Permit: T15CM02190
Permit Details
Apply Date:
04/03/2015
Applicant:
HENRY CHAN
Description:
TCO approved for training operations. AREA 1 THRU 8 NEW DISTRIBUTION CENTER
Architects:
- EVERNHAM, KEVIN TODD
Contractors:
- LAYTON CONSTRUCTION CO INC
Permit Reviews
Permit Number - T15CM02190
Permit Status: C of o
Permit Description: TCO approved for training operations. AREA 1 THRU 8 NEW DISTRIBUTION CENTER
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 03/03/2016 | REVISION - - 4TH | 03/03/2016 | COMPLETED |
| 03/03/2016 | REVISION - - 4TH | 04/29/2016 | COMPLETED |
| 04/03/2015 | PLANS OK TO SUBMIT - COMM | 04/03/2015 | COMPLETED |
| 04/03/2015 | COMMERCIAL - NEW | 04/30/2015 | COMPLETED |
| 04/29/2016 | REVISION - - 4TH | 04/29/2016 | COMPLETED |
| 04/29/2016 | REVISION - - 4TH | 05/17/2016 | COMPLETED |
| 05/08/2015 | RESUBMITTAL | 06/01/2015 | COMPLETED |
| 05/17/2016 | RESUBMITTAL - TI ALL | 06/08/2016 | COMPLETED |
| 06/01/2015 | RESUBMITTAL | 06/03/2015 | COMPLETED |
| 06/03/2015 | RESUBMITTAL | 06/08/2015 | COMPLETED |
| 06/08/2015 | RESUBMITTAL | 06/12/2015 | COMPLETED |
| 09/14/2015 | REVISION - - 1ST | 09/14/2015 | COMPLETED |
| 09/14/2015 | REVISION - - 1ST | 09/28/2015 | COMPLETED |
| 09/28/2015 | REVISION - - 2ND | 09/28/2015 | COMPLETED |
| 10/09/2015 | REVISION - - 2ND | 10/12/2015 | COMPLETED |
| 10/20/2015 | REVISION - - 3RD | 10/20/2015 | COMPLETED |
| 10/20/2015 | REVISION - - 3RD | 11/04/2015 | COMPLETED |
Completed Inspections
Permit Status: C of o
Permit Number: T15CM02190
Permit Description: TCO approved for training operations. AREA 1 THRU 8 NEW DISTRIBUTION CENTER
Total Completed Inspections - 48
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/03/2015 | SEWER - PRE CONSTRUCTION MTG | JBURGE | Approved | PRECON MEETING. PLUMBING UNDERGROUND: WASTELINES (2", 4", 6") GL: A-D/2-6 - ENSURE LEAK ON 2" LINE IS CORRECTED. OK TO COVER PROGRESS AREA |
| 08/03/2015 | SEWER - PRE CONSTRUCTION MTG | JBURGE | Approved | IVRS - Inspection :* |
| 09/03/2015 | OUTDOOR LIGHTING FINAL | JBURGE | Approved | 3/4" AND 1" CONDUITS FOR CAMERAS AND POLE LIGHTS SE CORNER - OK TO COVER |
| 09/03/2015 | OUTDOOR LIGHTING FINAL | JBURGE | Approved | IVRS - Inspection :* |
| 10/09/2015 | ELECTRIC - UFER | JBURGE | Approved | IVRS - Inspection :* |
| 10/30/2015 | ELECTRIC - PROGRESS | JBURGE | Approved | COUDIT AND BOXES FOR 23 DOCK LEVELERS AT WING "C"- SOUTH SIDE |
| 11/03/2015 | FIRE SPKLR - UG, PIPING, HYDRO | CSCHULTZ | Approved | |
| 11/03/2015 | PLUMBING - YARD WTR LINE/TEST | JBURGE | Approved | IVRS - Inspection :* |
| 11/04/2015 | ELECTRIC - UNDERGROUND | JBURGE | Approved | LOW BAY AREAS WING "A" SOUTH SIDE; WING "B" MID AREA; WING "C" NORTH SIDE. 3", 2", 1 1/2", 1" CONDUITS OK TO COVER PROGRESS |
| 11/10/2015 | BUILDING - PROGRESS | JBURGE | Approved | REBAR FOR DOCK LEVELERS AT WING A GL A.0/21-23 |
| 12/09/2015 | PLUMBING - ROUGH, SOIL | JBURGE | Approved | ROUGH SOIL. ACID RETENTION/ DILUTION TANK DETAIL #2 OK TO COVER |
| 12/10/2015 | SITE - SEWER | JBURGE | Approved | PRESSURE TEST ON MANDREL MH'S # 1,2,3 |
| 12/10/2015 | ELECTRIC - OUTDOOR LIGHTING | JBURGE | Approved | 22 CAISSON LIGHT POLE FOOTINGS- OK TO POUR |
| 12/14/2015 | BUILDING PRE-SLAB | JBURGE | Approved | DOCK LEVELERS LOW BAY GL- Q/7-20 ENSUR PROPER CLEARANCE OF VERTICALS AT FRAME OK TO POUR PROGRESS AREA |
| 12/15/2015 | FIRE SPKLR - UG PIPING FLUSH | CSCHULTZ | Approved | |
| 12/16/2015 | FIRE - ALARM FINAL | CSCHULTZ | Approved | Need to monitor all OSY's at the back flows for the fire lines X 4 (Tamper switches). |
| 12/18/2015 | ELECTRIC - INTERMEDIATE | JBURGE | Approved | IVRS - Inspection :* |
| 12/21/2015 | PLUMBING - PROGRESS | cpierce | Approved | NO INSPECTIONS ALLOWED UNTIL PRIVATE SEWER PERMIT ISSUED. |
| 12/22/2015 | PLUMBING - INTERMEDIATE | JBURGE | Approved | IVRS - Inspection :* |
| 12/22/2015 | FIRE - HYDRANTS | CSCHULTZ | Approved | TUCSON WATER IS STATING THAT THEY NO LONGER HAVE THE FUNDING TO PROVIDE LOCKS ON THE PRIVATE HYDRANTS. THIS CONDITION HAS BEEN REMOVED |
| 12/23/2015 | STEM WALL/RETAINING WALL | JBURGE | Approved | EAST - N. EAST; SOUTH CENTRAL |
| 12/23/2015 | FRAMING | JBURGE | Approved | IVRS - Inspection :* |
| 12/23/2015 | REINFORCED MASONRY PRE-GROUT | JBURGE | Approved | IVRS - Inspection :* |
| 12/29/2015 | EXCAVATION/LAYOUT REBAR & ZON | JBURGE | Approved | IVRS - Inspection :* |
| 05/19/2016 | ENGINEERING - FINAL | DROBERTS | Approved | WALKED THE SITE AND LOOKED AT THE WORK THAT IS REMAINING, NOTHING WILL AFFECT THE TEMPORARY CERTIFICATE OF OCCUPANCY. |
| 05/19/2016 | PLUMBING - ABOVE CEILING | MRAMBER | Approved | IVRS - Inspection :* |
| 05/19/2016 | MECHANICAL - ABOVE CEILING | MRAMBER | Approved | IVRS - Inspection :* |
| 05/19/2016 | MECHANICAL - INTERMEDIATE | MRAMBER | Approved | IVRS - Inspection :* |
| 05/19/2016 | ELECTRIC - TEMP POWER FOR TEST | MRAMBER | Approved | IVRS - Inspection :* |
| 05/19/2016 | ELECTRIC - CONSTRUCTION POWER | MRAMBER | Approved | IVRS - Inspection :* |
| 05/19/2016 | FIREWALL/FIREBARRIER/FIRESTOP | MRAMBER | Approved | IVRS - Inspection :* |
| 05/19/2016 | U VALUE FOR WINDOW | MRAMBER | Approved | IVRS - Inspection :* |
| 05/19/2016 | SHEET ROCK NAILING | MRAMBER | Approved | IVRS - Inspection :* |
| 05/19/2016 | EXT METAL CLIPS/EXT SHEATHING | MRAMBER | Approved | IVRS - Inspection :* |
| 05/19/2016 | FIRE SPKLR - FINAL | jvincent | Approved | sprinkler final approved. in rack and conveyor systems under separate permits. |
| 05/19/2016 | FIRE SPKLR - OH PIPING & HYDRO | jvincent | Approved | |
| 07/22/2016 | PLUMBING - ROOF DRAINS | ramber | Approved | |
| 07/22/2016 | ELECTRIC - ABOVE CEILING | ramber | Approved | |
| 07/22/2016 | BUILDING ABOVE CEILING | ramber | Approved | |
| 08/16/2016 | FIRE - FINAL | jvincent | Approved | Approved. Shell only. |
| 09/01/2016 | RIGHT OF WAY - FINAL | drussell | Approved | |
| 12/08/2016 | BUILDING - FINAL | mramber1 | Approved | middle fnger (area 8) ok temp C.O. |
| 02/01/2018 | NPPO - FINAL | DROBERTS | Approved | |
| 02/01/2018 | SIGN - FINAL | DROBERTS | Approved | |
| 02/01/2018 | LANDSCAPE - FINAL | DROBERTS | Approved | |
| 03/09/2018 | ELECTRIC - FINAL | mramber1 | Approved | |
| 03/09/2018 | MECHANICAL - FINAL | mramber1 | Approved | |
| 03/09/2018 | PLUMBING - FINAL | mramber1 | Approved |