Permit Details

Status:
Complete
Type:
Commercial Building
Apply Date:
10/29/2020
Applicant:
Michelle McConnell
Description:
CULTURAL KITCHEN EXPANSION

Permit Reviews

Permit Number - T20CM07489
Permit Status: Complete
Permit Description: CULTURAL KITCHEN EXPANSION
Start Date Submittal Complete Date Status  
02/24/2021 RESUBMITTAL - TI ALL 03/24/2021 COMPLETED Review Details
04/05/2021 RESUBMITTAL 04/15/2021 COMPLETED Review Details
04/20/2021 RESUBMITTAL 04/22/2021 COMPLETED Review Details
05/25/2021 REVISION - - 1ST 06/08/2021 COMPLETED Review Details
06/10/2021 REVISION - - 2ND 06/21/2021 COMPLETED Review Details
07/28/2021 REVISION - - 3RD 08/25/2021 COMPLETED Review Details
10/12/2021 REVISION - - 3RD 10/12/2021 COMPLETED Review Details
10/15/2021 RESUBMITTAL 10/25/2021 COMPLETED Review Details
10/29/2020 COMMERCIAL - NEW 12/21/2020 COMPLETED Review Details
03/28/2024 BUILDING DEFERRED SUBMITTAL REVIEW v.1 04/02/2024 APPROVED Review Details
05/02/2023 BUILDING DEFERRED SUBMITTAL REVIEW v.1 05/03/2023 REQUIRES RESUBMIT Review Details
05/17/2023 BUILDING DEFERRED SUBMITTAL REVIEW v.2 05/19/2023 APPROVED Review Details

Conditions

Permit Number - T20CM07489
Permit Status: Complete
Permit Description: CULTURAL KITCHEN EXPANSION
Date Description Comments
10/29/2020 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.
03/28/2024 SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED.
04/03/2024 SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED.
03/28/2024 WOOD JOIST STRENGTHENING
03/28/2024 SPECIAL INSPECTION FOR STRUCTURAL MASONRY IS REQUIRED.
03/28/2024 SPECIAL INSPECTION FOR WELDING IS REQUIRED.

Outstanding Inspections

Permit Status: Complete
Permit Number: T20CM07489
Permite Description: CULTURAL KITCHEN EXPANSION
Total Outstanding Inspections - 17
Last Inspection Date Description Inspector Results Comments
10/26/2022 COT - FCON - Hood System - Final N/A Not Ready
10/26/2022 COT - LCME - Mechanical Final N/A Not Ready
10/26/2022 COT - LCBU - Stem Wall/Retaining Wall N/A Not Ready
07/28/2023 COT - LCBU - Masonry Pregrout N/A Not Applicable 7/28/23: needed preslab for building 3b booths
10/26/2022 COT - LCBU - Exterior Clips/Sheathing N/A Not Ready
10/26/2022 COT - LCBU - Roof Nailing N/A Not Ready
10/26/2022 COT - FCON - Alarm - Final N/A Not Ready
10/26/2022 COT - LCME - Kitchen Hood N/A Not Ready
10/26/2022 COT - LCPL - Sewer N/A Not Ready
10/26/2022 COT - LCEL - Temporary Service N/A Not Ready
10/26/2022 COT - LCEL - Electrical Above Ceiling N/A Not Ready
10/26/2022 COT - LCBU - Building Above Ceiling N/A Not Ready
02/21/2023 COT - LCPL - Rough Soil N/A Not Ready
10/26/2022 COT - LCPL - Gas Pressure Test N/A Not Ready
02/07/2024 COT - LCBU - Building Final N/A Partial Pass Partial pending other inspections. 2/7/2024
02/20/2024 COT - ENGR - Site - Assurance Release N/A Not Applicable no site/phone contact
02/07/2024 COT - LCBU - CofO N/A Partial Pass Partial pending other inspections. 2/7/2024

Completed Inspections

Permit Status: Complete
Permit Number: T20CM07489
Permit Description: CULTURAL KITCHEN EXPANSION
Total Completed Inspections - 39
Date Description Inspector Results Comments
06/24/2021 COT - LCEL - Grounding/Bonding Passed {Activity date: 06/24/2021; Status: Approved; Inspector: DQUINN; Comment: Entered by VLEON1 - }
12/07/2021 COT - LCPL - Plumbing Intermediate Passed {Activity date: 12/07/2021; Status: Approved; Inspector: DQUINN; Comment: Entered by RSALDAT1 - Ap
All in wall pvc and copper ok to cover.
Gas piping not ready.}
12/28/2021 COT - LCEL - Construction Power Passed {Activity date: 12/28/2021; Status: Approved; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Approved, please send ECO Clearance to TEP for the construction power

}
01/14/2022 COT - LCEL - Electrical Intermediate Passed {Activity date: 01/14/2022; Status: Approved; Inspector: DQUINN; Comment: Entered by NGARCIA3 - Ap
Ok to insulate, rock, and tape} ; {Activity date: 09/22/2021; Status: Partial Approval; Inspector: JBURGE; Comment: Entered by VVERA1 - Partial. Building #4; in wall electric. Ok to cover walls.
}
01/14/2022 COT - LCBU - Framing Passed {Activity date: 01/14/2022; Status: Approved; Inspector: DQUINN; Comment: Entered by NGARCIA3 - Ap} ; {Activity date: 09/22/2021; Status: Partial Approval; Inspector: JBURGE; Comment: Entered by VVERA1 - Partial. Building #4 framing, Ok to insulate and cover walls.}
03/11/2022 PDSD Building Division - TEP PM Clearance Passed {Activity date: 03/11/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - CODE ECO FOR NEW 400A SERVICE} ; {Activity date: 12/28/2021; Status: Approved; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - CODE ECO}
03/11/2022 COT - LCEL - Service Upgrade Passed {Activity date: 03/11/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Approved, please send ECO Clearance to TEP for the new 400A service}
08/10/2022 COT - LCBU - Preslab Passed {Activity date: 08/10/2022; Status: Approved; Inspector: DQUINN; Comment: Entered by VVERA1 - Ap
Walk-in cooler slabs ok to pour at senior center.} ; {Activity date: 06/16/2022; Status: Partial Approval; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Partial for the Fire pit area, okay for concrete placement} ; {Activity date: 09/10/2021; Status: Partial Approval; Inspector: RELEFANTE; Comment: Entered by VVERA1 - PA} ; {Activity date: 09/09/2021; Status: Cancelled; Inspector: RELEFANTE; Comment: Entered by NGARCIA3 - cancel
Contractor canceled because he won’t be ready today so he is recalling it in for tomorrow} ; {Activity date: 06/18/2021; Status: Partial Approval; Inspector: DQUINN; Comment: Entered by ESTEVEN1 - Interior slab cut for new footings and slab repour, ok to pour}
10/10/2022 COT - LCBU - Building Progress Passed {Activity date: 10/10/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by VVERA1 - Approved}
04/24/2023 COT - FCON - Hood System - Final Passed
04/25/2023 COT - LCPL - Yard Water Line Passed Inspection performed by Robert Chandler on 4.24.23.
04/25/2023 COT - LCME - Mechanical Final Passed Inspection performed by Robert Chandler on 4.24.23.
07/07/2023 COT - LCBU - Excavation/Rebar/Zoning Passed 7/7/23: 8 Canopy Column Footings for building 3B ok to pour
07/17/2023 COT - LCBU - Stem Wall/Retaining Wall Passed
07/28/2023 COT - HCBU - Preslab Passed 7/28/23: preslab for building 3b booths
09/01/2023 COT - LCBU - Exterior Clips/Sheathing Passed Ok to cover exterior walls.
09/01/2023 COT - LCBU - Roof Nailing Passed Ok to dry-in roof system.
09/21/2023 COT - HCBU - Masonry Pregrout Passed Caisson footings for solar columns and 4’ stem wall footings. Ok to place concrete in progress areas.
12/06/2023 COT - FCON - Alarm - Final Passed
12/06/2023 COT - LCME - Kitchen Hood Passed
12/06/2023 COT - LCPL - Plumbing Final Passed
12/06/2023 COT - LCEL - Electrical Final Passed
12/06/2023 COT - LCME - Mechanical Intermediate Passed Mechanical intermediate to include Mechanical Final - complete.
12/06/2023 COT - LCPL - Sewer Passed
12/06/2023 COT - FCON - Fire - Final Passed
02/07/2024 COT - LCEL - Outdoor Lighting Passed
02/20/2024 BULD - Electrical Clearance Passed
02/20/2024 COT - BULD - SWG Clearance Passed
02/20/2024 COT - LCEL - Temporary Service Passed
02/20/2024 COT - LCEL - Electrical Above Ceiling Passed
02/20/2024 COT - LCBU - Building Above Ceiling Passed
02/20/2024 COT - LCPL - Rough Soil Passed
02/20/2024 COT - LCPL - Gas Pressure Test Passed
02/20/2024 COT - LCBU - Building Final Passed
02/20/2024 COT - LCEL - Electrical Underground Passed
02/20/2024 COT - FCON - Sprinkler - Final Passed
02/26/2024 ENGR Engineering Final Passed
02/26/2024 COT - ENGR - Site - Assurance Release Passed
02/26/2024 COT - LCBU - CofO Passed

Documents

File Name Document Type  
JOB CARD 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
PERMIT 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
PLAN SET 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
COFO_FINALCOFO_COMMERCIAL.PDF DOCUMENTS VIEW
SI CERTIFICATE CULTURAL KITCHEN-2024-03-28_V1.PDF DOCUMENTS VIEW
COFO_FINALCOFO_COMMERCIAL.PDF DOCUMENTS VIEW
PYT OLD PASCUA COMMUNITY KITCHEN - SENIOR CNTR. - KH-2 CONTAINMENT TEST_V2.PDF DOCUMENTS VIEW
JOB CARD.PDF DOCUMENTS VIEW
PERMIT.PDF DOCUMENTS VIEW
PLAN SET.PDF DOCUMENTS VIEW
REV1_PLAN SET.PDF CONSTRPLANS VIEW
REV2_PLAN SET.PDF CONSTRPLANS VIEW
REV2_REVISION LETTER.PDF DOCUMENTS VIEW
REV2_STRUCTURAL CALCS.PDF DOCUMENTS VIEW
REV3_STRUCTURAL CALCS.PDF DOCUMENTS VIEW
REV3_REVISION NARRATIVE.PDF DOCUMENTS VIEW
REV3_PLAN SET.PDF CONSTRPLANS VIEW
PERMIT.PDF DOCUMENTS VIEW
APPLICATION.PDF DOCUMENTS VIEW
JOB CARD.PDF DOCUMENTS VIEW
SPECIAL INSPECTION CERT.PDF DOCUMENTS VIEW
STRUCTURAL CALCS.PDF DOCUMENTS VIEW
PLAN SET.PDF CONSTRPLANS VIEW