Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Details

Status:
Needs Resubmittal
Type:
Commercial Building
Apply Date:
05/24/2022
Applicant:
Adam Jones
Description:
NEW INDUSTRIAL WAREHOUSE BUILDING #2 Shell

Permit Reviews

Permit Number - T22CM03954
Permit Status: Needs resubmittal
Permit Description: NEW INDUSTRIAL WAREHOUSE BUILDING #2 Shell
Start Date Submittal Complete Date Status  
05/24/2022 COMMERCIAL - BLDG/FIRE/ZONING/ENG 10/14/2022 COMPLETED Review Details
10/18/2022 RESUBMITTAL 10/18/2022 ACTIVE Review Details
10/29/2025 COMMERCIAL REVIEW - FULL v.3 11/04/2025 APPROVED Review Details
10/28/2022 COMMERCIAL REVIEW - FULL v.1 12/07/2022 REQUIRES RESUBMIT Review Details
01/16/2025 COMMERCIAL REVIEW - FULL v.2 02/20/2025 REQUIRES RESUBMIT Review Details
07/20/2023 COMMERCIAL REVIEW - FULL v.3 07/24/2023 APPROVED Review Details
12/02/2025 BUILDING DEFERRED SUBMITTAL REVIEW v.1 12/04/2025 REQUIRES RESUBMIT Review Details
11/10/2025 BUILDING DEFERRED SUBMITTAL REVIEW v.1 11/19/2025 REQUIRES RESUBMIT Review Details
11/20/2024 COMMERCIAL REVIEW - FULL v.1 12/23/2024 REQUIRES RESUBMIT Review Details
06/07/2023 COMMERCIAL REVIEW - FULL v.2 06/22/2023 REQUIRES RESUBMIT Review Details

Outstanding Activity Conditions

Permit Number - T22CM03954
Permit Status: Needs resubmittal
Permit Description: NEW INDUSTRIAL WAREHOUSE BUILDING #2 Shell
Total Outstanding Activity Conditions - 19
Date Name
08/21/2024 Applies to All: Deferred submittal documents must be submitted and approved prior to installation of construction elements included in deferred submittal documents.
08/21/2024 Special inspections must be performed by an approved third party inspection agency at the owner's expense. Special inspection forms and reports are required to be submitted for review and approved prior to issuance of final approval documents.
08/21/2024 SPECIAL INSPECTION FOR BOLTS INSTALLED IN CONCRETE IS REQUIRED.
08/21/2024 SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED.
08/21/2024 SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED.
08/21/2024 SPECIAL INSPECTION FOR EXPANSION ANCHORS IS REQUIRED.
08/21/2024 Exterior Building Signage Designs must be submitted and approved prior to final
08/21/2024 High Pile Storage Designs must be submitted and approved prior to final
08/21/2024 SPECIAL INSPECTION FOR HIGH STRENGTH BOLTING IS REQUIRED.
08/21/2024 Ladder Safety System Design and Support Designs must be submitted and approved prior to final
08/21/2024 SPECIAL INSPECTION FOR OUTDOOR LIGHTING IS REQUIRED.
08/21/2024 Roof Access Ladder/Platform Design and Support Deferred Submittal Designs must be submitted and approved prior to final
08/21/2024 SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED.
08/21/2024 SPECIAL INSPECTION FOR Plywood Roof Diaphragm IS REQUIRED
08/21/2024 Stair Designs must be submitted and approved prior to intermediate inspections if residential building or finalizing the permit if commercial building
08/21/2024 Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building.
08/21/2024 SPECIAL INSPECTION FOR STRUCTURAL MASONRY IS REQUIRED.
08/21/2024 SPECIAL INSPECTION FOR WELDING IS REQUIRED.
10/30/2025 Submission of the final Elevation Certificate and completion of the Floodplain Use Permit is required PRIOR TO FINALING this permit.

Conditions

Permit Number - T22CM03954
Permit Status: Needs resubmittal
Permit Description: NEW INDUSTRIAL WAREHOUSE BUILDING #2 Shell
Date Description Comments
06/07/2023 Please contact Pima County Addressing to resolve your addressing issue related to FILL IN THIS SPACE. Addressing@pima.gov or 520-724-9512
05/24/2022 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.
06/07/2023 Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit.
07/24/2023 Prior to Issuance: This project requires issuance of a Development Package (DP22-0122) permit prior to issuance of this permit. Prior to TCO/Final: This project requires full completion of a Development Package (DP) permit prior to Temporary C of O and/or final completion this permit.
08/21/2024 SPECIAL INSPECTION FOR REINFORCING STEEL AND/OR PRE-STRESSING TENDONS IS REQUIRED.
06/15/2023 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment.
08/21/2024 Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. For More Information visit https://www.pima.gov/1076/Sewer-Connection-Permits, To check your permit status https://permits.pima.gov/

Outstanding Inspections

Permit Status: Needs Resubmittal
Permit Number: T22CM03954
Permite Description: NEW INDUSTRIAL WAREHOUSE BUILDING #2 Shell
Total Outstanding Inspections - 12
Last Inspection Date Description Inspector Results Comments
02/21/2025 COT - HCPL - Rough Soil N/A Partial Pass 2-21-25, previously inspected and approved by Gustavo.
09/11/2025 COT - HCBU - Masonry Pregrout N/A Not Applicable 9-11-25: not applicable
05/02/2025 COT - HCEL - Electrical Underground N/A Partial Pass 5-2-25, verified approximately 70' of 2-1" Schedule 40 conduits on west side of Building 2 for side lighting. Okay to backfill progress areas.
07/09/2025 COT - HCEL - Electrical Progress N/A Partial Pass 7-9-25: SES ,panels , grounding/bonding on Building 2 verified per plans. Okay to continue with construction at progress areas.
12/31/2024 COT - HCBU - Excavation/Rebar/Zoning N/A Partial Pass Grid line B, C, and D. From 2-13. Total of 36 spread footers 6’x6’x16”. Rebar per plan okay for concrete placement. 10/17/2024
10/22/24: reinforcement per plan at footing 1 GL E 2.5/12
10/25/24: reinforcement per plan at footing 1 GL A 2.5/12
10/25/24: partial for UFER encased in concrete ok to proceed.
10/30/24: reinforcement per plan at GL E.5-D/1, B-D/2, D/7,
11/15/24: reinforcement per plan at second pour at slab ok to proceed.
12/10/24:Tilt Panel Rebar Pour #1 SE corner of Building passed. Ok to proceed
12/18/24: tilt panel rebar pour #2,3,4 reinforced per plans ok to proceed.
12/23/24: called Don no answer. Footings not ready
12/31/24: Rebar inspection of footing connections Panel 66-77A per detail 103/ S5.1. And Detail 108/ S5.1 for ramp walls prior to concrete placement.
09/11/2025 HCBU - Preslab and Floodplain Inspection N/A Not Applicable 9-11-25: n/a
01/23/2025 COT - HCBU - Framing N/A Partial Pass 1/23/25: Pre-Inspection purlin hardware
03/13/2025 COT - HCBU - Building Progress N/A Re-inspection required 3-13-25, pressure test for manhole 1 verified at 10 psi. Manholes 2-6 at 8 psi-reinspection required.
10/29/2025 ENGR Engineering Final N/A Not Ready Recall Inspection after permit revision is completed.
10/29/2025 BULD - Electrical Clearance N/A Not Applicable 10-29-25: previously inspected and cleared with TEP.
10/29/2025 COT - BULD - SWG Clearance N/A Not Applicable 10-29-25: not applicable.
11/20/2025 COT - HCBU - TCO N/A Not Applicable 11-20-25: not applicable-duplicate work order.

Completed Inspections

Permit Status: Needs Resubmittal
Permit Number: T22CM03954
Permit Description: NEW INDUSTRIAL WAREHOUSE BUILDING #2 Shell
Total Completed Inspections - 19
Date Description Inspector Results Comments
02/18/2025 COT - HCBU - Roof Nailing Passed
08/13/2025 COT - FCON - Sprinkler - Final Passed
08/13/2025 COT - HCEL - Electrical Final Passed 8-13-25 electrical final approved.
08/13/2025 COT - HCEL - Outdoor Lighting Passed 8-13-25: outdoor lighting approved.
08/14/2025 COT - FCON - Alarm - Final Passed
08/14/2025 COT - HCPL - Plumbing Final Passed 8-14-25: plumbing final approved.
Note: RFI reference drain leader height has been submitted to the city on Building 2 & 3.
08/14/2025 COT - LCBU - Building Final Passed 8-14-25: Building final on Building 2 approved.
Note: See pending conditions.
09/11/2025 COT - HCPL - Rough Soil Passed 9-11-25: approved.
09/11/2025 COT - HCEL - Electrical Underground Passed 9-11-25: approved
09/11/2025 COT - HCEL - Electrical Progress Passed 9-11-25: previously inspected & approved.
09/11/2025 COT - HCEL - Electrical Intermediate Passed 9-11-25: previously inspected & approved.
09/11/2025 COT - HCEL - Electrical Above Ceiling Passed 9-11-25: previously inspected & approved.
09/11/2025 COT - HCBU - Excavation/Rebar/Zoning Passed 9-11-25: approved
09/11/2025 COT - HCBU - Framing Passed 9-11-25: previously inspected & approved.
09/11/2025 COT - HCBU - Building Progress Passed 9-11-25: approved
09/11/2025 COT - HCBU - Building Final Passed 9-11-25: approved
09/11/2025 COT - HCBU - Building Above Ceiling Passed 9-11-25: previously inspected & approved.
09/11/2025 COT - HCPL - Plumbing Intermediate Passed 9-11-25: previously inspected & approved.
09/11/2025 COT - FCON - Fire - Final Passed

Documents

File Name Document Type  
CONS-PLAN SET_V2 BUILDING 2_V2_V1.PDF DOCUMENTS VIEW
PERMIT CARD.PDF DOCUMENTS VIEW
COFO_TEMPORARYCOFO.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
CONS-PLAN SET_V1.PDF DOCUMENTS VIEW
I-10 INTERNATIONAL RESPONSE TO COM-B_V3_V1.PDF DOCUMENTS VIEW
CONS-1_PLAN SET (BUILDING B)_V3_V1.PDF DOCUMENTS VIEW
CONS-2_CIVIL-LANDSCAPE DEVELOPMENT PACKAGE_V3_V1.PDF DOCUMENTS VIEW