Inspection History Details
Inspection Status: Approved
Inspection History: PLUMBING - ROUGH, SOIL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/24/2009 | PLUMBING - ROUGH, SOIL | Approved | IVRS - Inspection :* | |
| 04/22/2009 | PLUMBING - ROUGH, SOIL | Not ready for Inspection | IVRS - Inspection :* | |
| 03/04/2009 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* LAB 121 AT COLS. 4/D |
|
| 01/09/2009 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* | |
| 10/21/2008 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* ROOM 120 PHASE 4 PIPING CAPPED OFF BELOW FLOOR OK PIPING CAPPED OFF ABOVE CEILING OK |
|
| 10/07/2008 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* RM. 120 OK |
|
| 08/19/2008 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* PHASE 3 IN WALLS, FLOOR AND DEMO OK |
|
| 07/23/2008 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* | |
| 07/22/2008 | PLUMBING - ROUGH, SOIL | Not ready for Inspection | IVRS - Inspection :* | |
| 07/10/2008 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* UNIT # ON PERMIT SHALL ACCURATELY REFLECT JOB DEMO IN 105 AND 109 OK |
|
| 05/22/2008 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* 1) PHASE I DEMO OK 2) PROCESSING ROOM 105 P-3 INWALL PIPING OK 3) PROVIDE NEW UNIT #120 NOT #200 |