Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T08CM00764
Permit Details
Apply Date:
03/07/2008
Applicant:
REX, CATHERINE APPLEGATE
Description:
PUBLIC HIGH SCHOOL
Contractors:
- STREAMLINE UNLIMITED L L C
Permit Reviews
Permit Number - T08CM00764
Permit Status: C of o
Permit Description: PUBLIC HIGH SCHOOL
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 03/07/2008 | COMMERCIAL TI | 03/14/2008 | COMPLETED |
| 03/14/2008 | COMMERCIAL TI | 04/08/2008 | COMPLETED |
| 04/08/2008 | COMMERCIAL TI | 04/24/2008 | COMPLETED |
| 04/24/2008 | OTHER | 04/25/2008 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T08CM00764
Permit Status: C of o
Permit Description: PUBLIC HIGH SCHOOL
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 03/07/2008 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T08CM00764
Permit Description: PUBLIC HIGH SCHOOL
Total Completed Inspections - 22
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/23/2008 | ELECTRIC - SERVICE UPGRADE | DSANTACR | Approved | IVRS - Inspection :* |
| 05/27/2008 | TEP CLEARANCE - AM | JWEATHER | Approved | INCR CLEARED PER D. SANTACRUZ |
| 09/05/2008 | FRAMING | AQUIROZ | Approved | IVRS - Inspection :* |
| 09/05/2008 | MECHANICAL - ABOVE CEILING | MRAMBER | Approved | IVRS - Inspection :* |
| 09/05/2008 | MECHANICAL - INTERMEDIATE | MRAMBER | Approved | IVRS - Inspection :* |
| 09/23/2008 | SHEET ROCK NAILING | AQUIROZ | Approved | IVRS - Inspection :* |
| 10/13/2008 | MECHANICAL - FINAL | MRAMBER | Approved | IVRS - Inspection : See detailed listing on site.| 999* 1. PROVIDE AIR BALANCE REPORT 2. PROVIDE ISOLATORS UNDER CONDENSOR UNITS PER DETAILS 3. ISOLATE COPPER REFRIGERATION LINES FROM GALVANIZED |
| 10/13/2008 | BUILDING - PROGRESS | AQUIROZ | Approved | IVRS - Inspection :* |
| 10/31/2008 | ELECTRIC - INTERMEDIATE | RHOLLAND | Approved | IVRS - Inspection :* |
| 11/07/2008 | ELECTRIC - FINAL | RHOLLAND | Approved | IVRS - Inspection :* 1. MAINTAIN WORKING CLEARANCE AT A/C DISCONNECT 2. FAN COIL CONDUCTOR TO SMALL FOR LOAD 3. FINISH #2 OLD INSPECTIONS |
| 11/07/2008 | ELECTRIC - ABOVE CEILING | RHOLLAND | Approved | IVRS - Inspection :* |
| 02/27/2009 | ELECTRIC - OUTDOOR LIGHTING | RJIROUDE | Approved | IVRS - Inspection :* |
| 07/31/2009 | RIGHT OF WAY - FINAL | MOTERO | Approved | PER EMAIL |
| 07/31/2009 | NPPO - FINAL | ACONNOR | Approved | |
| 07/31/2009 | LANDSCAPE - FINAL | ACONNOR | Approved | N/A |
| 07/31/2009 | SIGN - FINAL | JYBARRA | Approved | NO SIGN ON SITE |
| 08/05/2009 | FIRE - ALARM FINAL | DRAMIREZ | Approved | |
| 08/06/2009 | FIRE - FINAL | DRAMIREZ | Approved | |
| 08/07/2009 | BUILDING - FINAL | AQUIROZ | Approved | IVRS - Inspection :* 1) NEED TO ADDRESS ENGINEERING ISSUES |
| 08/28/2009 | ENGINEERING - FINAL | MRUSSO | Approved | |
| 08/28/2009 | ENGINEERING - FINAL | MRUSSO | Approved | PROVIDE AN APPROVED SITE PLAN THAT SHOWS WHAT WAS CONSTRUCTED - TEMP C OF O ONLY |
| 08/06/2010 | FIRE SPKLR - FINAL | LTHOMAS | Approved | SEE FIRE SPRINKLER PERMIT FINALED 9-3-2009 |