Permit: T22CM03954

Parcel: 14044004C

Inspection Status: Re-inspection required

Inspection History: COT - HCBU - Building Progress

Date Description Inspector Results Comments
03/13/2025 COT - HCBU - Building Progress Re-inspection required 3-13-25, pressure test for manhole 1 verified at 10 psi. Manholes 2-6 at 8 psi-reinspection required.
04/28/2025 COT - HCBU - Building Progress Canceled 4-28-25, canceled.
09/11/2025 COT - HCBU - Building Progress Passed 9-11-25: approved
11/15/2024 COT - HCBU - Building Progress Partial Pass 11/15/24: reinforcement per plan at second pour ok to proceed.
12/12/2024 COT - HCBU - Building Progress Partial Pass 11/15/24: reinforcement per plan at second pour ok to proceed.
12/12/24:Tilt Panel Rebar and embed for Panel Pour #2 passed (panels 6,7,8,9,10,16,17,18,11,15,13,19,28,20,21,22,23,24,25,26,27,29,30,31,32)
12/18/2024 COT - HCBU - Building Progress Partial Pass 11/15/24: reinforcement per plan at second pour ok to proceed.
12/12/24:Tilt Panel Rebar and embed for Panel Pour #2 passed (panels 6,7,8,9,10,16,17,18,11,15,13,19,28,20,21,22,23,24,25,26,27,29,30,31,32)
Grid line B, C, and D. From 2-13. Total of 36 spread footers 6’x6’x16”. Rebar per plan okay for concrete placement. 10/17/2024
10/22/24: reinforcement per plan at footing 1 GL E 2.5/12
10/25/24: reinforcement per plan at footing 1 GL A 2.5/12
10/25/24: partial for UFER encased in concrete ok to proceed.
10/30/24: reinforcement per plan at GL E.5-D/1, B-D/2, D/7,
11/15/24: reinforcement per plan at second pour at slab ok to proceed.
12/10/24:Tilt Panel Rebar Pour #1 SE corner of Building passed. Ok to proceed
12/18/24: tilt panel rebar pour #2,3,4 reinforced per plans ok to proceed.