Proposed Construction of new 2-lane drive-through salad-assembly restaurant with carry out facility.

Permit Reviews

Permit Number - T22CM04580
Permit Status: Complete
Permit Description: Proposed Construction of new 2-lane drive-through salad-assembly restaurant with carry out facility.
Start Date Submittal Complete Date Status  
06/18/2022 COMMERCIAL - BLDG/FIRE/ZONING/ENG 08/08/2022 COMPLETED Review Details
01/28/2023 COMMERCIAL REVIEW - FULL v.1 03/02/2023 REQUIRES RESUBMIT Review Details
04/11/2024 BUILDING DEFERRED SUBMITTAL REVIEW v.2 04/11/2024 REQUIRES RESUBMIT Review Details
04/08/2024 BUILDING DEFERRED SUBMITTAL REVIEW v.1 04/08/2024 REQUIRES RESUBMIT Review Details
05/07/2024 BUILDING DEFERRED SUBMITTAL REVIEW v.3 05/09/2024 APPROVED Review Details
05/22/2024 BUILDING DEFERRED SUBMITTAL REVIEW v.1 05/22/2024 APPROVED Review Details
10/20/2023 BUILDING DEFERRED SUBMITTAL REVIEW v.1 10/20/2023 APPROVED Review Details
03/07/2023 COMMERCIAL REVIEW - FULL v.2 03/14/2023 APPROVED Review Details

Conditions

Permit Number - T22CM04580
Permit Status: Complete
Permit Description: Proposed Construction of new 2-lane drive-through salad-assembly restaurant with carry out facility.
Date Description Comments
03/10/2023 AIR BALANCING/COMMISSIONING REPORT IS REQUIRED.
03/27/2024 SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED.
03/10/2023 Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit.
03/27/2024 COUNTY HEALTH INSPECTION IS REQUIRED - PLEASE PROVIDE DOCUMENTATION THAT THE INSPECTION HAS BEEN COMPLETED AND PASSED.
05/09/2024 SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED.
03/27/2024 SPECIAL INSPECTION FOR STRUCTURAL MASONRY IS REQUIRED.
03/10/2023 WATER STERILIZATION REPORT IS REQUIRED.

Outstanding Inspections

Permit Status: Complete
Permit Number: T22CM04580
Permite Description: Proposed Construction of new 2-lane drive-through salad-assembly restaurant with carry out facility.
Total Outstanding Inspections - 10
Last Inspection Date Description Inspector Results Comments
07/13/2023 COT - HCME - Mechanical Intermediate N/A Not Applicable
05/12/2023 COT - HCPL - Plumbing Progress N/A Canceled 5-12-23: Wanted water meter.
04/11/2023 COT - HCBU - Building Progress N/A Partial Pass 4-10-23: Wall sheathing.
04/03/2023 COT - HCBU - Framing N/A Partial Pass 4-3-23: Complete installation of screws in shear.
05/09/2023 COT - HCBU - Interior Shear Bracing N/A Not Ready
10/12/2023 COT - HCEL - Electrical Final N/A Re-inspection required 10/3/23: not ready for electrical final. Electric intermediate and electric above ceiling have not passed inspection.

10/12/23: not ready, above ceiling incomplete, type panel schedules, move j-box under pick-up window closer to building and finish concrete to match existing.
10/05/2023 COT - HCBU - Building Above Ceiling N/A Re-inspection required (with fee) 7/13/23: Not ready for the inspection, open j-boxes and wire not made up, flex duct and registers not installed.

8/14/23: inspection canceled per contractor.

10/4/23: not ready

10/5/23: Not ready. Pay a re-fee before any more inspections.
10/16/2023 ENGR Engineering Final N/A Not Ready ramp will stop at window, landing at window, ramp will continue after window. TCO level 4 granted per D Roberts.
09/22/2023 COT - HCPL - Plumbing Intermediate N/A Canceled Wanted sewer inspection.
10/16/2023 COT - HCBU - Building Final N/A Partial Pass 10/13/23: Not ready for final. Electric not ready, waiting on site engineering final.

10/16/23: OK to issue TCO level 4.

Completed Inspections

Permit Status: Complete
Permit Number: T22CM04580
Permit Description: Proposed Construction of new 2-lane drive-through salad-assembly restaurant with carry out facility.
Total Completed Inspections - 24
Date Description Inspector Results Comments
05/12/2023 COT - HCBU - Excavation/Rebar/Zoning Passed
05/18/2023 COT - HCEL - Electrical Underground Passed passed clear for fill in
08/14/2023 TRSP - ROW - Final/Close-Out Passed
09/27/2023 BULD - Electrical Clearance Passed Approved 400A service, ECO Clearance to TEP is required
09/28/2023 COT - HCEL - Electrical Progress Passed
10/12/2023 COT - HCPL - Plumbing Final Passed
10/13/2023 COT - HCME - Mechanical Final Passed
10/13/2023 COT - HCBU - Building Progress Passed
10/13/2023 COT - HCBU - Framing Passed
10/13/2023 COT - HCEL - Electrical Intermediate Passed
10/13/2023 COT - HCPL - Sewer Passed
10/16/2023 COT - HCEL - Electrical Final Passed
10/16/2023 COT - HCBU - Building Above Ceiling Passed
10/17/2023 COT - FCON - Fire - Final Passed
10/18/2023 ENGR Engineering Final Passed
03/26/2024 COT - BULD - SWG Clearance Passed n.a
03/26/2024 COT - HCBU - Masonry Pregrout Passed
03/26/2024 COT - HCBU - Preslab Passed
03/26/2024 COT - HCBU - Roof Nailing Passed
03/26/2024 COT - HCPL - Plumbing Intermediate Passed
03/26/2024 COT - HCPL - Plumbing Above Ceiling Passed
03/26/2024 COT - HCPL - Plumbing Roof Drains Passed
03/26/2024 COT - HCPL - Rough Soil Passed
03/27/2024 COT - HCBU - Building Final Passed

Documents

File Name Document Type  
COFO_FINALCOFO_COMMERCIAL.PDF DOCUMENTS VIEW
T22CM4580, 2943XZ061, A - E BUILDERS, SALAD - GO SPEEDWAY, SRIC, FINAL INSPECTION[18]-2024-05-06_V3.PDF DOCUMENTS VIEW
COFO_TEMPORARYCOFO.PDF DOCUMENTS VIEW
CHLORINATION TEST- TURNER LABS_V1.PDF DOCUMENTS VIEW
SPEEDWAY AIR BALANCE REPORT_V1.PDF DOCUMENTS VIEW
COFO_TEMPORARYCOFO.PDF DOCUMENTS VIEW
COFO_TEMPORARYCOFO.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
CONS-CONS-T22CM04580-BUILDING DEPARTMENT RESUBMISSION-03-02-23_V2.PDF DOCUMENTS VIEW
DP22-0167 COMMENT RESPONSES_V1.PDF DOCUMENTS VIEW
TDC-COMMENT RESPONSES-01.10.23_V1.PDF DOCUMENTS VIEW