Inspection Status: Not Ready
Inspection History: ENGR Engineering Final
| Date |
Description |
Inspector |
Results |
Comments |
| 08/14/2023 |
ENGR Engineering Final
|
|
Not Ready |
complete project per approved plans |
| 10/12/2023 |
ENGR Engineering Final
|
|
Not Ready |
|
| 10/13/2023 |
ENGR Engineering Final
|
|
Partial Pass |
Engineering has no issues it would prevent a temporary certificate of occupancy. Complete the remaining work and schedule inspections from the development package permit. |
| 10/16/2023 |
ENGR Engineering Final
|
|
Not Ready |
ramp will stop at window, landing at window, ramp will continue after window. TCO level 4 granted per D Roberts. |
| 10/17/2023 |
ENGR Engineering Final
|
|
Passed |
|