Permit: T07CM03741
Permit Details
Status:
C of o
Type:
COMMERCIAL NEW
Address:
8317 S CAMINO DE CAFE
Address NEW:
8317 S CAMINO DE CAFE
Apply Date:
09/14/2007
Applicant:
THE BUILT ENVIRONMENT
Description:
NEW METAL BUILDING
Architects:
- HAMILTON, MATTHEW HALE
Contractors:
- BUNGER STEEL INC ,
Permit Reviews
Permit Number - T07CM03741
Permit Status: C of o
Permit Description: NEW METAL BUILDING
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/07/2008 | RESUBMITTAL | 01/31/2008 | COMPLETED |
| 06/12/2008 | REVISION - - 1ST | 06/17/2008 | COMPLETED |
| 06/17/2008 | REVISION - - 1ST | 06/19/2008 | COMPLETED |
| 06/24/2008 | REVISION - - 1ST | 06/24/2008 | COMPLETED |
| 09/14/2007 | PLANS OK TO SUBMIT - COMM | 09/18/2007 | COMPLETED |
| 09/18/2007 | COMMERCIAL NEW | 10/25/2007 | COMPLETED |
| 11/15/2007 | RESUBMITTAL | 12/14/2007 | COMPLETED |
| 12/20/2007 | RESUBMITTAL | 01/07/2008 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T07CM03741
Permit Status: C of o
Permit Description: NEW METAL BUILDING
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 09/14/2007 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T07CM03741
Permit Description: NEW METAL BUILDING
Total Completed Inspections - 35
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/21/2008 | PLUMBING - ROUGH, SOIL | RRICH | Approved | IVRS - Inspection :* APPROVED WATER TEST THRU BLD. TO 5' BLD. EXTERIOR PRIOR TO INSTALL OF SITE SEWER HAVE CONTRACTOR MAKE CONTACT WITH THIS INSPECTOR FOR REQUIREMENTS FOR VENT FOR BACKWATER VALVE INSTALL. |
| 03/12/2008 | BUILDING PRE-SLAB | GDABBS | Approved | IVRS - Inspection :* |
| 03/19/2008 | PLUMBING - PRE SLAB | RRICH | Approved | IVRS - Inspection :* |
| 03/27/2008 | PLUMBING - SEWER HCS CONNECT | RRICH | Approved | IVRS - Inspection :* |
| 04/03/2008 | PLUMBING - BACK WATER VALVE | RRICH | Approved | IVRS - Inspection :* |
| 04/25/2008 | ROOF NAILING | GDABBS | Approved | IVRS - Inspection :* |
| 05/07/2008 | PLUMBING - PROGRESS | RRICH | Approved | IVRS - Inspection :* |
| 05/07/2008 | PLUMBING - YARD WTR LINE/TEST | RRICH | Approved | IVRS - Inspection :* |
| 05/13/2008 | SHEET ROCK NAILING | GDABBS | Approved | IVRS - Inspection :* |
| 06/04/2008 | FIRE - HYDRANTS | DRAMIREZ | Approved | Approved 6/4/08 |
| 06/09/2008 | MECHANICAL - ABOVE CEILING | JMILITEL | Approved | IVRS - Inspection :* STRAP FIX UP OFF OF CONDENSATE PIPE OK FOR CEILING TILES |
| 06/24/2008 | RIGHT OF WAY - FINAL | MCASTRO | Approved | PER EMAIL |
| 06/24/2008 | ELECTRIC - OUTDOOR LIGHTING | RJIROUDE | Approved | |
| 06/24/2008 | SIGN - FINAL | JYBARRA | Approved | IVRS - Inspection :* |
| 06/24/2008 | ELECTRIC - CABLE DROP | RJIROUDE | Approved | IVRS - Inspection :* |
| 06/24/2008 | EXT METAL CLIPS/EXT SHEATHING | GDABBS | Approved | IVRS - Inspection :* |
| 06/24/2008 | ENGINEERING - FINAL | NKALAHAR | Approved | |
| 06/24/2008 | FIRE - FINAL | CSCHULTZ | Approved | |
| 06/25/2008 | TEP CLEARANCE - AM | JWEATHER | Approved | TEC CLEARED PER R. JIROUDEK |
| 06/25/2008 | NPPO - FINAL | ACONNOR | Approved | |
| 06/25/2008 | LANDSCAPE - FINAL | ACONNOR | Approved | |
| 07/01/2008 | MECHANICAL - FINAL | JMILITEL | Approved | IVRS - Inspection :* |
| 07/01/2008 | PLUMBING - INTERMEDIATE | RRICH | Approved | IVRS - Inspection :* |
| 07/02/2008 | ELECTRIC - FINAL | RJIROUDE | Approved | IVRS - Inspection :* AIR COMPRESSOR REMOVED WILL NEED TO PULL SEPARATE PERMIT FOR INSTALLING ANY NEW EQUIPMENT |
| 07/02/2008 | ELECTRIC - ABOVE CEILING | RJIROUDE | Approved | IVRS - Inspection :* |
| 07/02/2008 | ELECTRIC - INTERMEDIATE | RJIROUDE | Approved | IVRS - Inspection :* |
| 07/02/2008 | ELECTRIC - UNDERGROUND | RJIROUDE | Approved | IVRS - Inspection :* |
| 07/02/2008 | ELECTRIC - UFER | RJIROUDE | Approved | IVRS - Inspection :* |
| 07/02/2008 | PLUMBING - FINAL | RRICH | Approved | IVRS - Inspection :* |
| 07/03/2008 | BUILDING - FINAL | GDABBS | Approved | IVRS - Inspection :* |
| 07/03/2008 | BUILDING - PROGRESS | GDABBS | Approved | IVRS - Inspection :* |
| 07/03/2008 | FRAMING | GDABBS | Approved | IVRS - Inspection :* |
| 07/03/2008 | REINFORCED MASONRY PRE-GROUT | GDABBS | Approved | IVRS - Inspection :* |
| 07/03/2008 | EXCAVATION/LAYOUT REBAR & ZON | GDABBS | Approved | IVRS - Inspection :* |
| 07/03/2008 | STEM WALL/RETAINING WALL | GDABBS | Approved | IVRS - Inspection :* |