Permit: T20CM06438
Permit Details
Apply Date:
09/18/2020
Applicant:
Description:
3 STORY MIXED USE
Permit Reviews
Permit Number - T20CM06438
Permit Status: Complete
Permit Description: 3 STORY MIXED USE
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
09/18/2020 | COMMERCIAL - NEW | 10/26/2020 | COMPLETED |
10/26/2020 | 3RD PARTY REVIEW - COMMERCIAL | 12/17/2020 | COMPLETED |
12/07/2021 | REVISION - - 1ST | 12/22/2021 | COMPLETED |
12/27/2021 | REVISION - - 2ND | 02/18/2022 | COMPLETED |
10/26/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 10/31/2023 | APPROVED |
11/02/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 11/02/2023 | APPROVED |
Outstanding Activity Conditions
Permit Number - T20CM06438
Permit Status: Complete
Permit Description: 3 STORY MIXED USE
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
10/31/2023 | AIR BALANCING/COMMISSIONING REPORT IS REQUIRED. |
Conditions
Permit Number - T20CM06438
Permit Status: Complete
Permit Description: 3 STORY MIXED USE
Date | Description | Comments |
---|---|---|
09/18/2020 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. | |
10/29/2020 | SPECIAL INSPECTION FOR CONCRETE IS REQUIRED.. | |
10/29/2020 | SPECIAL INSPECTION FOR STRUCTURAL MASONRY IS REQUIRED. | |
10/29/2020 | SPECIAL INSPECTION FOR SITE PREPARATION IS REQUIRED. | |
10/29/2020 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. | |
09/21/2020 | SPECIAL INSPECTION REQUIRED FOR OUTDOOR LIGHTING. | |
10/29/2020 | SPECIAL INSPECTION FOR STEEL FABRICATORS IS REQUIRED | |
10/29/2020 | SPECIAL INSPECTION FOR STRUCTURAL STEEL IS REQUIRED | |
10/29/2020 | SPECIAL INSPECTION FOR COLD FORMED STEEL FRAMING IS REQUIRED | |
10/31/2023 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. | |
10/31/2023 | WATER STERILIZATION REPORT IS REQUIRED. |
Outstanding Inspections
Permit Status: Complete
Permit Number: T20CM06438
Permite Description: 3 STORY MIXED USE
Total Outstanding Inspections - 16
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/26/2022 | COT - LCPL - Gas Pressure Test | N/A | Not Ready | |
10/26/2022 | COT - LCME - Mechanical Progress | N/A | Not Ready | |
10/26/2022 | COT - LCEL - Electrical Underground | N/A | Not Ready | |
10/26/2022 | COT - LCBU - Preslab | N/A | Not Ready | |
10/26/2022 | COT - HCBU - Interior Shear Bracing | N/A | Not Ready | |
10/26/2022 | COT - LCBU - Excavation/Rebar/Zoning | N/A | Not Ready | |
10/26/2022 | COT - LCBU - Roof Nailing | N/A | Not Ready | |
10/27/2022 | COT - LCBU - Framing | N/A | Not Ready | |
10/26/2022 | COT - LCEL - Electrical Intermediate | N/A | Not Ready | |
10/26/2022 | COT - LCEL - Construction Power | N/A | Not Ready | |
10/26/2022 | COT - LCPL - Rough Soil | N/A | Not Ready | |
10/26/2022 | COT - LCME - Kitchen Hood | N/A | Not Ready | |
02/07/2023 | COT - LCPL - Plumbing Intermediate | N/A | Partial Pass | Level #3, room #310; domestic water lines are in place. NOTE: address is incorrect; should read 1747 S. 6th Avenue: not 1747 N. 6th Avenue. |
10/26/2022 | COT - LCPL - Sewer | N/A | Not Ready | |
10/03/2023 | COT - FCON - Alarm - Final | N/A | Partial Pass | Tested all the following items and passed -General Alarm smokes not related to elevator operation -Pull Stations -Water Flows and Tampers -All notification Items needed to address -Add strobe in ADA restroom of Room 201 -Test supervisory smoke signals to the 14 resident suites on floors 2 and 3 |
10/03/2023 | COT - FCON - Fire - Final | N/A | Partial Pass | Need to address Fire Alarm issues. Need Final Elevator inspection report. |
Completed Inspections
Permit Status: Complete
Permit Number: T20CM06438
Permit Description: 3 STORY MIXED USE
Total Completed Inspections - 44
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
03/23/2021 | COT - LCEL - Grounding/Bonding | Passed | {Activity date: 03/23/2021; Status: Approved; Inspector: JBURGE; Comment: Entered by RSALDAT1 - Approved. Ok to cover ufer.} | |
06/07/2022 | PDSD Building Division - TEP PM Clearance | Passed | {Activity date: 06/07/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by NGARCIA3 - CODE TMPP} | |
08/17/2022 | COT - LCPL - Plumbing Roof Drains | Passed | {Activity date: 08/17/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by NGARCIA3 - Approved. Primary and secondary rain water leaders from roof to 1st floor. Under hydro test. Need to drain lines; inclement weather predicted. Needed to drain roof if heavy rains become a problem.} ; {Activity date: 06/15/2021; Status: Partial Approval; Inspector: JBURGE; Comment: Entered by VLEON1 - Partial. Roof drain leader lines at 4”-6”. Ok to cover progress areas.} | |
08/17/2022 | COT - LCPL - Plumbing Above Ceiling | Passed | {Activity date: 08/17/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by NGARCIA3 - Partial. Level #1; waste and vent lines (2"- 4"). Lines are under hydro test.} | |
08/24/2022 | COT - LCPL - Yard Water Line | Passed | {Activity date: 08/24/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by VVERA1 - Approved. Domestic water line under hydro test (approximately 120 psi). Back flow valve needs to be certified by 2nd party inspection. } |
|
11/14/2022 | COT - LCPL - Gas Pressure Test | Passed | Approved- 14 units (210-270) and (310-370) on the 2nd and 3rd levels | |
11/16/2022 | COT - LCME - Mechanical Intermediate | Passed | ||
11/16/2022 | COT - LCME - Mechanical Progress | Passed | ||
11/16/2022 | COT - LCME - Mechanical Above Ceiling | Passed | ||
06/08/2023 | COT - LCEL - Electrical Underground | Passed | ||
09/14/2023 | COT - LCBU - Preslab | Passed | ||
09/14/2023 | COT - HCBU - Interior Shear Bracing | Passed | ||
09/14/2023 | COT - LCBU - Excavation/Rebar/Zoning | Passed | ||
09/14/2023 | COT - LCBU - Roof Nailing | Passed | ||
09/14/2023 | COT - LCBU - Framing | Passed | ||
09/14/2023 | COT - LCEL - Electrical Intermediate | Passed | ||
09/14/2023 | COT - LCEL - Construction Power | Passed | ||
09/14/2023 | COT - LCPL - Rough Soil | Passed | ||
09/14/2023 | COT - LCME - Kitchen Hood | Passed | ||
11/01/2023 | COT - FCON - Underground Pressure | Passed | completed on 11/21/2021 by Kazal Fire | |
09/14/2023 | COT - LCPL - Plumbing Intermediate | Passed | ||
09/14/2023 | COT - LCPL - Sewer | Passed | ||
09/14/2023 | COT - LCBU - Firewall/Fire Barrier/Firestop | Passed | ||
09/14/2023 | COT - LCPL - Plumbing Final | Passed | ||
09/14/2023 | COT - LCEL - Electrical Progress | Passed | ||
09/14/2023 | COT - LCME - Mechanical Final | Passed | ||
11/01/2023 | COT - FCON - Underground Flush | Passed | completed on 11/21/2021 by Kazal Fire | |
09/14/2023 | COT - LCBU - Building Above Ceiling | Passed | ||
09/14/2023 | COT - LCBU - Building Progress | Passed | ||
09/14/2023 | COT - LCEL - Electrical Above Ceiling | Passed | ||
09/14/2023 | COT - LCEL - Outdoor Lighting | Passed | ||
09/14/2023 | COT - LCEL - Temporary Service | Passed | ||
09/14/2023 | COT - LCPL - Plumbing Progress | Passed | ||
09/14/2023 | FCON – OH Piping & Hydro | Passed | ||
09/14/2023 | PDSD Building Division - Sign Final | Passed | ||
09/26/2023 | TRSP - ROW - Final/Close-Out | Passed | All work completed | |
10/02/2023 | COT - FCON - Sprinkler - Final | Passed | ||
10/04/2023 | COT - LCBU - Building Final | Passed | Pending state elevator inspection. | |
10/04/2023 | COT - LCEL - Electrical Final | Passed | ||
10/04/2023 | COT - FCON - Alarm - Final | Passed | ||
10/19/2023 | PDSD Site/Engineering Division - NPPO | Passed | ||
10/19/2023 | PDSD Site/Engineering Division - Landscaping | Passed | ||
10/24/2023 | ENGR Engineering Final | Passed | ||
10/30/2023 | COT - FCON - Fire - Final | Passed |