Inspection Status: Approved
Inspection History: REINFORCED MASONRY PRE-GROUT
| Date |
Description |
Inspector |
Results |
Comments |
| 10/17/2019 |
REINFORCED MASONRY PRE-GROUT |
|
Approved |
|
| 10/16/2019 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
South column to 26’. |
| 10/15/2019 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
Inspector missed message requesting an early morning inspection. CMU walls grouted at 22’-26’. Inspection covers by Special Inspector from Terracon. |
| 10/14/2019 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
Ok to grout south column to 20’ |
| 10/09/2019 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
Ok to grout last column lift for south column inside gate |
| 10/08/2019 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
Top out North column and 1st lift for South Column. |
| 09/12/2019 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
2 north columns and 1 east column ok to grout to top. |
| 09/11/2019 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
Top out for three North columns. |
| 09/09/2019 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
Ok to grout 20’ lift on 2 north and 1 east column |
| 09/04/2019 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
2 north and 1 east column, 3rd lift. 12’ to 16’. |
| 08/23/2019 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
2 north and 1 east column ok to grout 2nd lift |
| 08/21/2019 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
North entrance columns and east entrance. |