Permit: T10CM01987
Permit Details
Apply Date:
07/16/2010
Applicant:
N/A
Description:
NEW RETAIL BUILDING
Architects:
- ACORN, KIM BRIAN
Contractors:
- CORNERSTONE HOMES LLC
Permit Reviews
Permit Number - T10CM01987
Permit Status: C of o
Permit Description: NEW RETAIL BUILDING
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 04/07/2011 | REVISION - - 1ST | 04/07/2011 | COMPLETED |
| 04/18/2011 | REVISION - SITE | 04/29/2011 | COMPLETED |
| 04/29/2011 | REVISION - SITE | 05/20/2011 | COMPLETED |
| 05/20/2011 | REVISION - - 1ST | 06/06/2011 | COMPLETED |
| 05/23/2011 | 3RD PARTY REVIEW - REVISION/OTHER | 06/06/2011 | COMPLETED |
| 07/16/2010 | PLANS OK TO SUBMIT - SITE | 07/16/2010 | COMPLETED |
| 07/16/2010 | SITE | 08/11/2010 | COMPLETED |
| 08/10/2011 | REVISION - SITE | 08/30/2011 | COMPLETED |
| 08/24/2010 | PLANS OK TO SUBMIT - 3RD PARTY | 08/24/2010 | COMPLETED |
| 08/24/2010 | RESUBMITTAL - SITE ALL | 09/22/2010 | COMPLETED |
| 08/24/2010 | 3RD PARTY REVIEW-COMMERCIAL | 11/08/2010 | COMPLETED |
| 08/30/2011 | REVISION - SITE | 08/30/2011 | COMPLETED |
| 08/30/2011 | RESUBMITTAL - SITE | 09/14/2011 | COMPLETED |
| 09/29/2011 | REVISION - - 1ST | 10/03/2011 | COMPLETED |
| 10/07/2011 | REVISION - SITE | 10/07/2011 | COMPLETED |
| 11/08/2010 | POST 3RD PARTY REVIEW | 12/14/2010 | COMPLETED |
| 11/18/2010 | RESUBMITTAL - SITE ALL | 11/22/2010 | COMPLETED |
| 11/22/2010 | RESUBMITTAL - SITE ALL | 01/07/2011 | COMPLETED |
| 12/14/2010 | RESUBMITTAL | 12/29/2010 | COMPLETED |
| 12/29/2010 | RESUBMITTAL | 01/28/2011 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T10CM01987
Permit Status: C of o
Permit Description: NEW RETAIL BUILDING
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 07/16/2010 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T10CM01987
Permit Description: NEW RETAIL BUILDING
Total Completed Inspections - 41
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/04/2011 | ELECTRIC - UFER | JBURGE | Approved | IVRS - Inspection :* |
| 04/22/2011 | PLUMBING - YARD WTR LINE/TEST | BBENEDON | Approved | IVRS - Inspection :* |
| 04/27/2011 | PLUMBING - SEWER HCS CONNECT | BBENEDON | Approved | IVRS - Inspection :* |
| 04/29/2011 | PLUMBING - PRE SLAB | RMYERS | Approved | IVRS - Inspection :* |
| 04/29/2011 | BUILDING PRE-SLAB | JBURGE | Approved | IVRS - Inspection :* |
| 05/24/2011 | ROOF NAILING | JBURGE | Approved | IVRS - Inspection :* 1) OK TO DRY IN; TRUSSES IN PLACE; CRICKET INCORPORATED IN TRUSS SYSTEM |
| 06/01/2011 | ELECTRIC - CABLE DROP | RMORENO | Approved | IVRS - Inspection :* |
| 06/02/2011 | TEP CLEARANCE - AM | JWEATHER | Approved | INCR CLEARED PER R. MORENO |
| 06/16/2011 | FIRE SPKLR - UG, PIPING, HYDRO | WMOTTO | Approved | |
| 06/16/2011 | FIREWALL/FIREBARRIER/FIRESTOP | AQUIROZ | Approved | IVRS - Inspection :* |
| 06/16/2011 | FRAMING | AQUIROZ | Approved | IVRS - Inspection :* |
| 06/16/2011 | ELECTRIC - INTERMEDIATE | RMORENO | Approved | IVRS - Inspection :* |
| 06/20/2011 | PLUMBING - INTERMEDIATE | BBENEDON | Approved | IVRS - Inspection :* |
| 06/21/2011 | PLUMBING - ROUGH, SOIL | BBENEDON | Approved | IVRS - Inspection :* |
| 06/22/2011 | SITE - SEWER | BBENEDON | Approved | IVRS - Inspection :* |
| 06/27/2011 | SHEET ROCK NAILING | JBURGE | Approved | IVRS - Inspection :* 1) OK TO TAPE THROUGHOUT |
| 06/29/2011 | STUCCO MESH | JBURGE | Approved | IVRS - Inspection :* |
| 09/14/2011 | REINFORCED MASONRY PRE-GROUT | JBURGE | Approved | IVRS - Inspection :* |
| 09/20/2011 | PLUMBING - ABOVE CEILING | BBENEDON | Approved | IVRS - Inspection :* |
| 09/21/2011 | PLUMBING - ROOF DRAINS | BBENEDON | Approved | IVRS - Inspection :* |
| 09/28/2011 | FIRE SPKLR - FINAL | WMOTTO | Approved | |
| 10/05/2011 | MECHANICAL - FINAL | JMILITEL | Approved | IVRS - Inspection :* |
| 10/05/2011 | MECHANICAL - ABOVE CEILING | JMILITEL | Approved | IVRS - Inspection :* |
| 10/05/2011 | MECHANICAL - INTERMEDIATE | JMILITEL | Approved | IVRS - Inspection :* |
| 10/05/2011 | ELECTRIC - OUTDOOR LIGHTING | RMORENO | Approved | |
| 10/05/2011 | OUTDOOR LIGHTING FINAL | RMORENO | Approved | |
| 10/05/2011 | PLUMBING - FINAL | BBENEDON | Approved | IVRS - Inspection :* |
| 10/05/2011 | FIRE - FINAL | DSIWARSKI | Approved | |
| 10/05/2011 | RIGHT OF WAY - FINAL | P.Whiddon | Approved | |
| 10/05/2011 | ELECTRIC - FINAL | RMORENO | Approved | IVRS - Inspection :* |
| 10/06/2011 | ZONING - FINAL | DROBERTS | Approved | |
| 10/11/2011 | ENGINEERING - FINAL | DROBERTS | Approved | |
| 10/11/2011 | CERTIFICATE OF OCCUPANCY | JBURGE | Approved | |
| 10/11/2011 | BUILDING - PROGRESS | JBURGE | Approved | |
| 10/11/2011 | STEM WALL/RETAINING WALL | JBURGE | Approved | |
| 10/11/2011 | EXCAVATION/LAYOUT REBAR & ZON | JBURGE | Approved | |
| 10/11/2011 | BUILDING - FINAL | JBURGE | Approved | |
| 10/11/2011 | ENGINEERING - FINAL | MRUSSO | Approved | 1) INSTALL BIKE PARKING SHOWN ON APPROVED PLAN. 2) INSTALL "ROLL-ASIDE" DECORATIVE GATE W/ METAL SLATS AS SHOWN ON APPROVED PLANS CALL FOR RE-INSPECTION |
| 10/11/2011 | LANDSCAPE - FINAL | MRUSSO | Approved | |
| 10/11/2011 | NPPO - FINAL | MRUSSO | Approved | |
| 10/11/2011 | SIGN - FINAL | MRUSSO | Approved |