Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Permit Details

Status:
C of o
Type:
COMMERCIAL OTHER
Address NEW:
630 N ALVERNON WY #120
Apply Date:
01/25/2008
Applicant:
N/A
Description:
TI: OFFICE
Contractors:
  • EPSTEIN FENTON L L C ,

Permit Reviews

Permit Number - T08CM00262
Permit Status: C of o
Permit Description: TI: OFFICE
Start Date Submittal Complete Date Status  
01/25/2008 PLANS OK TO SUBMIT - COMM 01/31/2008 COMPLETED Review Details
01/31/2008 3RD PARTY REVIEW-COMMERCIAL TI 04/21/2008 COMPLETED Review Details
02/25/2009 3RD PARTY REVIEW-REVISION/OTHER 03/11/2009 COMPLETED Review Details
04/21/2008 POST 3RD PARTY REVIEW 05/16/2008 COMPLETED Review Details
05/13/2009 3RD PARTY REVIEW-REVISION/OTHER 05/26/2009 COMPLETED Review Details
05/26/2009 RESUBMITTAL 05/26/2009 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T08CM00262
Permit Status: C of o
Permit Description: TI: OFFICE
Total Outstanding Activity Conditions - 1
Date Name
01/25/2008 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: C of o
Permit Number: T08CM00262
Permit Description: TI: OFFICE
Total Completed Inspections - 17
Date Description Inspector Results Comments
07/15/2008 MECHANICAL - INTERMEDIATE MRAMBER Approved IVRS - Inspection :*
1. PROVIDE SPIN IN COLLARS PER PLANS
2. PROVIDE DAMPERS PER PLANS
3. SEAL ALL DUCTS PER PLANS
09/18/2008 MECHANICAL - FINAL JMILITEL Approved IVRS - Inspection :*
OK FOR FINAL PHASE 3
10/07/2008 PLUMBING - INTERMEDIATE BBENEDON Approved IVRS - Inspection :*
10/21/2008 MECHANICAL - ABOVE CEILING JMILITEL Approved IVRS - Inspection :*
OK FOR CEILING TILES ROOM 120
10/21/2008 PLUMBING - ROUGH, SOIL RMYERS Approved IVRS - Inspection :*
ROOM 120 PHASE 4 PIPING CAPPED OFF BELOW FLOOR OK
PIPING CAPPED OFF ABOVE CEILING OK
10/21/2008 PLUMBING - ABOVE CEILING RMYERS Approved IVRS - Inspection :*
10/23/2008 ELECTRIC - INTERMEDIATE RJIROUDE Approved OK WALLS PROCESSING LAB PHASE IV ROOM 120
10/28/2008 BUILDING ABOVE CEILING JBURGE Approved IVRS - Inspection :*
ROOM #120 PHASE IV -- OK TO SET TILE
10/31/2008 PLUMBING - FINAL BBENEDON Approved IVRS - Inspection :*
RM. 120 PAS #4 FIXTURES OK
11/03/2008 ELECTRIC - FINAL DSANTACR Approved IVRS - Inspection :*
OK PHASE 4 ROOM #120
11/03/2008 ELECTRIC - ABOVE CEILING DSANTACR Approved IVRS - Inspection :*
11/06/2008 BUILDING - FINAL JBURGE Approved IVRS - Inspection :*
PHASE IV -- ROOM #120
11/06/2008 FIRE - FINAL CSCHULTZ Approved Phase #4 room 120 Partial approval
11/06/2008 FIRE SPKLR - FINAL CSCHULTZ Approved Phase#4 room 120
Adjust sprinkler heads to 1 inch below drop ceciling
11/21/2008 FRAMING JBURGE Approved IVRS - Inspection :*
PHASE IV -- ROOM #121A -- OK TO SHEETROCK
12/11/2008 SHEET ROCK NAILING JBURGE Approved IVRS - Inspection :*
PHASE II; ROOM 121A & PONY WALL
OK TO TAPE PROGRESS AREAS
05/28/2009 PLUMBING - PRE SLAB BBENEDON Approved

Documents

File Name Document Type  
C OF O_05-29-2009.TIF CERT OF OCC VIEW
001__X1.TIF CONSTRPLANS VIEW
002__D1.TIF CONSTRPLANS VIEW
003__A1.TIF CONSTRPLANS VIEW
004__A2.TIF CONSTRPLANS VIEW
005__A3.TIF CONSTRPLANS VIEW
006__A4.TIF CONSTRPLANS VIEW
007__A5.TIF CONSTRPLANS VIEW
008__A6.TIF CONSTRPLANS VIEW
009__A7.TIF CONSTRPLANS VIEW
010__A8.TIF CONSTRPLANS VIEW
011__DM1.TIF CONSTRPLANS VIEW
012__MP0.TIF CONSTRPLANS VIEW
013__M1.TIF CONSTRPLANS VIEW
014__M2.TIF CONSTRPLANS VIEW
015__DP1.TIF CONSTRPLANS VIEW
016__DP2.TIF CONSTRPLANS VIEW
017__P1.TIF CONSTRPLANS VIEW
018__P2.TIF CONSTRPLANS VIEW
019__P3.TIF CONSTRPLANS VIEW
020__E1.TIF CONSTRPLANS VIEW
021__E2.TIF CONSTRPLANS VIEW
022__E3.TIF CONSTRPLANS VIEW
023__E4.TIF CONSTRPLANS VIEW
024__E5.TIF CONSTRPLANS VIEW
005_E6.TIF CONSTRPLANS VIEW
None DOCUMENTS VIEW