Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit: T15CM02190

Parcel: 14041134D


Addresses:

7000 S ALVERNON WY


Inspection Status: Approved

Inspection History: FIRE SPKLR - UG, PIPING, HYDRO

Permit Number - T15CM02190

Inspection Description - FIRE SPKLR - UG, PIPING, HYDRO

Inspection Status - Approved

Date Description Inspector Results Comments
11/03/2015 FIRE SPKLR - UG, PIPING, HYDRO Approved
10/05/2015 FIRE SPKLR - UG, PIPING, HYDRO Cancelled On site (1:45PM) found nothing has changed and could not find UG contractor talked to a person driving by in a Layton truck asked he has seen anybody from the UG company stated no, I did a drive by on the property could not find UG contractor.
09/30/2015 FIRE SPKLR - UG, PIPING, HYDRO Partial Approval Okay to bury 400' Feet of 10" inch PVC pipe northside first 45 to riser after the first 10 loading docks going west ward. Still need to pressure test and flush.
09/29/2015 FIRE SPKLR - UG, PIPING, HYDRO Partial Approval Okay to bury 220 feet 10" PVC northside center of building
Still need to pressure test and flush.
09/21/2015 FIRE SPKLR - UG, PIPING, HYDRO Cancelled
09/17/2015 FIRE SPKLR - UG, PIPING, HYDRO Partial Approval Visual inspection 60 feet 0f 10" line for riser #1 west of fire pump house
Visual inspection 20 feet of 10" line to pump house
Visual inspection 20 feet of 10" pipe for FDC's
Visual inspection 20' feet of 6" ductile for city fire hydrant
Still need to pressure test and flush.
09/16/2015 FIRE SPKLR - UG, PIPING, HYDRO Partial Approval At this time 680 feet of 12" line inspected southeast even with fir pump room, 197 feet of 10" line looked at southeast even with fire pump room, still needs 225 psi test and flushing. Thrust blocking being used for all 12" lines according to FM requirements (contractor stated), contractor will be leaving all 45's, 90's in the open and then pour blocking for TFD inspector to inspect.
Still need to pressure test and flush.
09/11/2015 FIRE SPKLR - UG, PIPING, HYDRO Partial Approval 1. Awaiting letter from Engineer in regards to bell restraints and joints.
2. Courtesy inspection
3. Ok to backfill SE corner of 10" pipe
4. Still need hydro and flush
09/03/2015 FIRE SPKLR - UG, PIPING, HYDRO Partial Approval Call out to inspect 238' OF 10" C-900 underground piping NOT APPROVED - DO NOT cover until answers are given from Civil Engineer Mark Beck about needing to add bell restrains to all bell joints or correct and install per C.O.T. standards DTL. W-610 (SD-610).
Still need to pressure test and flush.
08/18/2015 FIRE SPKLR - UG, PIPING, HYDRO Continued SET UP MEETING WITH CONTRACTOR TO DISCUSS FD EXPECTATIONS