/2023 | COMMERCIAL REVIEW - FULL v.4 | 04/21/2023 | REQUIRES RESUBMIT |
| 08/30/2023 | COMMERCIAL REVIEW - FULL v.9 | 09/14/2023 | APPROVED |
| 11/21/2022 | COMMERCIAL REVIEW - FULL v.1 | 12/06/2022 | REQUIRES RESUBMIT |
| 07/06/2023 | COMMERCIAL REVIEW - FULL v.8 | 08/03/2023 | REQUIRES RESUBMIT |
| 02/16/2023 | COMMERCIAL REVIEW - FULL v.3 | 03/15/2023 | REQUIRES RESUBMIT |
Conditions
Permit Number - T22CM07302
Permit Status: Complete
Permit Description: Re-construction of burnt structure unit #2, #3, and #4
| Date | Description | Comments |
|---|---|---|
| 09/15/2023 | AIR BALANCING REPORT IS REQUIRED. | |
| 02/28/2023 | WATER STERILIZATION REPORT IS REQUIRED. |
Completed Inspections
Permit Status: Complete
Permit Number: T22CM07302
Permit Description: Re-construction of burnt structure unit #2, #3, and #4
Total Completed Inspections - 14
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/25/2023 | COT - LCPL - Rough Soil | Passed | Approved rough soil, okay to backfill and for concrete placement all units | |
| 09/27/2023 | COT - LCEL - Electrical Intermediate | Passed | Approved for all affected units #2,#3,#4 | |
| 09/25/2023 | COT - LCPL - Plumbing Intermediate | Passed | Approved for all affected units #2,#3,#4 | |
| 09/25/2023 | COT - LCME - Mechanical Intermediate | Passed | Approved for all affected units #2,#3,#4 | |
| 02/02/2024 | COT - LCEL - Electrical Above Ceiling | Passed | ||
| 04/09/2024 | BULD - Electrical Clearance | Passed | Clearance for Washer/water heater | |
| 04/26/2024 | COT - LCBU - Building Final | Passed | ||
| 05/02/2024 | COT - BULD - SWG Clearance | Passed | ||
| 05/06/2024 | COT - LCPL - Plumbing Final | Passed | ||
| 05/07/2024 | COT - LCBU - Framing | Passed | ||
| 05/07/2024 | COT - LCBU - Roof Nailing | Passed | ||
| 05/07/2024 | COT - LCEL - Electrical Final | Passed | ||
| 05/07/2024 | COT - LCME - Mechanical Final | Passed | ||
| 05/10/2024 | COT - LCBU - Building Progress | Passed |