Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO.
If you cannot find what you are looking for please
submit a records request.
Inspection Status: Approved
Inspection History: SHEET ROCK NAILING
| Date |
Description |
Inspector |
Results |
Comments |
| 03/05/2020 |
SHEET ROCK NAILING |
|
Approved |
|
| 02/26/2020 |
SHEET ROCK NAILING |
|
Partial Approval |
Rooms. 112, 102, 103, 104, 105, 107. 133, 134. |
| 02/07/2020 |
SHEET ROCK NAILING |
|
Partial Approval |
Top 4’ around center of the arts and band room section. |
| 02/04/2020 |
SHEET ROCK NAILING |
|
Partial Approval |
Atrium in center for the arts section. Theater offices. |
| 01/28/2020 |
SHEET ROCK NAILING |
|
Partial Approval |
Ok to drywall from 8' and above in rooms 138, 137 and 136. |
| 10/28/2019 |
SHEET ROCK NAILING |
|
Cancelled |
Canceled by contractor. |
| 09/18/2019 |
SHEET ROCK NAILING |
|
Partial Approval |
South costume room firewall ok to cover. |