Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

PRO is currently experiencing an outage. Some documents and records may not be available on PRO momentarily. We apologize for the inconvenience and are working to restore full access.

Permit: T22CM03954

Parcel: 14044004C

Inspection Status: Re-inspection required

Inspection History: COT - HCBU - Excavation/Rebar/Zoning 

Date Description Inspector Results Comments
01/08/2025 COT - HCBU - Excavation/Rebar/Zoning  Re-inspection required Grid line B, C, and D. From 2-13. Total of 36 spread footers 6’x6’x16”. Rebar per plan okay for concrete placement. 10/17/2024
10/22/24: reinforcement per plan at footing 1 GL E 2.5/12
10/25/24: reinforcement per plan at footing 1 GL A 2.5/12
10/25/24: partial for UFER encased in concrete ok to proceed.
10/30/24: reinforcement per plan at GL E.5-D/1, B-D/2, D/7,
11/15/24: reinforcement per plan at second pour at slab ok to proceed.
12/10/24:Tilt Panel Rebar Pour #1 SE corner of Building passed. Ok to proceed
12/18/24: tilt panel rebar pour #2,3,4 reinforced per plans ok to proceed.
12/23/24: called Don no answer. Footings not ready
12/31/24: Rebar inspection of footing connections Panel 66-77A per detail 103/ S5.1. And Detail 108/ S5.1 for ramp walls prior to concrete placement.
1/8/24: reinforcement at Tilt up panels tie-in not per plan (details 103 B), reinforcement missing per plan at tie-ins, reinforcement not per plan, panel missing 3#6 dowels on both ends to tie in (RFI required)
01/10/2025 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Grid line B, C, and D. From 2-13. Total of 36 spread footers 6’x6’x16”. Rebar per plan okay for concrete placement. 10/17/2024
10/22/24: reinforcement per plan at footing 1 GL E 2.5/12
10/25/24: reinforcement per plan at footing 1 GL A 2.5/12
10/25/24: partial for UFER encased in concrete ok to proceed.
10/30/24: reinforcement per plan at GL E.5-D/1, B-D/2, D/7,
11/15/24: reinforcement per plan at second pour at slab ok to proceed.
12/10/24:Tilt Panel Rebar Pour #1 SE corner of Building passed. Ok to proceed
12/18/24: tilt panel rebar pour #2,3,4 reinforced per plans ok to proceed.
12/23/24: called Don no answer. Footings not ready
12/31/24: Rebar inspection of footing connections Panel 66-77A per detail 103/ S5.1. And Detail 108/ S5.1 for ramp walls prior to concrete placement.
1/8/24: reinforcement at Tilt up panels tie-in not per plan (details 103 B), reinforcement missing per plan at tie-ins, reinforcement not per plan, panel missing 3#6 dowels on both ends to tie in (RFI required)
1/10/25: corrections made at panel tie-ins. Ok to proceed with concrete placement, 3 ramp footings inspected and passed.
04/11/2025 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 4-11-25, reinforcement for tie back around entire interior perimeter of Building 2 approved. Okay to progress areas.
09/11/2025 COT - HCBU - Excavation/Rebar/Zoning  Passed 9-11-25: approved
10/18/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Grid line B, C, and D. From 2-13. Total of 36 spread footers 6’x6’x16”. Rebar per plan okay for concrete placement. 10/17/2024
10/22/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Grid line B, C, and D. From 2-13. Total of 36 spread footers 6’x6’x16”. Rebar per plan okay for concrete placement. 10/17/2024
10/22/24: reinforcement per plan at footing 1 GL E 2.5/12
10/25/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Grid line B, C, and D. From 2-13. Total of 36 spread footers 6’x6’x16”. Rebar per plan okay for concrete placement. 10/17/2024
10/22/24: reinforcement per plan at footing 1 GL E 2.5/12
10/25/24: reinforcement per plan at footing 1 GL A 2.5/12
10/30/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Grid line B, C, and D. From 2-13. Total of 36 spread footers 6’x6’x16”. Rebar per plan okay for concrete placement. 10/17/2024
10/22/24: reinforcement per plan at footing 1 GL E 2.5/12
10/25/24: reinforcement per plan at footing 1 GL A 2.5/12
10/25/24: partial for UFER encased in concrete ok to proceed.
10/30/24: reinforcement per plan at GL E.5-D/1, B-D/2, D/7,
11/15/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Grid line B, C, and D. From 2-13. Total of 36 spread footers 6’x6’x16”. Rebar per plan okay for concrete placement. 10/17/2024
10/22/24: reinforcement per plan at footing 1 GL E 2.5/12
10/25/24: reinforcement per plan at footing 1 GL A 2.5/12
10/25/24: partial for UFER encased in concrete ok to proceed.
10/30/24: reinforcement per plan at GL E.5-D/1, B-D/2, D/7,
11/15/24: reinforcement per plan at second pour at slab ok to proceed.
11/20/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Grid line B, C, and D. From 2-13. Total of 36 spread footers 6’x6’x16”. Rebar per plan okay for concrete placement. 10/17/2024
10/22/24: reinforcement per plan at footing 1 GL E 2.5/12
10/25/24: reinforcement per plan at footing 1 GL A 2.5/12
10/25/24: partial for UFER encased in concrete ok to proceed.
10/30/24: reinforcement per plan at GL E.5-D/1, B-D/2, D/7,
11/15/24: reinforcement per plan at second pour at slab ok to proceed.
12/10/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Grid line B, C, and D. From 2-13. Total of 36 spread footers 6’x6’x16”. Rebar per plan okay for concrete placement. 10/17/2024
10/22/24: reinforcement per plan at footing 1 GL E 2.5/12
10/25/24: reinforcement per plan at footing 1 GL A 2.5/12
10/25/24: partial for UFER encased in concrete ok to proceed.
10/30/24: reinforcement per plan at GL E.5-D/1, B-D/2, D/7,
11/15/24: reinforcement per plan at second pour at slab ok to proceed.
12/10/24:Tilt Panel Rebar Pour #1 SE corner of Building passed. Ok to proceed
12/18/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Grid line B, C, and D. From 2-13. Total of 36 spread footers 6’x6’x16”. Rebar per plan okay for concrete placement. 10/17/2024
10/22/24: reinforcement per plan at footing 1 GL E 2.5/12
10/25/24: reinforcement per plan at footing 1 GL A 2.5/12
10/25/24: partial for UFER encased in concrete ok to proceed.
10/30/24: reinforcement per plan at GL E.5-D/1, B-D/2, D/7,
11/15/24: reinforcement per plan at second pour at slab ok to proceed.
12/10/24:Tilt Panel Rebar Pour #1 SE corner of Building passed. Ok to proceed
12/18/24: tilt panel rebar pour #2,3,4 reinforced per plans ok to proceed.
12/23/2024 COT - HCBU - Excavation/Rebar/Zoning  Not Ready Grid line B, C, and D. From 2-13. Total of 36 spread footers 6’x6’x16”. Rebar per plan okay for concrete placement. 10/17/2024
10/22/24: reinforcement per plan at footing 1 GL E 2.5/12
10/25/24: reinforcement per plan at footing 1 GL A 2.5/12
10/25/24: partial for UFER encased in concrete ok to proceed.
10/30/24: reinforcement per plan at GL E.5-D/1, B-D/2, D/7,
11/15/24: reinforcement per plan at second pour at slab ok to proceed.
12/10/24:Tilt Panel Rebar Pour #1 SE corner of Building passed. Ok to proceed
12/18/24: tilt panel rebar pour #2,3,4 reinforced per plans ok to proceed.
12/23/24: called Don no answer. Footings not ready
12/31/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Grid line B, C, and D. From 2-13. Total of 36 spread footers 6’x6’x16”. Rebar per plan okay for concrete placement. 10/17/2024
10/22/24: reinforcement per plan at footing 1 GL E 2.5/12
10/25/24: reinforcement per plan at footing 1 GL A 2.5/12
10/25/24: partial for UFER encased in concrete ok to proceed.
10/30/24: reinforcement per plan at GL E.5-D/1, B-D/2, D/7,
11/15/24: reinforcement per plan at second pour at slab ok to proceed.
12/10/24:Tilt Panel Rebar Pour #1 SE corner of Building passed. Ok to proceed
12/18/24: tilt panel rebar pour #2,3,4 reinforced per plans ok to proceed.
12/23/24: called Don no answer. Footings not ready
12/31/24: Rebar inspection of footing connections Panel 66-77A per detail 103/ S5.1. And Detail 108/ S5.1 for ramp walls prior to concrete placement.