Inspection History Details
Inspection Status: Approved
Inspection History: PLUMBING - INTERMEDIATE
Permit Number - T18CM09798
Inspection Description - PLUMBING - INTERMEDIATE
Inspection Status - Approved
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/02/2020 | PLUMBING - INTERMEDIATE | Approved | Approved | |
| 07/27/2020 | PLUMBING - INTERMEDIATE | Partial Approval | Partial. Plumbing extensions in restrooms 102, 103, 104, &105. | |
| 01/22/2020 | PLUMBING - INTERMEDIATE | Partial Approval | Rooms 152 and 153 are complete(restrooms). | |
| 01/16/2020 | PLUMBING - INTERMEDIATE | Partial Approval | Dwv and potable ok to cover in east half of arts center | |
| 09/06/2019 | PLUMBING - INTERMEDIATE | Partial Approval | East side theater roof drains ok to back fill to south of e to w footing for south theater wall. Rooms 152 153 rough ok to backfill. Costume storage room interior roof drains ok to cover. |
|
| 08/19/2019 | PLUMBING - INTERMEDIATE | Partial Approval | All above inspections pertain to all framed walls in concession area, the electric and plumbing in same, supply and return plenums. All ok to rock and tape. South gym entry lobby- east framed wall and outlet ok to rock and tape. |
|
| 07/22/2019 | PLUMBING - INTERMEDIATE | Not ready for Inspection | Work incomplete at this time. | |
| 07/19/2019 | PLUMBING - INTERMEDIATE | Not ready for Inspection | not complete | |
| 06/25/2019 | PLUMBING - INTERMEDIATE | Not ready for Inspection | Not complete. |