Permit: T21CM01719
Permit Details
Status:
Complete
Type:
Commercial Building
Address:
785 W SAHUARO ST BLDG 2
Address NEW:
785 W SAHUARO ST BLDG 2
Apply Date:
02/26/2021
Applicant:
Description:
NEW BUILDING ADDITION ON THE SOUTH SIDE OF THE EXISTING EDUCATION BUILDING. THE USE WILL BE OFFICE.
Permit Reviews
Permit Number - T21CM01719
Permit Status: Complete
Permit Description: NEW BUILDING ADDITION ON THE SOUTH SIDE OF THE EXISTING EDUCATION BUILDING. THE USE WILL BE OFFICE.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/19/2022 | REVISION - - 1ST | 01/20/2022 | COMPLETED |
| 02/02/2022 | REVISION - - 1ST | 02/07/2022 | COMPLETED |
| 03/01/2021 | COMMERCIAL - NEW | 04/09/2021 | COMPLETED |
| 04/26/2021 | RESUBMITTAL | 05/25/2021 | COMPLETED |
| 12/16/2021 | REVISION - - 1ST | 01/03/2022 | COMPLETED |
| 02/15/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 02/26/2024 | APPROVED |
Outstanding Inspections
Permit Status: Complete
Permit Number: T21CM01719
Permite Description: NEW BUILDING ADDITION ON THE SOUTH SIDE OF THE EXISTING EDUCATION BUILDING. THE USE WILL BE OFFICE.
Total Outstanding Inspections - 11
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/26/2022 | COT - LCEL - Electrical Intermediate | N/A | Not Ready | |
| 06/28/2023 | BULD - Electrical Clearance | N/A | Not Applicable | previously completed |
| 10/26/2022 | COT - LCME - Mechanical Final | N/A | Not Ready | |
| 10/26/2022 | COT - FCON - Alarm - Final | N/A | Not Ready | |
| 04/28/2023 | COT - LCEL - Electrical Progress | N/A | Not Ready | |
| 10/26/2022 | COT - LCPL - Plumbing Progress | N/A | Not Ready | |
| 02/07/2024 | COT - LCBU - Building Final | N/A | Partial Pass | Partial pending other inspections. 2/7/2024 |
| 10/26/2022 | COT - LCBU - Excavation/Rebar/Zoning | N/A | Not Ready | |
| 10/26/2022 | COT - LCBU - Masonry Pregrout | N/A | Not Ready | |
| 06/28/2023 | COT - LCEL - Electrical Above Ceiling | N/A | Not Ready | |
| 04/17/2023 | COT - LCBU - Building Progress | N/A | Partial Pass | partial approval for hard lid screws |
Completed Inspections
Permit Status: Complete
Permit Number: T21CM01719
Permit Description: NEW BUILDING ADDITION ON THE SOUTH SIDE OF THE EXISTING EDUCATION BUILDING. THE USE WILL BE OFFICE.
Total Completed Inspections - 30
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/27/2022 | COT - LCBU - Stem Wall/Retaining Wall | Passed | {Activity date: 09/27/2022; Status: Approved; Inspector: ESTEVENS; Comment: Entered by NGARCIA3 - Stem wall. Approved } |
|
| 10/12/2022 | COT - LCBU - Preslab | Passed | {Activity date: 10/12/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - Approved} | |
| 01/05/2023 | COT - LCBU - Roof Nailing | Passed | Ok to dry-in roof system. Trusses have been installed. | |
| 03/13/2023 | COT - LCPL - Plumbing Intermediate | Passed | ||
| 03/13/2023 | COT - LCBU - Framing | Passed | ||
| 03/13/2023 | COT - LCEL - Electrical Intermediate | Passed | ||
| 05/08/2023 | COT - LCBU - Building Above Ceiling | Passed | Education center,ok to set ceiling tiles throughout. | |
| 11/02/2023 | COT - LCPL - Plumbing Final | Passed | ||
| 11/29/2023 | COT - LCEL - Electrical Final | Passed | ||
| 11/29/2023 | COT - LCME - Mechanical Final | Passed | ||
| 01/19/2024 | COT - FCON - Alarm - Final | Passed | ||
| 02/12/2024 | COT - LCEL - Electrical Progress | Passed | ||
| 02/12/2024 | COT - LCPL - Gas Pressure Test | Passed | ||
| 02/12/2024 | COT - LCPL - Plumbing Progress | Passed | ||
| 02/12/2024 | COT - LCBU - Building Final | Passed | ||
| 02/14/2024 | COT - LCBU - Excavation/Rebar/Zoning | Passed | ||
| 02/14/2024 | COT - LCBU - Masonry Pregrout | Passed | ||
| 02/14/2024 | COT - HCBU - Interior Shear Bracing | Passed | ||
| 02/14/2024 | COT - LCEL - Electrical Above Ceiling | Passed | ||
| 02/14/2024 | COT - LCME - Mechanical Above Ceiling | Passed | ||
| 02/14/2024 | COT - FCON - Fire - Final | Passed | ||
| 02/14/2024 | COT - LCBU - Sustainability | Passed | ||
| 02/14/2024 | COT - LCPL - Plumbing Above Ceiling | Passed | ||
| 02/14/2024 | COT - LCME - Mechanical Intermediate | Passed | ||
| 02/14/2024 | COT - LCBU - Building Progress | Passed | ||
| 02/14/2024 | COT - LCEL - Outdoor Lighting | Passed | ||
| 02/14/2024 | COT - LCPL - Plumbing Roof Drains | Passed | ||
| 02/14/2024 | COT - LCME - Mechanical Progress | Passed | ||
| 02/14/2024 | COT - FCON - Sprinkler - Final | Passed | ||
| 02/14/2024 | COT - HCPL - Rough Soil | Passed |