07/05/2012 PLUMBING - INTERMEDIATE Approved IVRS - Inspection :*
06/28/2012 PLUMBING - INTERMEDIATE Partial Approval IVRS - Inspection :*
06/15/2012 PLUMBING - INTERMEDIATE Partial Approval 1. First floor office restroom flange not set. 2. Fourth floor corridor strap CPVC.
06/06/2012 PLUMBING - INTERMEDIATE Partial Approval IVRS - Inspection :*
06/05/2012 PLUMBING - INTERMEDIATE Partial Approval IVRS - Inspection :*
5TH FLOOR NORTH WING EXCLUDE ROOM 510
6TH FLOOR NORTH WING EXCLUDE ROOM 608
EAST WING NOT READY 5TH FLOOR
05/08/2012 PLUMBING - INTERMEDIATE Partial Approval IVRS - Inspection :*
1) 3RD AND 4TH FLOOR FLANGES OK
05/03/2012 PLUMBING - INTERMEDIATE Partial Approval IVRS - Inspection :*
1) 3RD AND 4TH FLOOR CLOSET FLANGES THAT HAD BROKEN
TEST CAPS, REQUIRES CORRECTIONS. THE PIPE IS TO EXTEND THE TOP FACE OF THE FLANGE
04/18/2012 PLUMBING - INTERMEDIATE Partial Approval IVRS - Inspection :*
FIRST FLOOR FLANGES OK
04/17/2012 PLUMBING - INTERMEDIATE Not ready for Inspection IVRS - Inspection :*
04/11/2012 PLUMBING - INTERMEDIATE Not ready for Inspection IVRS - Inspection :*
04/10/2012 PLUMBING - INTERMEDIATE Not ready for Inspection IVRS - Inspection :*
1) 3" MULLER FLANGES NOT LISTED FOR INSIDE PIPE
2) 4" FLANGES (AND ALL FITTINGS) REQUIRE FULL MAKE UP WITH NO FOULING LEDGES
03/26/2012 PLUMBING - INTERMEDIATE Partial Approval IVRS - Inspection :*
1) 6TH FLOOR PEX AND PVC OK
03/07/2012 PLUMBING - INTERMEDIATE Partial Approval IVRS - Inspection :*
1) 4TH AND 5TH FLOOR PEX OK
03/05/2012 PLUMBING - INTERMEDIATE Partial Approval IVRS - Inspection :*
1) 4TH & 5TH FLOOR PVC DWV WATER TEST OK
2) 4TH FLOOR WATER PIPING NORTH BLDG OK
03/02/2012 PLUMBING - INTERMEDIATE Not ready for Inspection IVRS - Inspection :*
03/01/2012 PLUMBING - INTERMEDIATE Partial Approval IVRS - Inspection :*
1) 4TH FLOOR NORTH WING TO CORRIDOR-DWV OK AND PEX OK
02/06/2012 PLUMBING - INTERMEDIATE Partial Approval IVRS - Inspection :*
1) WATER 1ST TO 3RD FLOOR PRESSURIZED
01/18/2012 PLUMBING - INTERMEDIATE Partial Approval IVRS - Inspection :*
1) 3RD FLOOR EAST WING OK
01/11/2012 PLUMBING - INTERMEDIATE Partial Approval IVRS - Inspection :*
1) 3RD FLOOR NORTH WING OK
12/23/2011 PLUMBING - INTERMEDIATE Partial Approval IVRS - Inspection :*
1) 2ND & 3RD FLOOR DWV OK PEX OK
OK TO INSULATE HOT & RETURN
NEED TO SEE FLANGES
12/07/2011 PLUMBING - INTERMEDIATE Partial Approval IVRS - Inspection :*
1) 2ND FLOOR BEGIN TEST IN PVC DWV AND BEGIN TESTING ROOF DRAINS
2) DON'T FORGET RISER CLAMPS AND MID STORY GUIDES
12/02/2011 PLUMBING - INTERMEDIATE Not ready for Inspection IVRS - Inspection :*
11/23/2011 PLUMBING - INTERMEDIATE Partial Approval IVRS - Inspection :*
11/18/2011 PLUMBING - INTERMEDIATE Partial Approval IVRS - Inspection :*
1) DWV WATER TEST THRU REVENT ON 2ND LEVEL TO 10'
WATER DIST. 1ST LEVEL ONLY . ROOMS 101 THRU 108 INCLUDING ROOMS WEST OF THIS. RAIN DRAINAGE TO 10' 2ND LEVEL WATER TEST. (03037) SAME AREA
11/15/2011 PLUMBING - INTERMEDIATE Partial Approval IVRS - Inspection :*
11/14/2011 PLUMBING - INTERMEDIATE Partial Approval IVRS - Inspection :*
1) RAIN WATER LEADERS TAHT PASS UNDERGROUND TO HAVE CLEANOUT AT BASE OF VERTICAL RISER
2) JOB SITE TO WET FOR INSPECTION
3) ALL HOT AND HOT RECIRC PIPING TO BE INSULATED PER SPEC BOOK
11/07/2011 PLUMBING - INTERMEDIATE Not ready for Inspection IVRS - Inspection :*
1) CAP OFF ALL OPEN PIPING
2) UNABLE TO LOCATE APPROVED PLAN