Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Permit: T22CM05804

Parcel: 14042025A


Addresses:

2717 E CORONA RD

Inspection Status: Partial Pass

Inspection History: COT - HCBU - Excavation/Rebar/Zoning 

Date Description Inspector Results Comments
01/08/2025 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 12/13/24: spread footings @GL B-I/3-7
12/18/24: 6” Sanitary sewer per approved plans and under pressure. Ok to backfill. Shading required. GL A-J/3 and A-J/7, electrical underground at SES passed ok to backfill.
12/19/24: contentious footing from GL I-G/2 & F/1-2 & E/1-2 & C-D/2
1/3/25: contentious footing 1 GL A/7.5-8, A-B/9, B/8-9, C-H/8
1/8/25: Reinforcement at Slab on grade per plans at GL A-F/1-5
01/13/2025 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 12/13/24: spread footings @GL B-I/3-7
12/18/24: 6” Sanitary sewer per approved plans and under pressure. Ok to backfill. Shading required. GL A-J/3 and A-J/7, electrical underground at SES passed ok to backfill.
12/19/24: contentious footing from GL I-G/2 & F/1-2 & E/1-2 & C-D/2
1/3/25: contentious footing 1 GL A/7.5-8, A-B/9, B/8-9, C-H/8
1/8/25: Reinforcement at Slab on grade per plans at GL A-F/1-5
1/13/25: reinforcement at Slab on grade per plans for pour#2.
01/17/2025 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 12/13/24: spread footings @GL B-I/3-7
12/18/24: 6” Sanitary sewer per approved plans and under pressure. Ok to backfill. Shading required. GL A-J/3 and A-J/7, electrical underground at SES passed ok to backfill.
12/19/24: contentious footing from GL I-G/2 & F/1-2 & E/1-2 & C-D/2
1/3/25: contentious footing 1 GL A/7.5-8, A-B/9, B/8-9, C-H/8
1/8/25: Reinforcement at Slab on grade per plans at GL A-F/1-5
1/13/25: reinforcement at Slab on grade per plans for pour#2.
1/17/25: reinforcement at Slab on grade per plans for pour #3 and4 ok to proceed,
01/27/2025 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 12/13/24: spread footings @GL B-I/3-7
12/18/24: 6” Sanitary sewer per approved plans and under pressure. Ok to backfill. Shading required. GL A-J/3 and A-J/7, electrical underground at SES passed ok to backfill.
12/19/24: contentious footing from GL I-G/2 & F/1-2 & E/1-2 & C-D/2
1/3/25: contentious footing 1 GL A/7.5-8, A-B/9, B/8-9, C-H/8
1/8/25: Reinforcement at Slab on grade per plans at GL A-F/1-5
1/13/25: reinforcement at Slab on grade per plans for pour#2.
1/17/25: reinforcement at Slab on grade per plans for pour #3 and4 ok to proceed,
1/27/25: reinforcement per plan at perimeter footing GL I-J/1-9.
02/10/2025 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 12/13/24: spread footings @GL B-I/3-7
12/18/24: 6” Sanitary sewer per approved plans and under pressure. Ok to backfill. Shading required. GL A-J/3 and A-J/7, electrical underground at SES passed ok to backfill.
12/19/24: contentious footing from GL I-G/2 & F/1-2 & E/1-2 & C-D/2
1/3/25: contentious footing 1 GL A/7.5-8, A-B/9, B/8-9, C-H/8
1/8/25: Reinforcement at Slab on grade per plans at GL A-F/1-5
1/13/25: reinforcement at Slab on grade per plans for pour#2.
1/17/25: reinforcement at Slab on grade per plans for pour #3 and4 ok to proceed,
1/27/25: reinforcement per plan at perimeter footing GL I-J/1-9.
2/10/25: reinforcement per plans at panels1-9, 79-64
02/11/2025 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 12/13/24: spread footings @GL B-I/3-7
12/18/24: 6” Sanitary sewer per approved plans and under pressure. Ok to backfill. Shading required. GL A-J/3 and A-J/7, electrical underground at SES passed ok to backfill.
12/19/24: contentious footing from GL I-G/2 & F/1-2 & E/1-2 & C-D/2
1/3/25: contentious footing 1 GL A/7.5-8, A-B/9, B/8-9, C-H/8
1/8/25: Reinforcement at Slab on grade per plans at GL A-F/1-5
1/13/25: reinforcement at Slab on grade per plans for pour#2.
1/17/25: reinforcement at Slab on grade per plans for pour #3 and4 ok to proceed,
1/27/25: reinforcement per plan at perimeter footing GL I-J/1-9.
2/10/25: reinforcement per plans at panels1-9, 79-64
2/11/25: reinforcement per plans at pour two for tilt up panels.
02/14/2025 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 12/13/24: spread footings @GL B-I/3-7
12/18/24: 6” Sanitary sewer per approved plans and under pressure. Ok to backfill. Shading required. GL A-J/3 and A-J/7, electrical underground at SES passed ok to backfill.
12/19/24: contentious footing from GL I-G/2 & F/1-2 & E/1-2 & C-D/2
1/3/25: contentious footing 1 GL A/7.5-8, A-B/9, B/8-9, C-H/8
1/8/25: Reinforcement at Slab on grade per plans at GL A-F/1-5
1/13/25: reinforcement at Slab on grade per plans for pour#2.
1/17/25: reinforcement at Slab on grade per plans for pour #3 and4 ok to proceed,
1/27/25: reinforcement per plan at perimeter footing GL I-J/1-9.
2/10/25: reinforcement per plans at panels1-9, 79-64
2/11/25: reinforcement per plans at pour two for tilt up panels.
2/14/25: reinforcement per plan at continuous footer for concrete tilt up wall GL A-J/1 and J/1-9.
02/19/2025 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 12/13/24: spread footings @GL B-I/3-7
12/18/24: 6” Sanitary sewer per approved plans and under pressure. Ok to backfill. Shading required. GL A-J/3 and A-J/7, electrical underground at SES passed ok to backfill.
12/19/24: contentious footing from GL I-G/2 & F/1-2 & E/1-2 & C-D/2
1/3/25: contentious footing 1 GL A/7.5-8, A-B/9, B/8-9, C-H/8
1/8/25: Reinforcement at Slab on grade per plans at GL A-F/1-5
1/13/25: reinforcement at Slab on grade per plans for pour#2.
1/17/25: reinforcement at Slab on grade per plans for pour #3 and4 ok to proceed,
1/27/25: reinforcement per plan at perimeter footing GL I-J/1-9.
2/10/25: reinforcement per plans at panels1-9, 79-64
2/11/25: reinforcement per plans at pour two for tilt up panels.
2/14/25: reinforcement per plan at continuous footer for concrete tilt up wall GL A-J/1 and J/1-9.
2/20/25: reinforcement per plan for pour 3 and 4 for tilt up panels. Approved by third party inspector.
02/24/2025 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 2-24-25, reinforcement layout on pads 10, 11, 12, 13, 14, 15, 16, & 20 verified per plan. Okay to pour.
02/28/2025 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 12/13/24: spread footings @GL B-I/3-7
12/18/24: 6” Sanitary sewer per approved plans and under pressure. Ok to backfill. Shading required. GL A-J/3 and A-J/7, electrical underground at SES passed ok to backfill.
12/19/24: contentious footing from GL I-G/2 & F/1-2 & E/1-2 & C-D/2
1/3/25: contentious footing 1 GL A/7.5-8, A-B/9, B/8-9, C-H/8
1/8/25: Reinforcement at Slab on grade per plans at GL A-F/1-5
1/13/25: reinforcement at Slab on grade per plans for pour#2.
1/17/25: reinforcement at Slab on grade per plans for pour #3 and4 ok to proceed,
1/27/25: reinforcement per plan at perimeter footing GL I-J/1-9.
2/10/25: reinforcement per plans at panels1-9, 79-64
2/11/25: reinforcement per plans at pour two for tilt up panels.
2/14/25: reinforcement per plan at continuous footer for concrete tilt up wall GL A-J/1 and J/1-9.
2/20/25: reinforcement per plan for pour 3 and 4 for tilt up panels. Approved by third party inspector.
2-24-25, reinforcement layout on pads 10, 11, 12, 13, 14, 15, 16, & 20 verified per plan. Okay to pour.
2/28/25: reinforcement per plan at west continuous footer.
04/07/2025 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass East side loading dock leveler pads, Ok to place concrete in progress areas.
05/08/2025 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 5-8-25, reinforcement for interior perimeter pour back on south end verified per plans. Okay to pour concrete.
05/15/2025 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 5-15-25, reinforcement on along east side interior perimeter pour back per plans. Okay to pour concrete.
09/25/2025 COT - HCBU - Excavation/Rebar/Zoning  Passed 9-25-25: previously inspected & approved.