Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit: T22CM03954

Parcel: 14044004C

Inspection Status: Re-inspection required

Inspection History: COT - HCBU - Excavation/Rebar/Zoning 

Permit Number - T22CM03954

Inspection Description - COT - HCBU - Excavation/Rebar/Zoning 

Inspection Status - Re-inspection required

Date Description Inspector Results Comments
01/08/2025 COT - HCBU - Excavation/Rebar/Zoning  Re-inspection required Grid line B, C, and D. From 2-13. Total of 36 spread footers 6’x6’x16”. Rebar per plan okay for concrete placement. 10/17/2024
10/22/24: reinforcement per plan at footing 1 GL E 2.5/12
10/25/24: reinforcement per plan at footing 1 GL A 2.5/12
10/25/24: partial for UFER encased in concrete ok to proceed.
10/30/24: reinforcement per plan at GL E.5-D/1, B-D/2, D/7,
11/15/24: reinforcement per plan at second pour at slab ok to proceed.
12/10/24:Tilt Panel Rebar Pour #1 SE corner of Building passed. Ok to proceed
12/18/24: tilt panel rebar pour #2,3,4 reinforced per plans ok to proceed.
12/23/24: called Don no answer. Footings not ready
12/31/24: Rebar inspection of footing connections Panel 66-77A per detail 103/ S5.1. And Detail 108/ S5.1 for ramp walls prior to concrete placement.
1/8/24: reinforcement at Tilt up panels tie-in not per plan (details 103 B), reinforcement missing per plan at tie-ins, reinforcement not per plan, panel missing 3#6 dowels on both ends to tie in (RFI required)
01/10/2025 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Grid line B, C, and D. From 2-13. Total of 36 spread footers 6’x6’x16”. Rebar per plan okay for concrete placement. 10/17/2024
10/22/24: reinforcement per plan at footing 1 GL E 2.5/12
10/25/24: reinforcement per plan at footing 1 GL A 2.5/12
10/25/24: partial for UFER encased in concrete ok to proceed.
10/30/24: reinforcement per plan at GL E.5-D/1, B-D/2, D/7,
11/15/24: reinforcement per plan at second pour at slab ok to proceed.
12/10/24:Tilt Panel Rebar Pour #1 SE corner of Building passed. Ok to proceed
12/18/24: tilt panel rebar pour #2,3,4 reinforced per plans ok to proceed.
12/23/24: called Don no answer. Footings not ready
12/31/24: Rebar inspection of footing connections Panel 66-77A per detail 103/ S5.1. And Detail 108/ S5.1 for ramp walls prior to concrete placement.
1/8/24: reinforcement at Tilt up panels tie-in not per plan (details 103 B), reinforcement missing per plan at tie-ins, reinforcement not per plan, panel missing 3#6 dowels on both ends to tie in (RFI required)
1/10/25: corrections made at panel tie-ins. Ok to proceed with concrete placement, 3 ramp footings inspected and passed.
04/11/2025 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 4-11-25, reinforcement for tie back around entire interior perimeter of Building 2 approved. Okay to progress areas.
09/11/2025 COT - HCBU - Excavation/Rebar/Zoning  Passed 9-11-25: approved
10/18/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Grid line B, C, and D. From 2-13. Total of 36 spread footers 6’x6’x16”. Rebar per plan okay for concrete placement. 10/17/2024
10/22/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Grid line B, C, and D. From 2-13. Total of 36 spread footers 6’x6’x16”. Rebar per plan okay for concrete placement. 10/17/2024
10/22/24: reinforcement per plan at footing 1 GL E 2.5/12
10/25/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Grid line B, C, and D. From 2-13. Total of 36 spread footers 6’x6’x16”. Rebar per plan okay for concrete placement. 10/17/2024
10/22/24: reinforcement per plan at footing 1 GL E 2.5/12
10/25/24: reinforcement per plan at footing 1 GL A 2.5/12
10/30/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Grid line B, C, and D. From 2-13. Total of 36 spread footers 6’x6’x16”. Rebar per plan okay for concrete placement. 10/17/2024
10/22/24: reinforcement per plan at footing 1 GL E 2.5/12
10/25/24: reinforcement per plan at footing 1 GL A 2.5/12
10/25/24: partial for UFER encased in concrete ok to proceed.
10/30/24: reinforcement per plan at GL E.5-D/1, B-D/2, D/7,
11/15/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Grid line B, C, and D. From 2-13. Total of 36 spread footers 6’x6’x16”. Rebar per plan okay for concrete placement. 10/17/2024
10/22/24: reinforcement per plan at footing 1 GL E 2.5/12
10/25/24: reinforcement per plan at footing 1 GL A 2.5/12
10/25/24: partial for UFER encased in concrete ok to proceed.
10/30/24: reinforcement per plan at GL E.5-D/1, B-D/2, D/7,
11/15/24: reinforcement per plan at second pour at slab ok to proceed.
11/20/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Grid line B, C, and D. From 2-13. Total of 36 spread footers 6’x6’x16”. Rebar per plan okay for concrete placement. 10/17/2024
10/22/24: reinforcement per plan at footing 1 GL E 2.5/12
10/25/24: reinforcement per plan at footing 1 GL A 2.5/12
10/25/24: partial for UFER encased in concrete ok to proceed.
10/30/24: reinforcement per plan at GL E.5-D/1, B-D/2, D/7,
11/15/24: reinforcement per plan at second pour at slab ok to proceed.
12/10/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Grid line B, C, and D. From 2-13. Total of 36 spread footers 6’x6’x16”. Rebar per plan okay for concrete placement. 10/17/2024
10/22/24: reinforcement per plan at footing 1 GL E 2.5/12
10/25/24: reinforcement per plan at footing 1 GL A 2.5/12
10/25/24: partial for UFER encased in concrete ok to proceed.
10/30/24: reinforcement per plan at GL E.5-D/1, B-D/2, D/7,
11/15/24: reinforcement per plan at second pour at slab ok to proceed.
12/10/24:Tilt Panel Rebar Pour #1 SE corner of Building passed. Ok to proceed
12/18/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Grid line B, C, and D. From 2-13. Total of 36 spread footers 6’x6’x16”. Rebar per plan okay for concrete placement. 10/17/2024
10/22/24: reinforcement per plan at footing 1 GL E 2.5/12
10/25/24: reinforcement per plan at footing 1 GL A 2.5/12
10/25/24: partial for UFER encased in concrete ok to proceed.
10/30/24: reinforcement per plan at GL E.5-D/1, B-D/2, D/7,
11/15/24: reinforcement per plan at second pour at slab ok to proceed.
12/10/24:Tilt Panel Rebar Pour #1 SE corner of Building passed. Ok to proceed
12/18/24: tilt panel rebar pour #2,3,4 reinforced per plans ok to proceed.
12/23/2024 COT - HCBU - Excavation/Rebar/Zoning  Not Ready Grid line B, C, and D. From 2-13. Total of 36 spread footers 6’x6’x16”. Rebar per plan okay for concrete placement. 10/17/2024
10/22/24: reinforcement per plan at footing 1 GL E 2.5/12
10/25/24: reinforcement per plan at footing 1 GL A 2.5/12
10/25/24: partial for UFER encased in concrete ok to proceed.
10/30/24: reinforcement per plan at GL E.5-D/1, B-D/2, D/7,
11/15/24: reinforcement per plan at second pour at slab ok to proceed.
12/10/24:Tilt Panel Rebar Pour #1 SE corner of Building passed. Ok to proceed
12/18/24: tilt panel rebar pour #2,3,4 reinforced per plans ok to proceed.
12/23/24: called Don no answer. Footings not ready
12/31/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Grid line B, C, and D. From 2-13. Total of 36 spread footers 6’x6’x16”. Rebar per plan okay for concrete placement. 10/17/2024
10/22/24: reinforcement per plan at footing 1 GL E 2.5/12
10/25/24: reinforcement per plan at footing 1 GL A 2.5/12
10/25/24: partial for UFER encased in concrete ok to proceed.
10/30/24: reinforcement per plan at GL E.5-D/1, B-D/2, D/7,
11/15/24: reinforcement per plan at second pour at slab ok to proceed.
12/10/24:Tilt Panel Rebar Pour #1 SE corner of Building passed. Ok to proceed
12/18/24: tilt panel rebar pour #2,3,4 reinforced per plans ok to proceed.
12/23/24: called Don no answer. Footings not ready
12/31/24: Rebar inspection of footing connections Panel 66-77A per detail 103/ S5.1. And Detail 108/ S5.1 for ramp walls prior to concrete placement.