Permit: T10CM03525
Permit Details
Apply Date:
12/21/2010
Applicant:
N/A
Description:
NEW CLASSROOM
Architects:
- BOLLARD, MARK EDWARD
Contractors:
- CORE CONSTRUCTION SERVICES OF AZ *C*
Permit Reviews
Permit Number - T10CM03525
Permit Status: C of o
Permit Description: NEW CLASSROOM
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/21/2011 | RESUBMITTAL - SITE | 02/22/2011 | COMPLETED |
| 01/21/2011 | RESUBMITTAL | 02/11/2011 | COMPLETED |
| 02/11/2011 | RESUBMITTAL | 02/17/2011 | COMPLETED |
| 02/17/2011 | RESUBMITTAL | 02/22/2011 | COMPLETED |
| 12/21/2010 | PLANS OK TO SUBMIT - COMM | 12/21/2010 | COMPLETED |
| 12/21/2010 | PLANS OK TO SUBMIT - SITE | 12/21/2010 | COMPLETED |
| 12/21/2010 | COMMERCIAL - NEW | 01/14/2011 | COMPLETED |
| 12/21/2010 | SITE | 01/14/2011 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T10CM03525
Permit Status: C of o
Permit Description: NEW CLASSROOM
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 12/21/2010 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T10CM03525
Permit Description: NEW CLASSROOM
Total Completed Inspections - 46
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/02/2011 | ELECTRIC - UFER | DSANTACR | Approved | IVRS - Inspection :* |
| 06/06/2011 | PLUMBING - PRE SLAB | RMYERS | Approved | IVRS - Inspection :* OKAY FOR CONCRETE STOI |
| 09/22/2011 | PLUMBING - GAS PRESSURE TEST | RMYERS | Approved | |
| 09/27/2011 | ROOF NAILING | AQUIROZ | Approved | IVRS - Inspection :* |
| 10/12/2011 | FRAMING | AQUIROZ | Approved | IVRS - Inspection :* |
| 10/24/2011 | STUCCO MESH | MHENSON | Approved | IVRS - Inspection :* |
| 11/04/2011 | SHEET ROCK NAILING | AQUIROZ | Approved | IVRS - Inspection :* |
| 11/09/2011 | BUILDING - PROGRESS | AQUIROZ | Approved | IVRS - Inspection :* |
| 11/15/2011 | PLUMBING - GAS PRESS TEST FNL | RMYERS | Approved | IVRS - Inspection :* 1) IN THE FUTURE USE 100 POUND GAUGE IN ONE POUND INCREMENTATION 2) CANNOT MEDIUM PRESSURE REGULATOR 3) BLDG INSPECTOR WILL LEAVE GAS CARD AFTER YOU PASS BLDG FINAL |
| 11/17/2011 | MECHANICAL - ABOVE CEILING | JMILITEL | Approved | IVRS - Inspection :* |
| 12/02/2011 | EXCAVATION/LAYOUT REBAR & ZON | MHENSON | Approved | IVRS - Inspection :* 1) LAST SITE WALL FOOTING |
| 12/07/2011 | PLUMBING - ROUGH, SOIL | RMYERS | Approved | IVRS - Inspection :* |
| 12/07/2011 | PLUMBING - BACK WATER VALVE | RMYERS | Approved | IVRS - Inspection :* |
| 12/07/2011 | PLUMBING - ABOVE CEILING | RMYERS | Approved | IVRS - Inspection :* |
| 12/07/2011 | PLUMBING - INTERMEDIATE | RMYERS | Approved | IVRS - Inspection :* |
| 12/09/2011 | U VALUE FOR WINDOW | AQUIROZ | Approved | IVRS - Inspection :* |
| 12/09/2011 | BUILDING ABOVE CEILING | AQUIROZ | Approved | IVRS - Inspection :* |
| 12/12/2011 | MECHANICAL - HOODS | JMILITEL | Approved | IVRS - Inspection :* |
| 12/12/2011 | MECHANICAL - INTERMEDIATE | JMILITEL | Approved | IVRS - Inspection :* |
| 12/12/2011 | MECHANICAL - HYDRONIC PIPING | JMILITEL | Approved | IVRS - Inspection :* |
| 12/12/2011 | REINFORCED MASONRY PRE-GROUT | MHENSON | Approved | IVRS - Inspection :* |
| 12/12/2011 | STEM WALL/RETAINING WALL | MHENSON | Approved | IVRS - Inspection :* |
| 12/12/2011 | PLUMBING - FINAL | RMYERS | Approved | IVRS - Inspection :* |
| 12/12/2011 | SITE - SEWER | RMYERS | Approved | IVRS - Inspection :* |
| 12/12/2011 | PLUMBING - PROGRESS | RMYERS | Approved | IVRS - Inspection :* |
| 12/13/2011 | BUILDING PRE-SLAB | AQUIROZ | Approved | IVRS - Inspection :* |
| 12/14/2011 | FIRE - FINAL | WMOTTO | Approved | |
| 12/14/2011 | FIRE - ALARM FINAL | WMOTTO | Approved | |
| 12/14/2011 | FIRE SPKLR - FINAL | WMOTTO | Approved | |
| 12/14/2011 | FIRE SPKLR - OH PIPING & HYDRO | WMOTTO | Approved | |
| 12/14/2011 | FIRE SPKLR - UG PIPING FLUSH | WMOTTO | Approved | |
| 12/14/2011 | FIRE SPKLR - UG, PIPING, HYDRO | WMOTTO | Approved | |
| 12/14/2011 | RIGHT OF WAY - FINAL | P.Whiddon | Approved | |
| 12/15/2011 | NPPO - FINAL | MRUSSO | Approved | |
| 12/15/2011 | SIGN - FINAL | MRUSSO | Approved | |
| 12/15/2011 | LANDSCAPE - FINAL | MRUSSO | Approved | |
| 12/15/2011 | ENGINEERING - FINAL | MRUSSO | Approved | COMPLETE ALL SITE WORK PER YOUR APPROVED SITE/GRADING PLAN. FINAL YOUR GRADING PERMIT #T10BU01890 |
| 12/16/2011 | MECHANICAL - FINAL | MRAMBER | Approved | IVRS - Inspection :* 1) AIR HANDLER AT ELEVATOR EQUIPMENT ROOM HAS LINE SETS NOT PROPERLY INSULATED |
| 12/19/2011 | BUILDING - FINAL | AQUIROZ | Approved | IVRS - Inspection :* 1) OK TEMP C OF O |
| 12/22/2011 | ELECTRIC - FINAL | RHOLLAND | Approved | IVRS - Inspection :* |
| 12/22/2011 | ELECTRIC - OUTDOOR LIGHTING | RHOLLAND | Approved | IVRS - Inspection :* |
| 12/22/2011 | ELECTRIC - PROGRESS | RHOLLAND | Approved | IVRS - Inspection :* |
| 12/22/2011 | ELECTRIC - ABOVE CEILING | RHOLLAND | Approved | IVRS - Inspection :* |
| 12/22/2011 | ELECTRIC - INTERMEDIATE | RHOLLAND | Approved | IVRS - Inspection :* |
| 12/22/2011 | ELECTRIC - UNDERGROUND | RHOLLAND | Approved | IVRS - Inspection :* |
| 12/30/2011 | PLUMBING - YARD WTR LINE/TEST | LHANLY | Approved |