Permit: T20CM06438

Parcel: 11707226B


Addresses:

747 S 6TH AV

Inspection Status: Not Ready

Inspection History: COT - LCBU - Excavation/Rebar/Zoning 

Date Description Inspector Results Comments
10/26/2022 COT - LCBU - Excavation/Rebar/Zoning  Not Ready
06/28/2022 COT - LCBU - Excavation/Rebar/Zoning  JBURGE Partial Approval Entered by NGARCIA3 - Partial. East stairwell and elevator shaft. Ok to set forms and place concrete.
06/23/2022 COT - LCBU - Excavation/Rebar/Zoning  JBURGE Partial Approval Entered by NGARCIA3 - Partial. Level #4 Northwest stairwell and West/ South 17" curb. Ok to place concrete in curb areas; OK to frame exterior of Northwest stairwell and place,concrete in progress areas.
05/16/2022 COT - LCBU - Excavation/Rebar/Zoning  JBURGE Partial Approval Entered by VVERA1 - Partial. Level #3 slab: Post Tension Cable System. Cables and rebar in place; Ok to place concrete.
03/14/2022 COT - LCBU - Excavation/Rebar/Zoning  JBURGE Partial Approval Entered by NGARCIA3 - Partial. Northwest stairs at Level #4; Ok to set forms and place concrete.
03/03/2022 COT - LCBU - Excavation/Rebar/Zoning  JBURGE Partial Approval Entered by NGARCIA3 - Partial. Level #3; 15 rebar columns, Ok to set forms and place concrete in progress areas.
02/14/2022 COT - LCBU - Excavation/Rebar/Zoning  JBURGE Partial Approval Entered by VVERA1 - Partial. Level #3, Post Tension Cable System. Ok to place concrete in progress areas.
01/20/2022 COT - LCBU - Excavation/Rebar/Zoning  JBURGE Partial Approval Entered by RSALDAT1 - Partial. Level #3; Northwest stairwell. Ok to set forms and place concrete.
01/19/2022 COT - LCBU - Excavation/Rebar/Zoning  JBURGE Partial Approval Entered by NGARCIA3 - Partial. Level #3; Southeast stairwell/elevator. Rebar in place, Ok to set forms and place concrete in progress areas.
01/11/2022 COT - LCBU - Excavation/Rebar/Zoning  JBURGE Partial Approval Entered by VVERA1 - Partial. Level #2 to #3; 16 columns at 10’6”above floor level. Ok to place forms and place concrete.
12/21/2021 COT - LCBU - Excavation/Rebar/Zoning  JBURGE Partial Approval Entered by RSALDAT1 - Partial. Level #2, Post Tension Cable System at GL: A-G/1-4. Ok to place concrete in progress areas.
11/23/2021 COT - LCBU - Excavation/Rebar/Zoning  JBURGE Partial Approval Entered by VVERA1 - Partial. West stairwell #201. Rebar and forms are in place. Ok to place concrete.
11/09/2021 COT - LCBU - Excavation/Rebar/Zoning  JBURGE Partial Approval Entered by RSALDAT1 - Partial. Stairwell #2 at 13’8”. Ok to place concrete in progress areas. 16 each concrete columns. Ok to set forms and place concrete in progress areas.
10/26/2021 COT - LCBU - Excavation/Rebar/Zoning  JBURGE Partial Approval Entered by RSALDAT1 - Partial. Level #2 rebar on slab (10”-12”) slab at GL: A-E.5/2-2.75; 2.5-4/A-E.5. Ok to place concrete in progress areas.
09/27/2021 COT - LCBU - Excavation/Rebar/Zoning  JBURGE Partial Approval Entered by NGARCIA3 - . Partial. Level #1; East slab at GL: 2-4/D-G with 10” slab.
08/11/2021 COT - LCBU - Excavation/Rebar/Zoning  DQUINN Partial Approval Entered by RSALDAT1 - Partial. Reinforcing wall at GL:1/D-E.5. Ok to set forms and place concrete in progress area.
08/04/2021 COT - LCBU - Excavation/Rebar/Zoning  JBURGE Partial Approval Entered by RSALDAT1 - Partial. Northwest corner of slab area at GL: 1-2/A-B. 0k to place concrete in progress areas. Slab in fill at GL: C/1-4.
08/02/2021 COT - LCBU - Excavation/Rebar/Zoning  JBURGE Partial Approval Entered by RSALDAT1 - Partial. East garage slab (01015) at GL: 1-4/B-D. Ok to place concrete in progress areas.
07/30/2021 COT - LCBU - Excavation/Rebar/Zoning  JBURGE Partial Approval Entered by RSALDAT1 - Partial. North wall footing at GL: 1/D-E.5. Ok to place concrete in progress areas.
07/29/2021 COT - LCBU - Excavation/Rebar/Zoning  JBURGE Not ready for Inspection Entered by RSALDAT1 - Not ready. Inspection should read 01015
07/21/2021 COT - LCBU - Excavation/Rebar/Zoning  JBURGE Not ready for Inspection Entered by RSALDAT1 - Not ready; slab area flooded.
07/20/2021 COT - LCBU - Excavation/Rebar/Zoning  JBURGE Partial Approval Entered by RSALDAT1 - Partial. Building pre-slab at parking garage Level #1; interior edge of approximately 4’ of perimeter on GL; 4/B-D; 4/E-G; E.5-F/2. Ok to place concrete in progress areas.
07/19/2021 COT - LCBU - Excavation/Rebar/Zoning  JBURGE Partial Approval Entered by RSALDAT1 - Partial. Pre-slab in parking garage at GL: 2.5-4/A-B. Ok to place concrete in progress areas.
07/13/2021 COT - LCBU - Excavation/Rebar/Zoning  JBURGE Not ready for Inspection Entered by RSALDAT1 - Not ready. Parking garage area flooded.
07/08/2021 COT - LCBU - Excavation/Rebar/Zoning  JBURGE Not ready for Inspection Entered by RSALDAT1 - Not ready. Contractor cancelled, materials did not arrive. Will reschedule for 8 July.
06/02/2021 COT - LCBU - Excavation/Rebar/Zoning  JBURGE Partial Approval Entered by VLEON1 - Partial. Retaining wall on GL: 1/A-C.5. Ok to set forms and place concrete in progress areas.
05/26/2021 COT - LCBU - Excavation/Rebar/Zoning  JBURGE Partial Approval Entered by VLEON1 - Partial. Retaining walls on GL: A/1-3.5; 1/A.25. Ok to set forms and place concrete in progress areas.
05/19/2021 COT - LCBU - Excavation/Rebar/Zoning  JBURGE Partial Approval Entered by VLEON1 - Partial. Retaining walls on GL: 2/F-G, G/2-2.75; 2/D.25-C. Ok to place grout in progress areas.
05/10/2021 COT - LCBU - Excavation/Rebar/Zoning  JBURGE Partial Approval Entered by VLEON1 - Partial. Retaining wall on GL: 2/C-E. Ok to set forms and place concrete in progress areas.
04/26/2021 COT - LCBU - Excavation/Rebar/Zoning  JBURGE Partial Approval Entered by VLEON1 - Partial. Retaining walls and stairwell walls at GL: 4/A-B.25; A/4-4.75; G/3.25-4; F.5-G/2.75-4; A-B/2-2.25. Ok to set forms and place concrete in progress
04/20/2021 COT - LCBU - Excavation/Rebar/Zoning  JBURGE Partial Approval Entered by VLEON1 - Partial. Concrete wall at 12’8” at GL: 4/B.25-D.25. Ok to place concrete in progress areas
04/16/2021 COT - LCBU - Excavation/Rebar/Zoning  ESTEVENS Partial Approval Entered by VLEON1 - PARTIAL F1 FOOTINGS BETWEEN COLUMNS C & D
04/13/2021 COT - LCBU - Excavation/Rebar/Zoning  JBURGE Partial Approval Entered by VLEON1 - Partial. Vertical poured in place walls at GL: 4/D-F (W3) at 10”. Elevator sump wall at GL: F.5/3.75 as per detail #105. Ok to place concrete in progress areas.
04/06/2021 COT - LCBU - Excavation/Rebar/Zoning  JBURGE Not ready for Inspection Entered by VLEON1 - NOT READY WILL RESCHEDULE FOR 7 APRIL
03/30/2021 COT - LCBU - Excavation/Rebar/Zoning  JBURGE Partial Approval Entered by VLEON1 -
03/23/2021 COT - LCBU - Excavation/Rebar/Zoning  JBURGE Partial Approval Entered by RSALDAT1 - Partial. Column footings and wall footings (F5; F6) at GL: D.5-G/2-2.75. Ok to place concrete in progress areas.
03/12/2021 COT - LCBU - Excavation/Rebar/Zoning  JBURGE Partial Approval Entered by VLEON1 - Partial. Wall footings ; F1; F2; F3: column footings CC2; CC3. Ok to place concrete in progress areas.
03/08/2021 COT - LCBU - Excavation/Rebar/Zoning  DQUINN Partial Approval Entered by VLEON1 - PARTIAL SOUTH WALL OK TO POUR
03/01/2021 COT - LCBU - Excavation/Rebar/Zoning  DQUINN Partial Approval Entered by VLEON1 - PARTIAL - Elevator/stairwell double mat and verts ok to pour. This footing contains the sump pit. Future adjacent footing will contain ufers.
05/18/2023 COT - LCBU - Excavation/Rebar/Zoning  Partial Pass Footings for trash enclosure. Ok to place concrete in progress areas
06/09/2023 COT - LCBU - Excavation/Rebar/Zoning  Partial Pass Footings and CMU walls for trash enclosure. NOTE: Check distance of light pole in trash enclosure to relationship of light pole north of trash enclosure. Is trash enclosure light pole too close to building?
06/20/2023 COT - LCBU - Excavation/Rebar/Zoning  Partial Pass Trash enclosure and apron area. Ok to,place concrete in progress areas.
09/14/2023 COT - LCBU - Excavation/Rebar/Zoning  Passed