Permit Details

Status:
C of o
Type:
COMMERCIAL ADDITION
Address:
1545 E COPPER ST
Address NEW:
1545 E COPPER ST
Apply Date:
12/17/2018
Applicant:
N/A
Description:
SCHOOL
Architects:
  • FRANKS, MICHAEL WILLIAM
Contractors:
  • DIVERSIFIED DESIGN AND CONSTRUCT

Permit Reviews

Permit Number - T18CM09798
Permit Status: C of o
Permit Description: SCHOOL
Start Date Submittal Complete Date Status  
01/25/2019 POST 3RD PARTY REVIEW 02/05/2019 COMPLETED Review Details
02/05/2019 POST 3RD PARTY REVIEW 02/07/2019 COMPLETED Review Details
04/26/2019 3RD PARTY REVIEW - REVISION/OTHER 05/07/2019 COMPLETED Review Details
10/02/2019 3RD PARTY REVIEW - REVISION/OTHER-2ND 11/20/2019 COMPLETED Review Details
12/17/2018 PLANS OK TO SUBMIT - COMM 12/19/2018 COMPLETED Review Details
12/19/2018 3RD PARTY REVIEW - COMMERCIAL TI 01/25/2019 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T18CM09798
Permit Status: C of o
Permit Description: SCHOOL
Total Outstanding Activity Conditions - 1
Date Name
12/17/2018 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: C of o
Permit Number: T18CM09798
Permit Description: SCHOOL
Total Completed Inspections - 45
Date Description Inspector Results Comments
07/12/2019 STEM WALL/RETAINING WALL GWEST Approved
07/22/2019 PLUMBING - YARD WTR LINE/TEST RCHANDLER Approved
09/06/2019 PLUMBING - INTERMEDIATE DQUINN Approved East side theater roof drains ok to back fill to south of e to w footing for south theater wall.
Rooms 152 153 rough ok to backfill.
Costume storage room interior roof drains ok to cover.
09/11/2019 EXCAVATION/LAYOUT REBAR & ZON RCHANDLER Approved
09/13/2019 PLUMBING - ROUGH, SOIL JBURGE Approved These inspections were performed by Dan Quinn on 9/12/19.
09/13/2019 PLUMBING - PRE SLAB JBURGE Approved These inspections were performed by Dan Quinn on 9/12/19.
09/13/2019 ELECTRIC - INTERMEDIATE JBURGE Approved These inspections were performed by Dan Quinn on 9/12/19.
09/23/2019 BUILDING PRE-SLAB DQUINN Approved Slab south of old theater ok to pour.
10/02/2019 MECHANICAL - INTERMEDIATE JCLAXTON Approved Intake exhaust for the underground water tank.
10/02/2019 ELECTRIC - UNDERGROUND JCLAXTON Approved Electric underground at north east patio.
10/17/2019 REINFORCED MASONRY PRE-GROUT RCHANDLER Approved
10/28/2019 SHEET ROCK NAILING ESTEVENS Approved Canceled by contractor.
11/08/2019 FRAMING DQUINN Approved North, east and southeast walls of arts center ok
12/05/2019 ROOF NAILING JCLAXTON Approved Ok to proceed
12/11/2019 EXT METAL CLIPS/EXT SHEATHING ESTEVENS Approved Densglass and foam insulation on southwest corner
12/23/2019 PLUMBING - GAS PRESSURE TEST ESTEVENS Approved Testing of new shut off valve.
02/14/2020 GAS CLEARANCE DQUINN Approved Clear gas
08/14/2020 CERTIFICATE OF OCCUPANCY TTREMBULAK Approved Partial. Rooms 158 & 133 only.
09/02/2020 SITE - SEWER DMUNIZ Approved Not Applicable.
09/02/2020 PLUMBING - SEWER HCS CONNECT DMUNIZ Approved Not Applicable.
09/02/2020 PLUMBING - GAS PRESS TEST FNL DMUNIZ Approved Not Applicable.
09/02/2020 PLUMBING - MD GAS/PRECONST MTG DMUNIZ Approved Not Applicable.
09/02/2020 ELECTRIC - UFER DMUNIZ Approved Approved
09/02/2020 U VALUE FOR WINDOW DMUNIZ Approved Approved
09/02/2020 MECHANICAL - ABOVE CEILING DMUNIZ Approved Approved
09/02/2020 ELECTRIC - ABOVE CEILING DMUNIZ Approved Approved
09/02/2020 PLUMBING - ABOVE CEILING DMUNIZ Approved Approved
09/02/2020 PLUMBING - ROOF DRAINS DMUNIZ Approved Approved
09/02/2020 FIREWALL/FIREBARRIER/FIRESTOP DMUNIZ Approved Approved
09/02/2020 BUILDING ABOVE CEILING DMUNIZ Approved Approved
12/04/2020 NPPO - FINAL BBENEDON Approved
12/04/2020 LANDSCAPE - FINAL BBENEDON Approved
12/07/2020 STUCCO MESH TTREMBULAK Approved APPROVED, work was completed and finished.
12/08/2020 OUTDOOR LIGHTING FINAL DQUINN Approved Ap
12/08/2020 ELECTRIC - FINAL DQUINN Approved Ap
12/08/2020 ELECTRIC - OUTDOOR LIGHTING DQUINN Approved Ap
12/09/2020 MECHANICAL - FINAL ESTEVENS Approved Partial. Pending air balance report.
12/10/2020 RIGHT OF WAY - FINAL DR Approved Work in ROW completed without DTM Permit.
12/11/2020 ENGINEERING - FINAL BBENEDON Approved
12/17/2020 SIGN - FINAL BBENEDON Approved Approved
12/21/2020 PLUMBING - FINAL DQUINN Approved Ap
12/22/2020 FIRE - FINAL jfordney Approved Knox boxes and gate keys
Address identification
12/22/2020 FIRE - ALARM FINAL jfordney Approved Duct smoke in ballet room not functioning
Duct smoke in music rom office mislabled
Duct smoke in prop storage room not functioning
12/22/2020 FIRE SPKLR - FINAL jfordney Approved
03/22/2021 BUILDING - FINAL DQUINN Approved SPECIAL INSPECTION COMPLETED