Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Permit Number: T07CM03741
Parcel: 14111365A

Review Status: Completed

Review Details: REVISION - - 1ST

Permit Number - T07CM03741
Review Name: REVISION - - 1ST
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
06/19/2008 LINDA BUCZYNSKI ELECTRICAL-COMMERCIAL REVIEW Denied TRANSMIT ORIGINAL DRAWINGS WITH NEXT SUBMITTAL.

PLEASE CALL AT 791-5550 X1106 OR EMAIL AT Linda.Buczynski@tucsonaz.gov
IF YOU CARE TO DISCUSS.

1. On 1st Generation Revision, the electrical loads of Panel PP1 Phase B abruptly changed without revision cloud. This is mysterious because Phases A and C are similar in nature and did not change. If the original 22920 VA on PP1 is carried through in tabulating electrical loads, then Panel PP4 will be overloaded.
2. On 1st Generation Revision, the GND on the secondaries of the transformers, properly sized per NEC Table 250.66, would be 1/0, not #3. However, coordinate this comment with those pertaining to the 2nd Generation Revision, below.
3. On 2nd Generation Revision, the GND on the secondaries of the transformers, properly sized per NEC Table 250.66, would be 1/0, not #2.
4. On 1st and 2nd Generation Revisions, Revision #4 on Sheet E6 is dated 1/28/08, but they are different revisions. Clarify.

Final Status

Task End Date Reviewer's Name Type of Review Description
06/19/2008 GERARDO BONILLA OUT TO CUSTOMER Completed