Permit: T19CM03731
Permit Details
Status:
Final
Type:
COMMERCIAL ALTERATION
Address:
2430 N HUACHUCA DR
Address NEW:
2430 N HUACHUCA DR
Apply Date:
05/24/2019
Applicant:
N/A
Description:
TI: OFFICE & MEETING SPACE
Contractors:
- CORE CONSTRUCTION SERVICES OF AZ ***APA***
Permit Reviews
Permit Number - T19CM03731
Permit Status: Final
Permit Description: TI: OFFICE & MEETING SPACE
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 05/20/2020 | REVISION - - 1ST | 06/15/2020 | COMPLETED |
| 05/24/2019 | PLANS OK TO SUBMIT - COMM | 05/28/2019 | COMPLETED |
| 06/04/2019 | COMMERCIAL - TI | 07/18/2019 | COMPLETED |
| 06/15/2020 | REVISION - - 1ST | 07/01/2020 | COMPLETED |
| 07/19/2019 | RESUBMITTAL | 07/26/2019 | COMPLETED |
| 07/26/2019 | RESUBMITTAL | 07/30/2019 | COMPLETED |
| 07/30/2019 | RESUBMITTAL | 08/02/2019 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T19CM03731
Permit Status: Final
Permit Description: TI: OFFICE & MEETING SPACE
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 05/24/2019 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T19CM03731
Permit Description: TI: OFFICE & MEETING SPACE
Total Completed Inspections - 21
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/18/2019 | MECHANICAL - FINAL | RSHERRY | Approved | AIR BALANCE REPORT REQUIRED |
| 07/30/2019 | PLUMBING - FINAL | RSHERRY | Approved | WATER DISINFECTION REPORT REQUIRED |
| 10/24/2019 | PLUMBING - ROUGH, SOIL | ESTEVENS | Approved | |
| 12/10/2019 | ELECTRIC - SERVICE UPGRADE | ESTEVENS | Approved | Not complete. |
| 12/20/2019 | FRAMING | TVALENCIA | Approved | |
| 12/30/2019 | ELECTRIC - INTERMEDIATE | ESTEVENS | Approved | |
| 12/31/2019 | PLUMBING - INTERMEDIATE | ESTEVENS | Approved | Missing nail plates in changing area, copper pipe touching aluminum stud in restroom. |
| 01/10/2020 | SHEET ROCK NAILING | DQUINN | Approved | |
| 03/13/2020 | FIREWALL/FIREBARRIER/FIRESTOP | ESTEVENS | Approved | |
| 03/13/2020 | BUILDING - PROGRESS | ESTEVENS | Approved | |
| 05/11/2020 | ELECTRIC - FINAL | ESTEVENS | Approved | RVI |
| 05/11/2020 | TEP CLEARANCE - PM | ESTEVENS | Approved | CODE INCR |
| 05/29/2020 | MECHANICAL - INTERMEDIATE | ESTEVENS | Approved | |
| 05/29/2020 | EXCAVATION/LAYOUT REBAR & ZON | ESTEVENS | Approved | |
| 06/02/2020 | GAS CLEARANCE | ESTEVENS | Approved | CODE |
| 06/02/2020 | PLUMBING - GAS PRESSURE TEST | ESTEVENS | Approved | |
| 06/02/2020 | BUILDING ABOVE CEILING | ESTEVENS | Approved | |
| 06/02/2020 | ENGINEERING - FINAL | BBENEDON | Approved | |
| 09/23/2020 | FIRE - FINAL | DQUINN | Approved | 9025 |
| 09/23/2020 | BUILDING - FINAL | DQUINN | Approved | 9025 |
| 09/23/2020 | CERTIFICATE OF OCCUPANCY | DQUINN | Approved | Ap Ok for c of o Close permit when all entities are Ap |