Inspection Status: Approved
Inspection History: PLUMBING - ROUGH, SOIL
| Date |
Description |
Inspector |
Results |
Comments |
| 05/19/2016 |
PLUMBING - ROUGH, SOIL |
|
Approved |
IVRS - Inspection :* |
| 12/09/2015 |
PLUMBING - ROUGH, SOIL |
|
Partial Approval |
ROUGH SOIL. ACID RETENTION/ DILUTION TANK DETAIL #2 OK TO COVER |
| 11/10/2015 |
PLUMBING - ROUGH, SOIL |
|
Partial Approval |
IVRS - Inspection :* |
| 10/21/2015 |
PLUMBING - ROUGH, SOIL |
|
Partial Approval |
PLUMBING ROUGH SOIL- PARTIAL-4" &2" LINES FOR RESTROOM AT N.E CORNER OF WING "A"- OK TO COVER PROGRESS AREA |
| 10/15/2015 |
PLUMBING - ROUGH, SOIL |
|
Partial Approval |
IVRS - Inspection :* |
| 10/15/2015 |
PLUMBING - ROUGH, SOIL |
|
Partial Approval |
WING "C" RESTROOM- UNDER TEST- OK TO COVER |
| 08/28/2015 |
PLUMBING - ROUGH, SOIL |
|
Partial Approval |
4" WTR LINE FROM MAIN VALVE TO APPROX 20' FROM BLDG OK TO COVER PROGRESS |
| 08/05/2015 |
PLUMBING - ROUGH, SOIL |
|
Partial Approval |
RESTROOM AT GL: M/16 - OK TO COVER |
| 07/30/2015 |
PLUMBING - ROUGH, SOIL |
|
Partial Approval |
8" WASTELINE AT GL: 8/B-Q (8 EACH 4" CLEANOUTS) - OK TO COVER PROGRESS AREA |
| 07/20/2015 |
PLUMBING - ROUGH, SOIL |
|
Partial Approval |
PARTIAL- 8" WASTE LINE APPROX 200' AT GL: M-15 OK TO COVER PROGRESS AREAS |
| 07/17/2015 |
PLUMBING - ROUGH, SOIL |
|
Partial Approval |
8" WASTE LINE WITH CLEAN-OUTS GL:21.1 PVC PIPING HAS BEEN APPROVED AS PER SPEC MANUAL PAGE 142150 |