Permit Details

Status:
C of o
Type:
COMMERCIAL NEW
Apply Date:
04/30/2008
Applicant:
N/A
Description:
NEW RED LOBSTER RESTAURANT
Contractors:
  • SELECT BUILDERS

Permit Reviews

Permit Number - T08CM01385
Permit Status: C of o
Permit Description: NEW RED LOBSTER RESTAURANT
Start Date Submittal Complete Date Status  
03/18/2009 3RD PARTY REVIEW-REVISION/OTHER 03/19/2009 COMPLETED Review Details
03/24/2009 SITE 04/28/2009 COMPLETED Review Details
04/02/2009 3RD PARTY REVIEW-REVISION/OTHER 04/02/2009 COMPLETED Review Details
04/06/2009 REVISION - - 1ST 04/08/2009 COMPLETED Review Details
04/07/2009 REVISION - - 2ND 04/08/2009 COMPLETED Review Details
04/30/2008 PLANS OK TO SUBMIT - 3RD PARTY 04/30/2008 COMPLETED Review Details
04/30/2008 3RD PARTY REVIEW-COMMERCIAL 09/23/2008 COMPLETED Review Details
07/22/2009 REVISION - - 3RD 07/22/2009 COMPLETED Review Details
07/22/2009 RESUBMITTAL - SITE ALL 08/03/2009 COMPLETED Review Details
07/29/2008 OTHER 09/23/2008 COMPLETED Review Details
09/23/2008 POST 3RD PARTY REVIEW 09/30/2008 COMPLETED Review Details
09/30/2008 3RD PARTY REVIEW-COMMERCIAL TI 11/03/2008 COMPLETED Review Details
11/03/2008 POST 3RD PARTY REVIEW 12/03/2008 COMPLETED Review Details
12/05/2008 POST 3RD PARTY REVIEW 01/15/2009 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T08CM01385
Permit Status: C of o
Permit Description: NEW RED LOBSTER RESTAURANT
Total Outstanding Activity Conditions - 1
Date Name
04/30/2008 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: C of o
Permit Number: T08CM01385
Permit Description: NEW RED LOBSTER RESTAURANT
Total Completed Inspections - 47
Date Description Inspector Results Comments
03/05/2009 ELECTRIC - UFER DSANTACR Approved IVRS - Inspection :*
03/23/2009 FIRE SPKLR - UG, PIPING, HYDRO LTHOMAS Approved
03/31/2009 PLUMBING - PRE SLAB RLEDONNE Approved IVRS - Inspection :*
04/15/2009 EXT METAL CLIPS/EXT SHEATHING MHENSON Approved IVRS - Inspection :*
1. SW AND HOLD DOWNS
2. ALSO SPECIAL INSPECTED
04/17/2009 PLUMBING - SEWER HCS CONNECT RLEDONNE Approved IVRS - Inspection :*
05/01/2009 ROOF NAILING MHENSON Approved IVRS - Inspection :*
05/06/2009 REINFORCED MASONRY PRE-GROUT MHENSON Approved IVRS - Inspection :*
TOP LIFT LOADING AREA
05/19/2009 PLUMBING - ROUGH, SOIL RLEDONNE Approved IVRS - Inspection :*
05/22/2009 FRAMING MHENSON Approved IVRS - Inspection :*
HAT CHANNEL HARD LIDS COMPLETE
06/05/2009 STUCCO MESH AQUIROZ Approved IVRS - Inspection :*
06/15/2009 BUILDING PRE-SLAB MHENSON Approved IVRS - Inspection :*
EPOXIED SLAB REBAR SPECIAL INSPECTED
06/19/2009 EXCAVATION/LAYOUT REBAR & ZON MHENSON Approved IVRS - Inspection :*
1) FLAG POLE CASSION
07/01/2009 BUILDING ABOVE CEILING MHENSON Approved IVRS - Inspection :*
07/02/2009 TEP CLEARANCE - AM JWEATHER Approved TEC CLEARED PER R. JIROUDEK
07/07/2009 MECHANICAL - ABOVE CEILING MRAMBER Approved IVRS - Inspection :*
1) OK GAS TILES IN KITCHEN AREA
07/09/2009 SHEET ROCK NAILING MHENSON Approved IVRS - Inspection :*
07/10/2009 PLUMBING - GAS PRESS TEST FNL RLEDONNE Approved IVRS - Inspection :*
07/13/2009 PLUMBING - INTERMEDIATE RLEDONNE Approved IVRS - Inspection :*
1) INSTALLED PER APPROVED PLANS
07/17/2009 RIGHT OF WAY - FINAL LLOPEZ Approved PER EMAIL
07/23/2009 BUILDING - PROGRESS MHENSON Approved IVRS - Inspection :*
07/23/2009 SIGN - FINAL JYBARRA Approved
07/23/2009 NPPO - FINAL ACONNOR Approved
07/23/2009 LANDSCAPE - FINAL ACONNOR Approved
07/24/2009 FIRE SPKLR - FINAL LTHOMAS Approved
07/24/2009 ELECTRIC - FINAL RHOLLAND Approved IVRS - Inspection :*
1) SUPPORT VDV CABELING 725.24 AND 300.11 6' INTERVALS UP OFF OF GRID AND INDEPENDENT
07/24/2009 ELECTRIC - PROGRESS RHOLLAND Approved IVRS - Inspection :*
07/24/2009 ELECTRIC - ABOVE CEILING RHOLLAND Approved IVRS - Inspection :*
07/24/2009 ELECTRIC - INTERMEDIATE RHOLLAND Approved IVRS - Inspection :*
07/24/2009 ELECTRIC - UNDERGROUND RHOLLAND Approved IVRS - Inspection :*
07/27/2009 FIRE - ALARM FINAL LTHOMAS Approved
07/28/2009 PLUMBING - FINAL RLEDONNE Approved IVRS - Inspection :*
07/28/2009 PLUMBING - PROGRESS RLEDONNE Approved IVRS - Inspection :*
07/28/2009 PLUMBING - GAS PRESSURE TEST RLEDONNE Approved IVRS - Inspection :*
07/28/2009 PLUMBING - ROOF DRAINS RLEDONNE Approved IVRS - Inspection :*
07/28/2009 PLUMBING - ABOVE CEILING RLEDONNE Approved IVRS - Inspection :*
07/30/2009 MECHANICAL - PROGRESS MRAMBER Approved IVRS - Inspection :*
07/30/2009 MECHANICAL - INTERMEDIATE MRAMBER Approved IVRS - Inspection :*
07/30/2009 MECHANICAL - HOOD SYSTEMS MRAMBER Approved IVRS - Inspection :*
07/30/2009 MECHANICAL - HOODS MRAMBER Approved IVRS - Inspection :*
07/31/2009 MECHANICAL - FINAL MRAMBER Approved IVRS - Inspection :*
07/31/2009 ENGINEERING - FINAL DROBERTS Approved SITE IS READY AT THIS TIME, MINOR CHANGES TO THE SOUTHSIDE PARKING LOT CAN BE EXPECTED WHEN THE ADJACENT SITE IS DEVELOPED.
08/03/2009 PLUMBING - YARD WTR LINE/TEST RLEDONNE Approved
08/03/2009 FIRE - FINAL DRAMIREZ Approved
08/03/2009 STEM WALL/RETAINING WALL MHENSON Approved
08/03/2009 FIRE - KITCHEN EXH HOOD FINAL DRAMIREZ Approved
08/03/2009 BUILDING - FINAL MHENSON Approved
08/06/2009 HEALTH DEPT - FINAL 724-7908 LGERINGER Approved