Permit: T18CM09798
Permit Details
Apply Date:
12/17/2018
Applicant:
N/A
Description:
SCHOOL
Architects:
- FRANKS, MICHAEL WILLIAM
Contractors:
- DIVERSIFIED DESIGN AND CONSTRUCT
Permit Reviews
Permit Number - T18CM09798
Permit Status: C of o
Permit Description: SCHOOL
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/25/2019 | POST 3RD PARTY REVIEW | 02/05/2019 | COMPLETED |
| 02/05/2019 | POST 3RD PARTY REVIEW | 02/07/2019 | COMPLETED |
| 04/26/2019 | 3RD PARTY REVIEW - REVISION/OTHER | 05/07/2019 | COMPLETED |
| 10/02/2019 | 3RD PARTY REVIEW - REVISION/OTHER-2ND | 11/20/2019 | COMPLETED |
| 12/17/2018 | PLANS OK TO SUBMIT - COMM | 12/19/2018 | COMPLETED |
| 12/19/2018 | 3RD PARTY REVIEW - COMMERCIAL TI | 01/25/2019 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T18CM09798
Permit Status: C of o
Permit Description: SCHOOL
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 12/17/2018 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T18CM09798
Permit Description: SCHOOL
Total Completed Inspections - 45
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/12/2019 | STEM WALL/RETAINING WALL | GWEST | Approved | |
| 07/22/2019 | PLUMBING - YARD WTR LINE/TEST | RCHANDLER | Approved | |
| 09/06/2019 | PLUMBING - INTERMEDIATE | DQUINN | Approved | East side theater roof drains ok to back fill to south of e to w footing for south theater wall. Rooms 152 153 rough ok to backfill. Costume storage room interior roof drains ok to cover. |
| 09/11/2019 | EXCAVATION/LAYOUT REBAR & ZON | RCHANDLER | Approved | |
| 09/13/2019 | PLUMBING - ROUGH, SOIL | JBURGE | Approved | These inspections were performed by Dan Quinn on 9/12/19. |
| 09/13/2019 | PLUMBING - PRE SLAB | JBURGE | Approved | These inspections were performed by Dan Quinn on 9/12/19. |
| 09/13/2019 | ELECTRIC - INTERMEDIATE | JBURGE | Approved | These inspections were performed by Dan Quinn on 9/12/19. |
| 09/23/2019 | BUILDING PRE-SLAB | DQUINN | Approved | Slab south of old theater ok to pour. |
| 10/02/2019 | MECHANICAL - INTERMEDIATE | JCLAXTON | Approved | Intake exhaust for the underground water tank. |
| 10/02/2019 | ELECTRIC - UNDERGROUND | JCLAXTON | Approved | Electric underground at north east patio. |
| 10/17/2019 | REINFORCED MASONRY PRE-GROUT | RCHANDLER | Approved | |
| 10/28/2019 | SHEET ROCK NAILING | ESTEVENS | Approved | Canceled by contractor. |
| 11/08/2019 | FRAMING | DQUINN | Approved | North, east and southeast walls of arts center ok |
| 12/05/2019 | ROOF NAILING | JCLAXTON | Approved | Ok to proceed |
| 12/11/2019 | EXT METAL CLIPS/EXT SHEATHING | ESTEVENS | Approved | Densglass and foam insulation on southwest corner |
| 12/23/2019 | PLUMBING - GAS PRESSURE TEST | ESTEVENS | Approved | Testing of new shut off valve. |
| 02/14/2020 | GAS CLEARANCE | DQUINN | Approved | Clear gas |
| 08/14/2020 | CERTIFICATE OF OCCUPANCY | TTREMBULAK | Approved | Partial. Rooms 158 & 133 only. |
| 09/02/2020 | SITE - SEWER | DMUNIZ | Approved | Not Applicable. |
| 09/02/2020 | PLUMBING - SEWER HCS CONNECT | DMUNIZ | Approved | Not Applicable. |
| 09/02/2020 | PLUMBING - GAS PRESS TEST FNL | DMUNIZ | Approved | Not Applicable. |
| 09/02/2020 | PLUMBING - MD GAS/PRECONST MTG | DMUNIZ | Approved | Not Applicable. |
| 09/02/2020 | ELECTRIC - UFER | DMUNIZ | Approved | Approved |
| 09/02/2020 | U VALUE FOR WINDOW | DMUNIZ | Approved | Approved |
| 09/02/2020 | MECHANICAL - ABOVE CEILING | DMUNIZ | Approved | Approved |
| 09/02/2020 | ELECTRIC - ABOVE CEILING | DMUNIZ | Approved | Approved |
| 09/02/2020 | PLUMBING - ABOVE CEILING | DMUNIZ | Approved | Approved |
| 09/02/2020 | PLUMBING - ROOF DRAINS | DMUNIZ | Approved | Approved |
| 09/02/2020 | FIREWALL/FIREBARRIER/FIRESTOP | DMUNIZ | Approved | Approved |
| 09/02/2020 | BUILDING ABOVE CEILING | DMUNIZ | Approved | Approved |
| 12/04/2020 | NPPO - FINAL | BBENEDON | Approved | |
| 12/04/2020 | LANDSCAPE - FINAL | BBENEDON | Approved | |
| 12/07/2020 | STUCCO MESH | TTREMBULAK | Approved | APPROVED, work was completed and finished. |
| 12/08/2020 | OUTDOOR LIGHTING FINAL | DQUINN | Approved | Ap |
| 12/08/2020 | ELECTRIC - FINAL | DQUINN | Approved | Ap |
| 12/08/2020 | ELECTRIC - OUTDOOR LIGHTING | DQUINN | Approved | Ap |
| 12/09/2020 | MECHANICAL - FINAL | ESTEVENS | Approved | Partial. Pending air balance report. |
| 12/10/2020 | RIGHT OF WAY - FINAL | DR | Approved | Work in ROW completed without DTM Permit. |
| 12/11/2020 | ENGINEERING - FINAL | BBENEDON | Approved | |
| 12/17/2020 | SIGN - FINAL | BBENEDON | Approved | Approved |
| 12/21/2020 | PLUMBING - FINAL | DQUINN | Approved | Ap |
| 12/22/2020 | FIRE - FINAL | jfordney | Approved | Knox boxes and gate keys Address identification |
| 12/22/2020 | FIRE - ALARM FINAL | jfordney | Approved | Duct smoke in ballet room not functioning Duct smoke in music rom office mislabled Duct smoke in prop storage room not functioning |
| 12/22/2020 | FIRE SPKLR - FINAL | jfordney | Approved | |
| 03/22/2021 | BUILDING - FINAL | DQUINN | Approved | SPECIAL INSPECTION COMPLETED |