Permit: T10CM00440
Permit Details
Apply Date:
02/23/2010
Applicant:
N/A
Description:
TI:WAREHOUSE
Contractors:
- WILLMENG CONSTRUCTION INC
Permit Reviews
Permit Number - T10CM00440
Permit Status: C of o
Permit Description: TI:WAREHOUSE
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
02/23/2010 | COMMERCIAL TI | 03/04/2010 | COMPLETED |
03/04/2010 | RESUBMITTAL | 03/05/2010 | COMPLETED |
03/05/2010 | RESUBMITTAL | 03/29/2010 | COMPLETED |
04/05/2010 | REVISION - - 1ST | 04/08/2010 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T10CM00440
Permit Status: C of o
Permit Description: TI:WAREHOUSE
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
02/23/2010 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T10CM00440
Permit Description: TI:WAREHOUSE
Total Completed Inspections - 31
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
04/09/2010 | PLUMBING - PRE SLAB | RLEDONNE | Approved | IVRS - Inspection :* |
04/09/2010 | ROOF NAILING | MHENSON | Approved | IVRS - Inspection :* |
04/23/2010 | MECHANICAL - ABOVE CEILING | JMILITEL | Approved | IVRS - Inspection :* 1) SHOW HOW EXHAUST FANS WILL RUN CONTINOUSLY |
04/23/2010 | SHEET ROCK NAILING | MHENSON | Approved | IVRS - Inspection :* 1) CANCELLED PER CONTRACTOR |
04/23/2010 | SHEET ROCK NAILING | MHENSON | Approved | IVRS - Inspection :* 1) MONEY ORDER #262948 FOR $150.00 2) INTERIOR WALLS OK |
04/23/2010 | FRAMING | MHENSON | Approved | IVRS - Inspection :* |
04/27/2010 | SIGN - FINAL | JYBARRA | Approved | NO SIGN AT THIS TIME |
04/27/2010 | NPPO - FINAL | MCARREON | Approved | |
04/27/2010 | LANDSCAPE - FINAL | MCARREON | Approved | |
04/27/2010 | ENGINEERING - FINAL | MCARREON | Approved | |
04/27/2010 | RIGHT OF WAY - FINAL | LLopez | Approved | |
04/28/2010 | ELECTRIC - UNDERGROUND | RHOLLAND | Approved | IVRS - Inspection :* |
04/28/2010 | ELECTRIC - UFER | RHOLLAND | Approved | IVRS - Inspection :* |
04/29/2010 | FIRE SPKLR - FINAL | DSIWARSKI | Approved | Approved |
04/29/2010 | PLUMBING - INTERMEDIATE | RLEDONNE | Approved | IVRS - Inspection :* |
04/29/2010 | TEP CLEARANCE - AM | JWEATHER | Approved | TMPP CLEARED FOR #156 PER R. HOLLANDER |
05/03/2010 | MECHANICAL - INTERMEDIATE | MRAMBER | Approved | IVRS - Inspection :* |
05/03/2010 | MECHANICAL - FINAL | MRAMBER | Approved | IVRS - Inspection :* |
05/04/2010 | ELECTRIC - FINAL | RHOLLAND | Approved | IVRS - Inspection :* |
05/04/2010 | ELECTRIC - PROGRESS | RHOLLAND | Approved | IVRS - Inspection :* |
05/04/2010 | ELECTRIC - TEMP POWER FOR TEST | RHOLLAND | Approved | IVRS - Inspection :* |
05/04/2010 | ELECTRIC - TEMPORARY SERVICE | RHOLLAND | Approved | IVRS - Inspection :* |
05/04/2010 | ELECTRIC - ABOVE CEILING | RHOLLAND | Approved | IVRS - Inspection :* |
05/04/2010 | ELECTRIC - INTERMEDIATE | RHOLLAND | Approved | IVRS - Inspection :* |
05/04/2010 | FIRE - FINAL | DSIWARSKI | Approved | Approved |
05/05/2010 | BUILDING - FINAL | MHENSON | Approved | IVRS - Inspection :* |
05/05/2010 | BUILDING ABOVE CEILING | MHENSON | Approved | IVRS - Inspection :* |
05/05/2010 | PLUMBING - FINAL | RLEDONNE | Approved | IVRS - Inspection :* |
05/05/2010 | PLUMBING - ROUGH, SOIL | RLEDONNE | Approved | IVRS - Inspection :* |
05/05/2010 | PLUMBING - PROGRESS | RLEDONNE | Approved | IVRS - Inspection :* |
05/05/2010 | PLUMBING - ABOVE CEILING | RLEDONNE | Approved | IVRS - Inspection :* |