Inspection Status: Approved
Inspection History: BUILDING PRE-SLAB
Permit Number - T15CM02190
Inspection Description - BUILDING PRE-SLAB
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
05/19/2016 | BUILDING PRE-SLAB | Approved | IVRS - Inspection :* | |
03/25/2016 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :* | |
03/08/2016 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :* | |
03/01/2016 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :* | |
02/24/2016 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :* | |
02/19/2016 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :* | |
02/17/2016 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :* | |
02/12/2016 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :* | |
02/01/2016 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :* | |
01/31/2016 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :* Super flat slab ( pour #7 ) - GL: 4/P.5-D.5 - ok to pour when area dries out. | |
01/27/2016 | BUILDING PRE-SLAB | Partial Approval | plmd int ok at office area pvc support not to exceed 48" cl 1.5 thru q-e ok to pour |
|
01/22/2016 | BUILDING PRE-SLAB | Partial Approval | 4,5,6 FROM EAST SUPER FLATS OK TO POUR | |
01/21/2016 | BUILDING PRE-SLAB | Partial Approval | SUPER FLAT SLAB AT GL 2.75/Q-E OK TO POUR | |
01/20/2016 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :* | |
12/14/2015 | BUILDING PRE-SLAB | Partial Approval | DOCK LEVELERS LOW BAY GL- Q/7-20 ENSUR PROPER CLEARANCE OF VERTICALS AT FRAME OK TO POUR PROGRESS AREA |
|
12/09/2015 | BUILDING PRE-SLAB | Partial Approval | DOCK LEVELERS HIGH BAY GL:-Q/9-13 OK TO POUR PROGRESS AREA |
|
12/06/2015 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :* | |
11/30/2015 | BUILDING PRE-SLAB | Partial Approval | HIGH AREA LOADING DOCK LEVELERS- OK TO POUR WING B | |
11/24/2015 | BUILDING PRE-SLAB | Partial Approval | LOW BAY DOCK LEVELERS SOUTH SIDE BOTTOM POUR OK TO POUR | |
11/19/2015 | BUILDING PRE-SLAB | Not ready for Inspection | IVRS - Inspection :* | |
11/18/2015 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :* | |
11/16/2015 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :* | |
10/14/2015 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :* | |
10/13/2015 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :* | |
10/01/2015 | BUILDING PRE-SLAB | Partial Approval | NW CORNER AT EAST END OF C WING OK TO POUR | |
09/11/2015 | BUILDING PRE-SLAB | Partial Approval | CHANGED FROM AP TO PA FOR ALLOW FOR REINSPECTION. - AROMERO |
|
09/10/2015 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :* | |
09/09/2015 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :* | |
09/09/2015 | BUILDING PRE-SLAB | Partial Approval | GL:D-F/8-13 | |
09/08/2015 | BUILDING PRE-SLAB | Not ready for Inspection | IVRS - Inspection :* | |
09/02/2015 | BUILDING PRE-SLAB | Partial Approval | OFFICE AREA - OK TO POUR | |
09/01/2015 | BUILDING PRE-SLAB | Not ready for Inspection | IVRS - Inspection :* | |
09/01/2015 | BUILDING PRE-SLAB | Not ready for Inspection | RAINED OUT | |
08/26/2015 | BUILDING PRE-SLAB | Not ready for Inspection | IVRS - Inspection :* | |
08/26/2015 | BUILDING PRE-SLAB | Not ready for Inspection | CONTRACTOR CANCELED | |
08/25/2015 | BUILDING PRE-SLAB | Not ready for Inspection | IVRS - Inspection :* | |
08/25/2015 | BUILDING PRE-SLAB | Not ready for Inspection | RAINED OUT | |
08/24/2015 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :* | |
08/24/2015 | BUILDING PRE-SLAB | Partial Approval | SLAB AT GL: N-P/13-21 - OK TO POUR PROGRESS AREA | |
08/19/2015 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :* | |
08/19/2015 | BUILDING PRE-SLAB | Partial Approval | TILT PANELS #1-21, 232, 233, 234, 277, 278, & 296 - OK TO POUR PROGRESS AREAS | |
08/18/2015 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :* | |
08/18/2015 | BUILDING PRE-SLAB | Partial Approval | GL: B-G/18-20.5 - OK TO POUR | |
08/13/2015 | BUILDING PRE-SLAB | Partial Approval | GL: G-P/18-21 - OK TO POUR | |
08/11/2015 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :* | |
08/11/2015 | BUILDING PRE-SLAB | Partial Approval | BUILDING SLAB AT GL: B-D/14-19 - OK TO POUR PENDING WEATHER | |
08/10/2015 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :* | |
08/10/2015 | BUILDING PRE-SLAB | Partial Approval | BUILDING SLAB AT GL: B-D/8-14 - OK TO POUR | |
08/04/2015 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :* | |
08/04/2015 | BUILDING PRE-SLAB | Partial Approval | WING "C" WEST PORTION; OK TO POUR | |
07/31/2015 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :* | |
07/31/2015 | BUILDING PRE-SLAB | Partial Approval | WING "B", WEST HALF - OK TO POUR | |
07/30/2015 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :* | |
07/30/2015 | BUILDING PRE-SLAB | Partial Approval | NW OF WING "A" - POURED (SPECIAL INSPECTED). | |
07/29/2015 | BUILDING PRE-SLAB | Partial Approval | "B" WING EAST HALF; GL; 21-26 OK TO POUR |
|
07/22/2015 | BUILDING PRE-SLAB | Partial Approval | WING "A" SLAB; 27-32/N.6-Q.9 OK TO POUR PROGRESS AREA |