Permit: T06CM06353
Permit Details
Apply Date:
12/15/2006
Applicant:
N/A
Description:
NEW RESTAURANT
Architects:
- PETRICK KEVIN BLAKE
Contractors:
- STARSYS DEVELOPMENT COMPANY ,
Permit Reviews
Permit Number - T06CM06353
Permit Status: C of o
Permit Description: NEW RESTAURANT
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
01/09/2007 | POST 3RD PARTY REVIEW | 02/14/2007 | COMPLETED |
12/15/2006 | PLANS OK TO SUBMIT - 3RD PARTY | 12/15/2006 | COMPLETED |
12/15/2006 | 3RD PARTY REVIEW-COMMERCIAL | 01/09/2007 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T06CM06353
Permit Status: C of o
Permit Description: NEW RESTAURANT
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
12/15/2006 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T06CM06353
Permit Description: NEW RESTAURANT
Total Completed Inspections - 31
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
02/28/2007 | ELECTRIC - RECONNECT | DSANTACR | Approved | IVRS - Inspection :* |
02/28/2007 | ELECTRIC - CONSTRUCTION POWER | DSANTACR | Approved | IVRS - Inspection :* |
03/14/2007 | PLUMBING - ROUGH, SOIL | RRICH | Approved | WATER TEST WASTE & VENT & GREASE WASTE UNDERGROUND OK WHEN REVISED APPROVED PLAN ON SITE FOR CHANGES & DELETION OF FLOOR SINK |
03/14/2007 | PLUMBING - PRE SLAB | RRICH | Approved | IVRS - Inspection :* |
04/10/2007 | FRAMING | GDABBS | Approved | IVRS - Inspection :* |
04/10/2007 | ELECTRIC - INTERMEDIATE | RJIROUDE | Approved | IVRS - Inspection :* |
04/18/2007 | PLUMBING - ABOVE CEILING | RRICH | Approved | IVRS - Inspection :* |
04/24/2007 | SHEET ROCK NAILING | GDABBS | Approved | IVRS - Inspection :* |
05/17/2007 | TEP CLEARANCE - AM | JWEATHER | Approved | TEC CLEARED FOR STE. #100-PANEL B PER C. CLEMENS 2ND TIME SENT TO TEP |
05/29/2007 | MECHANICAL - INTERMEDIATE | JMILITEL | Approved | IVRS - Inspection :* OK PARTIAL CEILING TILES |
05/29/2007 | PLUMBING - INTERMEDIATE | RRICH | Approved | IVRS - Inspection :* CLOSET FLANGE OK |
06/14/2007 | MECHANICAL - HOODS | JMILITEL | Approved | IVRS - Inspection :* 1) FIRE WRAP OK 2) OK FOR CEILING TILES-LEAVE OUT UNDER EACH DUCT SMOKE DETECTOR AND HAVE DETECTORS READY FOR SMOKE TEST 3) PROVIDE AUBIBLE AND VISIBLE ALARMS 4) REMOVE VENT FROM WALK IN CONDENSATE DRAIN 5) WILL CHECK TERMINATION ON FINAL 6) WILL CHECK WATER HEATER VENT AT FINAL |
06/18/2007 | BUILDING ABOVE CEILING | GDABBS | Approved | IVRS - Inspection :* |
06/19/2007 | ELECTRIC - ABOVE CEILING | RJIROUDE | Approved | IVRS - Inspection :* |
06/21/2007 | MECHANICAL - ABOVE CEILING | JMILITEL | Approved | IVRS - Inspection :* |
06/21/2007 | PLUMBING - GAS PRESS TEST FNL | RRICH | Approved | IVRS - Inspection :* |
06/21/2007 | PLUMBING - GAS PRESSURE TEST | RRICH | Approved | IVRS - Inspection :* |
06/21/2007 | LANDSCAPE - FINAL | ACONNOR | Approved | |
06/21/2007 | NPPO - FINAL | ACONNOR | Approved | |
06/21/2007 | RIGHT OF WAY - FINAL | PWHIDDON | Approved | PER EMAIL |
06/22/2007 | ENGINEERING - FINAL | NKALAHAR | Approved | ITEMS ADDRESSED |
06/25/2007 | FIRE SPKLR - FINAL | LTHOMAS | Approved | |
06/27/2007 | ELECTRIC - FINAL | RJIROUDE | Approved | IVRS - Inspection :* OK FINAL OK FOR TEMP C OF O |
06/27/2007 | PLUMBING - FINAL | RRICH | Approved | IVRS - Inspection :* |
06/27/2007 | FIRE - KITCHEN EXH HOOD FINAL | LLAKEY | Approved | |
06/27/2007 | FIRE - FINAL | LLAKEY | Approved | |
06/27/2007 | BUILDING - FINAL | GDABBS | Approved | IVRS - Inspection :* |
06/29/2007 | MECHANICAL - FINAL | JMILITEL | Approved | |
06/29/2007 | MECHANICAL - HOOD SYSTEMS | JMILITEL | Approved | |
06/29/2007 | SIGN - FINAL | JSONKIN | Approved | IVRS - Inspection :* |
07/02/2007 | HEALTH DEPT - FINAL 724-7908 | LMOSS | Approved |