Permit: T22CM05804
Permit Details
Apply Date:
07/29/2022
Applicant:
Description:
Proposed construction of a 147,646 sf concrete tilt shell/speculative building and associated site w
Permit Reviews
Permit Number - T22CM05804
Permit Status: Complete
Permit Description: Proposed construction of a 147,646 sf concrete tilt shell/speculative building and associated site w
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 07/29/2022 | COMMERCIAL - BLDG/FIRE/ZONING/ENG | 09/15/2022 | COMPLETED |
| 07/09/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 07/10/2024 | APPROVED |
| 10/17/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 10/21/2025 | APPROVED |
| 04/24/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 04/25/2025 | APPROVED |
| 11/30/2022 | COMMERCIAL REVIEW - FULL v.1 | 01/05/2023 | REQUIRES RESUBMIT |
| 10/29/2024 | COMMERCIAL REVIEW - FULL v.1 | 11/25/2024 | REQUIRES RESUBMIT |
| 08/21/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 09/24/2025 | APPROVED |
| 02/13/2026 | SPECIAL INSPECTION REVIEW v.1 | 02/18/2026 | APPROVED |
| 04/03/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 04/18/2025 | APPROVED |
| 02/16/2023 | COMMERCIAL REVIEW - FULL v.2 | 03/15/2023 | REQUIRES RESUBMIT |
| 07/20/2023 | RESTAMP - COMMERCIAL v.1 | 07/24/2023 | APPROVED |
| 01/17/2025 | COMMERCIAL REVIEW - LIMITED v.1 | 02/04/2025 | APPROVED |
| 12/14/2024 | COMMERCIAL REVIEW - FULL v.2 | 01/14/2025 | APPROVED |
| 07/14/2023 | COMMERCIAL REVIEW - FULL v.3 | 07/20/2023 | APPROVED |
| 01/14/2025 | RESTAMP - COMMERCIAL v.1 | 01/15/2025 | REQUIRES RESUBMIT |
Conditions
Permit Number - T22CM05804
Permit Status: Complete
Permit Description: Proposed construction of a 147,646 sf concrete tilt shell/speculative building and associated site w
| Date | Description | Comments |
|---|---|---|
| 08/20/2024 | SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED. | |
| 05/29/2024 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact. | |
| 06/07/2024 | Prior to Issuance: This project requires issuance of a Development Package (DP) permit prior to issuance of this permit. Prior to TCO/Final: This project requires full completion of a Development Package (DP) permit prior to Temporary C of O and/or final completion this permit. | |
| 08/20/2024 | SPECIAL INSPECTION FOR FIELD WELDING IS REQUIRED. | |
| 08/20/2024 | SPECIAL INSPECTION FOR FOUNDATION/EXCAVATION IS REQUIRED. | |
| 08/20/2024 | SPECIAL INSPECTION FOR HIGH STRENGTH BOLTING IS REQUIRED. | |
| 08/20/2024 | Irrigation Designs must be submitted and approved prior to Final | |
| 08/20/2024 | Storefront Designs must be submitted and approved prior to Final | |
| 08/06/2025 | SPECIAL INSPECTION FOR OUTDOOR LIGHTING IS REQUIRED. | |
| 08/20/2024 | SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED. | |
| 05/29/2024 | A Special Inspections Intermediate Certificate must be submitted and reviewed prior to issuance of this permit. | |
| 08/20/2024 | SPECIAL INSPECTION FOR STRUCTURAL WELDING IS REQUIRED. | |
| 08/20/2024 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. | |
| 03/13/2023 | WATER STERILIZATION REPORT IS REQUIRED. | |
| 08/20/2024 | SPECIAL INSPECTION FOR WOOD FRAMED DIAPHRAGMS AND SHEAR WALLS IS REQUIRED. |
Outstanding Inspections
Permit Status: Complete
Permit Number: T22CM05804
Permite Description: Proposed construction of a 147,646 sf concrete tilt shell/speculative building and associated site w
Total Outstanding Inspections - 8
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/25/2025 | COT - BULD - SWG Clearance | N/A | Not Applicable | 9-25-25: not applicable |
| 05/15/2025 | COT - HCBU - Excavation/Rebar/Zoning | N/A | Partial Pass | 5-15-25, reinforcement on along east side interior perimeter pour back per plans. Okay to pour concrete. |
| 06/24/2025 | COT - HCPL - Plumbing Roof Drains | N/A | Partial Pass | 6/24/2025 Roof drains on grid line I column 2, grid line E column 2, grid line C column 2, Grid line E column 8. Approved. Okay to proceed progress areas. |
| COT - FCON - Alarm - Final | N/A | Not Ready | ||
| 11/04/2025 | COT - FCON - Fire - Final | N/A | Partial Pass | EM lights |
| COT - FCON - Sprinkler - Final | N/A | Not Ready | ||
| 09/30/2025 | COT - HCBU - Building Final | N/A | Re-inspection required | 9-30-25: complete installing all can lights outside of fire pump room at covered awning,and all exterior lights above doors located on southside of building, missing light switch covers at electrical room/fire pump room, call for a drywall nailing inspection prior to tape & texture at south covered awning, provide 3rd party report for outdoor lighting or provide all documentation regarding exterior lights to compare with approved plans, water meter must be installed by the city before closing out plumbing final for shell. |
| 09/30/2025 | ENGR Engineering Final | N/A | Not Ready |
Completed Inspections
Permit Status: Complete
Permit Number: T22CM05804
Permit Description: Proposed construction of a 147,646 sf concrete tilt shell/speculative building and associated site w
Total Completed Inspections - 32
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/30/2025 | COT - HCBU - Roof Nailing | Passed | 4-30-25, nailing for entire roof decking checked & approved. Okay to dry-in roof and continue construction at progress areas. | |
| 07/08/2025 | COT - HCPL - Gas Pressure Test | Passed | 7-8-25: gas pressure test approved. | |
| 08/15/2025 | BULD - Electrical Clearance | Passed | 8-15-25: okay to energize MSA 3000A & Fire Pump-ECO clearance issued to TEP. | |
| 09/22/2025 | COT - HCBU - Building Progress | Passed | 9-22-25: building progress approved. | |
| 09/22/2025 | COT - HCBU - Exterior Clips/Sheathing | Passed | 9-22-25: previously inspected & approved. | |
| 09/22/2025 | COT - HCBU - Preslab | Passed | 9-22-25: previously inspected & approved. | |
| 09/22/2025 | COT - HCBU - Interior Shear Bracing | Passed | 9-22-25: interior shear bracing approved. | |
| 09/22/2025 | COT - HCME - Mechanical Intermediate | Passed | 9-22-25: approved. | |
| 09/22/2025 | COT - HCME - Mechanical Progress | Passed | 9-22-25: mechanical progress approved. | |
| 09/22/2025 | COT - HCPL - Backwater Valve | Passed | 9-22-25: backwater valve approved. | |
| 09/22/2025 | COT - HCPL - Gas Final | Passed | 9-22-25: gas final approved. | |
| 09/22/2025 | COT - HCPL - Plumbing Intermediate | Passed | 9-22-25: plumbing intermediate approved. | |
| 09/22/2025 | COT - HCPL - Rough Soil | Passed | 9-22-25: previously inspected & approved. | |
| 09/22/2025 | COT - HCPL - Sewer | Passed | 9-22-25: previously inspected & approved. | |
| 09/22/2025 | COT - LCBU - Preslab | Passed | 9-22-25: previously inspected & approved. | |
| 09/25/2025 | COT - HCBU - Excavation/Rebar/Zoning | Passed | 9-25-25: previously inspected & approved. | |
| 09/25/2025 | COT - HCBU - Firewall/Fire Barrier/Firestop | Passed | 9-25-25: previously inspected & approved. | |
| 09/25/2025 | COT - HCBU - Framing | Passed | 9-25-25: framing approved. | |
| 09/25/2025 | COT - HCEL - Electrical Intermediate | Passed | 9-25-25: intermediate approved-bonding/ grounding verified per plans. | |
| 09/25/2025 | COT - HCEL - Electrical Progress | Passed | 9-25-25: approved | |
| 09/25/2025 | COT - HCME - Mechanical Final | Passed | 9-25-25: approved. | |
| 09/25/2025 | COT - HCPL - Plumbing Progress | Passed | 9-25-25: approved. | |
| 09/25/2025 | COT - HCPL - Plumbing Roof Drains | Passed | 9-25-25: approved. | |
| 09/25/2025 | COT - HCEL - Electrical Underground | Passed | 9-25-25: bonding/ grounding approved. | |
| 10/01/2025 | TRSP - ROW - Final/Close-Out | Passed | ||
| 11/04/2025 | COT - FCON - Alarm - Final | Passed | ||
| 11/04/2025 | COT - HCEL - Electrical Final | Passed | 11-4-25: electrical final approved. | |
| 11/04/2025 | COT - HCEL - Outdoor Lighting | Passed | 11-4-25: outdoor lighting approved-3rd party inspector also approved and report submitted to the city for review | |
| 11/04/2025 | COT - HCPL - Plumbing Final | Passed | 11-4-25: plumbing final approved. | |
| 11/04/2025 | COT - FCON - Sprinkler - Final | Passed | ||
| 02/12/2026 | COT - HCBU - Building Final | Passed | 2-12-26: building final approved. | |
| 02/12/2026 | ENGR Engineering Final | Passed |