Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T22CM03954
Permit Details
Status:
Needs Resubmittal
Type:
Commercial Building
Address:
4150 E LOS REALES RD BLDG 2
Address NEW:
4150 E LOS REALES RD BLDG 2
Apply Date:
05/24/2022
Applicant:
Adam Jones
Description:
NEW INDUSTRIAL WAREHOUSE BUILDING #2 Shell
Permit Reviews
Permit Number - T22CM03954
Permit Status: Needs resubmittal
Permit Description: NEW INDUSTRIAL WAREHOUSE BUILDING #2 Shell
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 05/24/2022 | COMMERCIAL - BLDG/FIRE/ZONING/ENG | 10/14/2022 | COMPLETED |
| 10/18/2022 | RESUBMITTAL | 10/18/2022 | ACTIVE |
| 10/29/2025 | COMMERCIAL REVIEW - FULL v.3 | 11/04/2025 | APPROVED |
| 10/28/2022 | COMMERCIAL REVIEW - FULL v.1 | 12/07/2022 | REQUIRES RESUBMIT |
| 01/16/2025 | COMMERCIAL REVIEW - FULL v.2 | 02/20/2025 | REQUIRES RESUBMIT |
| 07/20/2023 | COMMERCIAL REVIEW - FULL v.3 | 07/24/2023 | APPROVED |
| 12/02/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 12/04/2025 | REQUIRES RESUBMIT |
| 11/10/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 11/19/2025 | REQUIRES RESUBMIT |
| 11/20/2024 | COMMERCIAL REVIEW - FULL v.1 | 12/23/2024 | REQUIRES RESUBMIT |
| 06/07/2023 | COMMERCIAL REVIEW - FULL v.2 | 06/22/2023 | REQUIRES RESUBMIT |
Outstanding Activity Conditions
Permit Number - T22CM03954
Permit Status: Needs resubmittal
Permit Description: NEW INDUSTRIAL WAREHOUSE BUILDING #2 Shell
Total Outstanding Activity Conditions - 19
| Date | Name |
|---|---|
| 08/21/2024 | Applies to All: Deferred submittal documents must be submitted and approved prior to installation of construction elements included in deferred submittal documents. |
| 08/21/2024 | Special inspections must be performed by an approved third party inspection agency at the owner's expense. Special inspection forms and reports are required to be submitted for review and approved prior to issuance of final approval documents. |
| 08/21/2024 | SPECIAL INSPECTION FOR BOLTS INSTALLED IN CONCRETE IS REQUIRED. |
| 08/21/2024 | SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED. |
| 08/21/2024 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. |
| 08/21/2024 | SPECIAL INSPECTION FOR EXPANSION ANCHORS IS REQUIRED. |
| 08/21/2024 | Exterior Building Signage Designs must be submitted and approved prior to final |
| 08/21/2024 | High Pile Storage Designs must be submitted and approved prior to final |
| 08/21/2024 | SPECIAL INSPECTION FOR HIGH STRENGTH BOLTING IS REQUIRED. |
| 08/21/2024 | Ladder Safety System Design and Support Designs must be submitted and approved prior to final |
| 08/21/2024 | SPECIAL INSPECTION FOR OUTDOOR LIGHTING IS REQUIRED. |
| 08/21/2024 | Roof Access Ladder/Platform Design and Support Deferred Submittal Designs must be submitted and approved prior to final |
| 08/21/2024 | SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED. |
| 08/21/2024 | SPECIAL INSPECTION FOR Plywood Roof Diaphragm IS REQUIRED |
| 08/21/2024 | Stair Designs must be submitted and approved prior to intermediate inspections if residential building or finalizing the permit if commercial building |
| 08/21/2024 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. |
| 08/21/2024 | SPECIAL INSPECTION FOR STRUCTURAL MASONRY IS REQUIRED. |
| 08/21/2024 | SPECIAL INSPECTION FOR WELDING IS REQUIRED. |
| 10/30/2025 | Submission of the final Elevation Certificate and completion of the Floodplain Use Permit is required PRIOR TO FINALING this permit. |
Conditions
Permit Number - T22CM03954
Permit Status: Needs resubmittal
Permit Description: NEW INDUSTRIAL WAREHOUSE BUILDING #2 Shell
| Date | Description | Comments |
|---|---|---|
| 06/07/2023 | Please contact Pima County Addressing to resolve your addressing issue related to FILL IN THIS SPACE. Addressing@pima.gov or 520-724-9512 | |
| 05/24/2022 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. | |
| 06/07/2023 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. | |
| 07/24/2023 | Prior to Issuance: This project requires issuance of a Development Package (DP22-0122) permit prior to issuance of this permit. Prior to TCO/Final: This project requires full completion of a Development Package (DP) permit prior to Temporary C of O and/or final completion this permit. | |
| 08/21/2024 | SPECIAL INSPECTION FOR REINFORCING STEEL AND/OR PRE-STRESSING TENDONS IS REQUIRED. | |
| 06/15/2023 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. | |
| 08/21/2024 | Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. For More Information visit https://www.pima.gov/1076/Sewer-Connection-Permits, To check your permit status https://permits.pima.gov/ |
Outstanding Inspections
Permit Status: Needs Resubmittal
Permit Number: T22CM03954
Permite Description: NEW INDUSTRIAL WAREHOUSE BUILDING #2 Shell
Total Outstanding Inspections - 12
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/21/2025 | COT - HCPL - Rough Soil | N/A | Partial Pass | 2-21-25, previously inspected and approved by Gustavo. |
| 09/11/2025 | COT - HCBU - Masonry Pregrout | N/A | Not Applicable | 9-11-25: not applicable |
| 05/02/2025 | COT - HCEL - Electrical Underground | N/A | Partial Pass | 5-2-25, verified approximately 70' of 2-1" Schedule 40 conduits on west side of Building 2 for side lighting. Okay to backfill progress areas. |
| 07/09/2025 | COT - HCEL - Electrical Progress | N/A | Partial Pass | 7-9-25: SES ,panels , grounding/bonding on Building 2 verified per plans. Okay to continue with construction at progress areas. |
| 12/31/2024 | COT - HCBU - Excavation/Rebar/Zoning | N/A | Partial Pass | Grid line B, C, and D. From 2-13. Total of 36 spread footers 6’x6’x16”. Rebar per plan okay for concrete placement. 10/17/2024 10/22/24: reinforcement per plan at footing 1 GL E 2.5/12 10/25/24: reinforcement per plan at footing 1 GL A 2.5/12 10/25/24: partial for UFER encased in concrete ok to proceed. 10/30/24: reinforcement per plan at GL E.5-D/1, B-D/2, D/7, 11/15/24: reinforcement per plan at second pour at slab ok to proceed. 12/10/24:Tilt Panel Rebar Pour #1 SE corner of Building passed. Ok to proceed 12/18/24: tilt panel rebar pour #2,3,4 reinforced per plans ok to proceed. 12/23/24: called Don no answer. Footings not ready 12/31/24: Rebar inspection of footing connections Panel 66-77A per detail 103/ S5.1. And Detail 108/ S5.1 for ramp walls prior to concrete placement. |
| 09/11/2025 | HCBU - Preslab and Floodplain Inspection | N/A | Not Applicable | 9-11-25: n/a |
| 01/23/2025 | COT - HCBU - Framing | N/A | Partial Pass | 1/23/25: Pre-Inspection purlin hardware |
| 03/13/2025 | COT - HCBU - Building Progress | N/A | Re-inspection required | 3-13-25, pressure test for manhole 1 verified at 10 psi. Manholes 2-6 at 8 psi-reinspection required. |
| 10/29/2025 | ENGR Engineering Final | N/A | Not Ready | Recall Inspection after permit revision is completed. |
| 10/29/2025 | BULD - Electrical Clearance | N/A | Not Applicable | 10-29-25: previously inspected and cleared with TEP. |
| 10/29/2025 | COT - BULD - SWG Clearance | N/A | Not Applicable | 10-29-25: not applicable. |
| 11/20/2025 | COT - HCBU - TCO | N/A | Not Applicable | 11-20-25: not applicable-duplicate work order. |
Completed Inspections
Permit Status: Needs Resubmittal
Permit Number: T22CM03954
Permit Description: NEW INDUSTRIAL WAREHOUSE BUILDING #2 Shell
Total Completed Inspections - 19
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/18/2025 | COT - HCBU - Roof Nailing | Passed | ||
| 08/13/2025 | COT - FCON - Sprinkler - Final | Passed | ||
| 08/13/2025 | COT - HCEL - Electrical Final | Passed | 8-13-25 electrical final approved. | |
| 08/13/2025 | COT - HCEL - Outdoor Lighting | Passed | 8-13-25: outdoor lighting approved. | |
| 08/14/2025 | COT - FCON - Alarm - Final | Passed | ||
| 08/14/2025 | COT - HCPL - Plumbing Final | Passed | 8-14-25: plumbing final approved. Note: RFI reference drain leader height has been submitted to the city on Building 2 & 3. |
|
| 08/14/2025 | COT - LCBU - Building Final | Passed | 8-14-25: Building final on Building 2 approved. Note: See pending conditions. |
|
| 09/11/2025 | COT - HCPL - Rough Soil | Passed | 9-11-25: approved. | |
| 09/11/2025 | COT - HCEL - Electrical Underground | Passed | 9-11-25: approved | |
| 09/11/2025 | COT - HCEL - Electrical Progress | Passed | 9-11-25: previously inspected & approved. | |
| 09/11/2025 | COT - HCEL - Electrical Intermediate | Passed | 9-11-25: previously inspected & approved. | |
| 09/11/2025 | COT - HCEL - Electrical Above Ceiling | Passed | 9-11-25: previously inspected & approved. | |
| 09/11/2025 | COT - HCBU - Excavation/Rebar/Zoning | Passed | 9-11-25: approved | |
| 09/11/2025 | COT - HCBU - Framing | Passed | 9-11-25: previously inspected & approved. | |
| 09/11/2025 | COT - HCBU - Building Progress | Passed | 9-11-25: approved | |
| 09/11/2025 | COT - HCBU - Building Final | Passed | 9-11-25: approved | |
| 09/11/2025 | COT - HCBU - Building Above Ceiling | Passed | 9-11-25: previously inspected & approved. | |
| 09/11/2025 | COT - HCPL - Plumbing Intermediate | Passed | 9-11-25: previously inspected & approved. | |
| 09/11/2025 | COT - FCON - Fire - Final | Passed |