Permit: T15CM02190

Parcel: 14041134D


Addresses:

7000 S ALVERNON WY

Inspection Status: Approved

Inspection History: EXCAVATION/LAYOUT REBAR & ZON

Date Description Inspector Results Comments
05/19/2016 EXCAVATION/LAYOUT REBAR & ZON Approved IVRS - Inspection :*
03/14/2016 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection IVRS - Inspection :*
03/04/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
02/03/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
12/29/2015 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
12/21/2015 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
12/08/2015 EXCAVATION/LAYOUT REBAR & ZON Partial Approval LAYOUT REBAR PARTIAL- RAMP AT GL: Q/6.1 OK TO POUR PROGRESS AREA
12/06/2015 EXCAVATION/LAYOUT REBAR & ZON Partial Approval LOW BAY DOCK LEVELERS SLAB POUR GL: B/9-20 OK TO POUR
VERTICLE BAYS EPOXIED IN EXISTINGFOOTINGS
12/03/2015 EXCAVATION/LAYOUT REBAR & ZON Partial Approval GL:Q/12.5-9 OK TO POUR PROGREE AREA
12/02/2015 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
11/23/2015 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
11/09/2015 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Wing A" (north) - dock levelers high pour
GL: c.3/21-32; slab (high) GL:32?A.0-C.3
ok to pour progress areas
11/05/2015 EXCAVATION/LAYOUT REBAR & ZON Partial Approval EXCAVATION/LAYOUT REBAR
GL: P-5 C/20.9-21 OK TO POUR AREA
11/04/2015 EXCAVATION/LAYOUT REBAR & ZON Partial Approval WING 'A' DOCK LEVELERS SOUTH SIDE LOW POUR; WING "C" DOCK LEVELERS SOUTH SIDE HIGH POUR OK TO POUR PROGRESS AREA
11/03/2015 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
10/29/2015 EXCAVATION/LAYOUT REBAR & ZON Partial Approval TILT PANELS # 38-51 299- 324 4 PANELS FOR PUMPHOUSE
WING C NORTH SIDE DOCK LEVELERS
10/22/2015 EXCAVATION/LAYOUT REBAR & ZON Partial Approval EXCAVATION/LAYOUT REBAR: PARTIAL-23@ DOCK LEVELERS AT GL" Q.9/22-28: OKAY TO POUR PROGRESS AREAS
10/21/2015 EXCAVATION/LAYOUT REBAR & ZON Partial Approval EXCAVATION LAYOUT REBAR-PARTIAL-3@ LIGHT POLE CAISSON FOOTINGS' WING "C"- CENTER AREA.
10/19/2015 EXCAVATION/LAYOUT REBAR & ZON Partial Approval EXCAVATION/LAYOUT REBAR-PARTIAL-PANEL TIES ON WEST SIDE OF WING "B": OK TO POUR PROGRESS AREAS
"A" WING PANEL TIES IN PLACE AT ALL WALLS
10/15/2015 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
10/15/2015 EXCAVATION/LAYOUT REBAR & ZON Partial Approval 4@ NW (MID AREA) ; 3 @ NE OF MAIN BUILDING
10/12/2015 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
10/09/2015 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection IVRS - Inspection :*
10/08/2015 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
10/07/2015 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection IVRS - Inspection :*
10/06/2015 EXCAVATION/LAYOUT REBAR & ZON Partial Approval TILT PANELS # 136,137,135,146-148,298A,298B PANELS 348-351,345,346; LOADING DOCK APRON "A" SOUTH GL A-O/11-21 OK TO POUR PROGRESS AREA
10/05/2015 EXCAVATION/LAYOUT REBAR & ZON Partial Approval piers f-3 gl: e/2-5; 5 /e-p FOOTINGS (F-7) GL; Q/4-3, 2-1; 1/Q-P; PANEL TIES AT WING "B" NORTH AND SOUTH SIDES; 2 BX CULVERTS: EAST SIDE & SE SIDE : LOADING DOCK APRON "A" WING-SOUTH PORTION GL: A.O/21-32 OK TO POUR PROGRESS
10/02/2015 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
10/01/2015 EXCAVATION/LAYOUT REBAR & ZON Partial Approval PANEL TIES 'c' WING SOUTH SIDE
09/30/2015 EXCAVATION/LAYOUT REBAR & ZON Partial Approval 12 AT F-3 SPREAD FOOTING GL; H-K/2-4 BRACING FOOTINGS AT GL B/7-8.5; 7/B-D WING "C"NORTH PANEL TIES GL: Q/21-32 OK TO POUR PROGRESS AREAS
09/28/2015 EXCAVATION/LAYOUT REBAR & ZON Partial Approval SPREAD FOOTING AT GL:N-P/6-6.1: F5 (6) F10 (2); 3TP/F11 (1)- OK TO POUR
09/28/2015 EXCAVATION/LAYOUT REBAR & ZON Partial Approval TILT PANELS#23-37 OK TO POUR PROGRESS AREAS
09/18/2015 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
09/15/2015 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection IVRS - Inspection :*
09/11/2015 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
09/09/2015 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
09/09/2015 EXCAVATION/LAYOUT REBAR & ZON Partial Approval FOOTINGS GL1/D.5-P.5; PEDISTALS GL: B/21 (2)
09/08/2015 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection CONTRACTOR CANCELLED NOT READY
09/02/2015 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
09/02/2015 EXCAVATION/LAYOUT REBAR & ZON Partial Approval CONTINUOUS FOOTING GL: 21/A-B.1; B-1/15-21: 6 @ WINGS AC, F-2, F-6
08/28/2015 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
08/28/2015 EXCAVATION/LAYOUT REBAR & ZON Partial Approval CONTINUOUS FOOTINGS AT WING "C" NORTH AND WEST - OK TO POUR PROGRESS AREA
08/27/2015 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
08/27/2015 EXCAVATION/LAYOUT REBAR & ZON Partial Approval CONTINUOUS FOOTINGS (F1 & F3) GL: D/2.5-7.5; 2/A-D; A/2-7; 6.75/A-B - OK TO POUR PROGRESS AREAS
08/26/2015 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection IVRS - Inspection :*
08/25/2015 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
08/25/2015 EXCAVATION/LAYOUT REBAR & ZON Partial Approval WEST END OF WING "B" GL: 32/G.2-I.7 - OK TO POUR
08/24/2015 EXCAVATION/LAYOUT REBAR & ZON Partial Approval CONTINUOUS FOOTINGS AT "A" WING GL: A-C.3/21-32 - OK TO POUR FOOTINGS
08/24/2015 EXCAVATION/LAYOUT REBAR & ZON Partial Approval PARTIAL WING B NORTH, DOCK LEVELERS
OK TO POUR PROGRESS AREA
08/19/2015 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
08/19/2015 EXCAVATION/LAYOUT REBAR & ZON Partial Approval CONTINUOUS FOOTINGS BETWEEN WINGS A-B. GL: C3-G2 - OK TO POUR
08/18/2015 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
08/18/2015 EXCAVATION/LAYOUT REBAR & ZON Partial Approval COLUMN FOOTINGS: F-6 GL: 7-8, 9/P (4 EACH) F-1 FOOTING GL: F-1 CONTINUOUS, 7/H-M: 4 F-8 FOOTINGS; F-8 E/10 (1)
08/14/2015 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
08/14/2015 EXCAVATION/LAYOUT REBAR & ZON Partial Approval TILT PANELS - #'S 217-231, 235-237, 295-297 - OK TO POUR PROGRESS AREAS (24 PANELS)
08/13/2015 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
08/13/2015 EXCAVATION/LAYOUT REBAR & ZON Partial Approval COLUMN FOOTINGS (F-8, F-4) GL: E/7-10
08/12/2015 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
08/12/2015 EXCAVATION/LAYOUT REBAR & ZON Partial Approval COLUMN FOOTINGS F-4 (31 EACH) GL: E/9.5-10.5 - OK TO POUR
08/11/2015 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection IVRS - Inspection :*
08/07/2015 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
08/07/2015 EXCAVATION/LAYOUT REBAR & ZON Partial Approval COLUMN FOOTINGS (F-4, F-8) GL: D.5-E.5/9-18 - OK TO POUR PROGRESS AREAS
08/05/2015 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
08/05/2015 EXCAVATION/LAYOUT REBAR & ZON Partial Approval SHIPPING BAY BETWEEN "C" AND "B" - CONTINUOUS FOOTINGS AT GL: 0/21-31; 21/Q.5-0; 0/21-31 - OK TO POUR
08/04/2015 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
08/04/2015 EXCAVATION/LAYOUT REBAR & ZON Partial Approval COLUMN FOOTINGS ON GL: 13.5-14.5/F-M.5; F-4, F-8 - OK TO POUR
07/31/2015 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
07/31/2015 EXCAVATION/LAYOUT REBAR & ZON Partial Approval COLUMN FOOTINGS GL: B-K/20-21 (F-4); COLUMN FOOTINGS (F-4/F-8) GL: F-H/11-13; H/19-17 (F-8) - OK TO POUR PROGRESS AREAS
07/29/2015 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection NOT READ- RAINED OUT
07/28/2015 EXCAVATION/LAYOUT REBAR & ZON Partial Approval COLUMN FOOTINGS GL; J-N/11-13 F8,F4 GL; 21/OK TO POUR. 2-F/2, 1F5, 1F6
07/27/2015 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
07/27/2015 EXCAVATION/LAYOUT REBAR & ZON Partial Approval C3/F8, F4 COLUMN FOOTINGS ON GL: 15-17/F-K - OK TO POUR PROGRESS AREAS
07/24/2015 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
07/24/2015 EXCAVATION/LAYOUT REBAR & ZON Partial Approval CS/F8 (6); F4 (9) COLUMN FOOTINGS GL: L-P/19-17 - OK TO POUR PROGRESS AREAS
07/22/2015 EXCAVATION/LAYOUT REBAR & ZON Partial Approval COLUMN FOOTINGS: C1/F6 GL: 19-20/P-N, F8/C3, F/4 GL: 19/N.5-H; 20/N.5-H
OK TO POUR PROGRESS AREAS
D/8-21, C/8-21
07/17/2015 EXCAVATION/LAYOUT REBAR & ZON Partial Approval COLUMN FOOTINGS C1/F6 GL: D/8-10
F8/C3 GL: E/8-10; F8/C3 GL: F/8-10; GL G/F8/C3 G/8-10
OK TO GROUTE PROGRESS AREAS
07/16/2015 EXCAVATION/LAYOUT REBAR & ZON Partial Approval 7 EACH C6/F5 COLUMN FOOTINGS AT GL: C/3-7; B /2-4
07/15/2015 EXCAVATION/LAYOUT REBAR & ZON Partial Approval WING "A"; C2-C10/F2-F-13
GL; P.6-P.9/21.1-32: OK TO POUR PROGRESS AREAS
07/14/2015 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
07/10/2015 EXCAVATION/LAYOUT REBAR & ZON Partial Approval WING C; P6, P9/ 21.5-31 COLUMNS & FOOTINGS C2/F2; C10/F13- OK TO POUR PROGRESS AREA