Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Inspection History Details
Inspection Status: Approved
Inspection History: PLUMBING - INTERMEDIATE
Permit Number - T11CM00617
Inspection Description - PLUMBING - INTERMEDIATE
Inspection Status - Approved
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/05/2012 | PLUMBING - INTERMEDIATE | Approved | IVRS - Inspection :* | |
| 06/28/2012 | PLUMBING - INTERMEDIATE | Partial Approval | IVRS - Inspection :* | |
| 06/15/2012 | PLUMBING - INTERMEDIATE | Partial Approval | 1. First floor office restroom flange not set. 2. Fourth floor corridor strap CPVC. | |
| 06/06/2012 | PLUMBING - INTERMEDIATE | Partial Approval | IVRS - Inspection :* | |
| 06/05/2012 | PLUMBING - INTERMEDIATE | Partial Approval | IVRS - Inspection :* 5TH FLOOR NORTH WING EXCLUDE ROOM 510 6TH FLOOR NORTH WING EXCLUDE ROOM 608 EAST WING NOT READY 5TH FLOOR |
|
| 05/08/2012 | PLUMBING - INTERMEDIATE | Partial Approval | IVRS - Inspection :* 1) 3RD AND 4TH FLOOR FLANGES OK |
|
| 05/03/2012 | PLUMBING - INTERMEDIATE | Partial Approval | IVRS - Inspection :* 1) 3RD AND 4TH FLOOR CLOSET FLANGES THAT HAD BROKEN TEST CAPS, REQUIRES CORRECTIONS. THE PIPE IS TO EXTEND THE TOP FACE OF THE FLANGE |
|
| 04/18/2012 | PLUMBING - INTERMEDIATE | Partial Approval | IVRS - Inspection :* FIRST FLOOR FLANGES OK |
|
| 04/17/2012 | PLUMBING - INTERMEDIATE | Not ready for Inspection | IVRS - Inspection :* | |
| 04/11/2012 | PLUMBING - INTERMEDIATE | Not ready for Inspection | IVRS - Inspection :* | |
| 04/10/2012 | PLUMBING - INTERMEDIATE | Not ready for Inspection | IVRS - Inspection :* 1) 3" MULLER FLANGES NOT LISTED FOR INSIDE PIPE 2) 4" FLANGES (AND ALL FITTINGS) REQUIRE FULL MAKE UP WITH NO FOULING LEDGES |
|
| 03/26/2012 | PLUMBING - INTERMEDIATE | Partial Approval | IVRS - Inspection :* 1) 6TH FLOOR PEX AND PVC OK |
|
| 03/07/2012 | PLUMBING - INTERMEDIATE | Partial Approval | IVRS - Inspection :* 1) 4TH AND 5TH FLOOR PEX OK |
|
| 03/05/2012 | PLUMBING - INTERMEDIATE | Partial Approval | IVRS - Inspection :* 1) 4TH & 5TH FLOOR PVC DWV WATER TEST OK 2) 4TH FLOOR WATER PIPING NORTH BLDG OK |
|
| 03/02/2012 | PLUMBING - INTERMEDIATE | Not ready for Inspection | IVRS - Inspection :* | |
| 03/01/2012 | PLUMBING - INTERMEDIATE | Partial Approval | IVRS - Inspection :* 1) 4TH FLOOR NORTH WING TO CORRIDOR-DWV OK AND PEX OK |
|
| 02/06/2012 | PLUMBING - INTERMEDIATE | Partial Approval | IVRS - Inspection :* 1) WATER 1ST TO 3RD FLOOR PRESSURIZED |
|
| 01/18/2012 | PLUMBING - INTERMEDIATE | Partial Approval | IVRS - Inspection :* 1) 3RD FLOOR EAST WING OK |
|
| 01/11/2012 | PLUMBING - INTERMEDIATE | Partial Approval | IVRS - Inspection :* 1) 3RD FLOOR NORTH WING OK |
|
| 12/23/2011 | PLUMBING - INTERMEDIATE | Partial Approval | IVRS - Inspection :* 1) 2ND & 3RD FLOOR DWV OK PEX OK OK TO INSULATE HOT & RETURN NEED TO SEE FLANGES |
|
| 12/07/2011 | PLUMBING - INTERMEDIATE | Partial Approval | IVRS - Inspection :* 1) 2ND FLOOR BEGIN TEST IN PVC DWV AND BEGIN TESTING ROOF DRAINS 2) DON'T FORGET RISER CLAMPS AND MID STORY GUIDES |
|
| 12/02/2011 | PLUMBING - INTERMEDIATE | Not ready for Inspection | IVRS - Inspection :* | |
| 11/23/2011 | PLUMBING - INTERMEDIATE | Partial Approval | IVRS - Inspection :* | |
| 11/18/2011 | PLUMBING - INTERMEDIATE | Partial Approval | IVRS - Inspection :* 1) DWV WATER TEST THRU REVENT ON 2ND LEVEL TO 10' WATER DIST. 1ST LEVEL ONLY . ROOMS 101 THRU 108 INCLUDING ROOMS WEST OF THIS. RAIN DRAINAGE TO 10' 2ND LEVEL WATER TEST. (03037) SAME AREA |
|
| 11/15/2011 | PLUMBING - INTERMEDIATE | Partial Approval | IVRS - Inspection :* | |
| 11/14/2011 | PLUMBING - INTERMEDIATE | Partial Approval | IVRS - Inspection :* 1) RAIN WATER LEADERS TAHT PASS UNDERGROUND TO HAVE CLEANOUT AT BASE OF VERTICAL RISER 2) JOB SITE TO WET FOR INSPECTION 3) ALL HOT AND HOT RECIRC PIPING TO BE INSULATED PER SPEC BOOK |
|
| 11/07/2011 | PLUMBING - INTERMEDIATE | Not ready for Inspection | IVRS - Inspection :* 1) CAP OFF ALL OPEN PIPING 2) UNABLE TO LOCATE APPROVED PLAN |