Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

PRO is currently experiencing an outage. Some documents and records may not be available on PRO momentarily. We apologize for the inconvenience and are working to restore full access.

Permit Details

Status:
C of o
Type:
COMMERCIAL NEW
Address:
125 S LINDA AV
Address NEW:
125 S LINDA AV
Apply Date:
02/28/2011
Applicant:
N/A
Description:
SENIOR HOUSING APARTMENTS
Contractors:
  • W E O'NEIL

Permit Reviews

Permit Number - T11CM00617
Permit Status: C of o
Permit Description: SENIOR HOUSING APARTMENTS
Start Date Submittal Complete Date Status  
01/20/2012 REVISION - - 2ND 01/20/2012 COMPLETED Review Details
02/15/2012 REVISION - - 3RD 02/16/2012 COMPLETED Review Details
02/16/2012 REVISION - - 3RD 02/17/2012 COMPLETED Review Details
02/28/2011 PLANS OK TO SUBMIT - COMM 02/28/2011 COMPLETED Review Details
02/28/2011 COMMERCIAL - NEW 03/23/2011 COMPLETED Review Details
03/31/2011 RESUBMITTAL - TI ALL 04/20/2011 COMPLETED Review Details
04/20/2011 RESUBMITTAL - TI ALL 05/19/2011 COMPLETED Review Details
07/21/2011 REVISION - - 1ST 07/25/2011 COMPLETED Review Details
12/15/2011 REVISION - - 2ND 01/19/2012 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T11CM00617
Permit Status: C of o
Permit Description: SENIOR HOUSING APARTMENTS
Total Outstanding Activity Conditions - 1
Date Name
02/28/2011 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: C of o
Permit Number: T11CM00617
Permit Description: SENIOR HOUSING APARTMENTS
Total Completed Inspections - 46
Date Description Inspector Results Comments
07/07/2011 STEM WALL/RETAINING WALL AQUIROZ Approved IVRS - Inspection :*
1) GL: 3-P-1, P-G/1
2) ELEVATOR PIT AT M-D/2-3
07/08/2011 ELECTRIC - UFER AQUIROZ Approved IVRS - Inspection :*
1) LINE K-6
07/19/2011 EXCAVATION/LAYOUT REBAR & ZON AQUIROZ Approved IVRS - Inspection :*
1) RETAINING WALL FOOTER GL B-C/2; G.4/P/01
07/19/2011 EXCAVATION/LAYOUT REBAR & ZON AQUIROZ Approved IVRS - Inspection :*
07/25/2011 PLUMBING - ROUGH, SOIL RMYERS Approved IVRS - Inspection :*
1) BLDG #2 PVC UNDERGROUND OK
08/01/2011 PLUMBING - YARD WTR LINE/TEST RMYERS Approved IVRS - Inspection :*
08/05/2011 PLUMBING - PRE SLAB RRICH Approved IVRS - Inspection :*
08/08/2011 BUILDING PRE-SLAB AQUIROZ Approved IVRS - Inspection :*
1) GL 1-15/P-J
11/16/2011 MECHANICAL - INTERMEDIATE MRAMBER Approved IVRS - Inspection :*
11/18/2011 ELECTRIC - UNDERGROUND DSANTACR Approved IVRS - Inspection :*
1) OK SECONDARIES FROM BLDG TO SES.
2) PROTECT M/C PER 300.4 (1 1/4")
3) KITCHEN COUNTER RECEPTS PER 210.52 (C)
11/30/2011 ELECTRIC - INTERMEDIATE AQUIROZ Approved IVRS - Inspection :*
1) 1ST FLOOR UNITS 101 THRU 119
12/02/2011 PLUMBING - ROOF DRAINS RMYERS Approved IVRS - Inspection :*
12/05/2011 PLUMBING - GAS PRESSURE TEST RMYERS Approved IVRS - Inspection :*
1) MEDIUM PRESSURE GAS MAIN DOWN CORRIDOR OK
2) 60 POUND TEST OK
12/23/2011 PLUMBING - INTERMEDIATE RMYERS Approved IVRS - Inspection :*
1) 2ND & 3RD FLOOR DWV OK PEX OK
OK TO INSULATE HOT & RETURN
NEED TO SEE FLANGES
12/28/2011 REINFORCED MASONRY PRE-GROUT LHANLY Approved 2nd lift/ 5th floor/ east wing complete
12/29/2011 FRAMING LHANLY Approved
02/22/2012 FIRE SPKLR - UG, PIPING, HYDRO DSIWARSKI Approved
05/17/2012 SHEET ROCK NAILING BBENEDON Approved 6TH FLOOR
05/25/2012 TEP CLEARANCE - AM JWEATHER Approved ECO CLEARED FOR #221 &321 PER R. MORENO
06/18/2012 ROOF NAILING AQUIROZ Approved IVRS - Inspection :*
06/18/2012 EXT METAL CLIPS/EXT SHEATHING AQUIROZ Approved IVRS - Inspection :*
06/22/2012 PLUMBING - GAS PRESS TEST FNL RMYERS Approved IVRS - Inspection :*
06/26/2012 FIREWALL/FIREBARRIER/FIRESTOP AQUIROZ Approved IVRS - Inspection :*
06/26/2012 BUILDING ABOVE CEILING AQUIROZ Approved IVRS - Inspection :*
06/26/2012 PLUMBING - SEWER HCS CONNECT AQUIROZ Approved IVRS - Inspection :*
06/26/2012 PLUMBING - ABOVE CEILING AQUIROZ Approved IVRS - Inspection :*
06/27/2012 ELECTRIC - ABOVE CEILING DSANTACR Approved IVRS - Inspection :*
06/28/2012 MECHANICAL - HYDRONIC PIPING MRAMBER Approved IVRS - Inspection :*
07/09/2012 MECHANICAL - ABOVE CEILING MRAMBER Approved IVRS - Inspection :*
07/10/2012 ELECTRIC - OUTDOOR LIGHTING DSANTACR Approved IVRS - Inspection :*
07/12/2012 ELECTRIC - FINAL DSANTACR Approved IVRS - Inspection :*
07/13/2012 NPPO - FINAL RLEDONNE Approved
07/13/2012 SIGN - FINAL RLEDONNE Approved
07/13/2012 LANDSCAPE - FINAL RLEDONNE Approved
07/16/2012 PLUMBING - FINAL AQUIROZ Approved IVRS - Inspection :*
07/16/2012 PLUMBING - PROGRESS AQUIROZ Approved IVRS - Inspection :*
07/17/2012 RIGHT OF WAY - FINAL TWOLFGAN Approved
07/18/2012 ZONING - FINAL RLEDONNE Approved
07/18/2012 ENGINEERING - FINAL RLEDONNE Approved
07/20/2012 MECHANICAL - FINAL MRAMBER Approved IVRS - Inspection :*
07/25/2012 BUILDING - PROGRESS AQUIROZ Approved IVRS - Inspection :*
07/26/2012 CERTIFICATE OF OCCUPANCY AQUIROZ Approved IVRS - Inspection :*
07/26/2012 BUILDING - FINAL AQUIROZ Approved IVRS - Inspection :*
07/27/2012 FIRE SPKLR - FINAL WMOTTO Approved
07/30/2012 FIRE - FINAL KENB Approved As builts plans were given to Fire Code Administrator.
07/30/2012 FIRE - ALARM FINAL KENB Approved