Permit: T06CM05771
Permit Details
Apply Date:
11/06/2006
Applicant:
TOM, RICHARD FE
Description:
SHELL BLDG
Architects:
- TOM, RICHARD FE
Contractors:
- LA CAUSA CONSTRUCTION INC
Permit Reviews
Permit Number - T06CM05771
Permit Status: Final
Permit Description: SHELL BLDG
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 11/06/2006 | PLANS OK TO SUBMIT - COMM | 11/08/2006 | COMPLETED |
| 11/06/2006 | PLANS OK TO SUBMIT - SITE | 11/08/2006 | COMPLETED |
| 11/09/2006 | SITE | 12/01/2006 | COMPLETED |
| 11/09/2006 | COMMERCIAL NEW | 12/01/2006 | COMPLETED |
| 12/11/2006 | RESUBMITTAL - SITE ALL | 12/19/2006 | COMPLETED |
| 12/11/2006 | RESUBMITTAL | 12/19/2006 | COMPLETED |
| 12/19/2006 | RESUBMITTAL - SITE | 12/20/2006 | COMPLETED |
| 12/20/2006 | RESUBMITTAL | 01/08/2007 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T06CM05771
Permit Status: Final
Permit Description: SHELL BLDG
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 11/06/2006 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T06CM05771
Permit Description: SHELL BLDG
Total Completed Inspections - 36
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/27/2008 | ROOF NAILING | MHENSON | Approved | IVRS - Inspection :* OK TO DRY IN |
| 09/08/2008 | ELECTRIC - UNDERGROUND | DSANTACR | Approved | IVRS - Inspection :* OK 4" SECONDARY INTO SES LOCATION FROM TEP X-FORMER AND 1 4" COMM. |
| 10/28/2008 | PLUMBING - ROOF DRAINS | RLEDONNE | Approved | IVRS - Inspection :* FROM ROOF TO STUB OUTSIDE OF BUILDING |
| 11/19/2008 | PLUMBING - BACK WATER VALVE | RLEDONNE | Approved | IVRS - Inspection :* GAS PIPING INSTALLED PER APPROVED PLAN FOR FUTURE |
| 11/19/2008 | PLUMBING - ROUGH, SOIL | RLEDONNE | Approved | IVRS - Inspection :* |
| 11/21/2008 | PLUMBING - GAS PRESSURE TEST | RLEDONNE | Approved | IVRS - Inspection :* |
| 11/21/2008 | PLUMBING - SEWER HCS CONNECT | RLEDONNE | Approved | IVRS - Inspection :* |
| 11/24/2008 | FRAMING | MHENSON | Approved | IVRS - Inspection :* SOUTH CANOPIES 1. PROVIDE WELD SPECIAL INSPECTION |
| 11/26/2008 | STUCCO MESH | MHENSON | Approved | IVRS - Inspection :* |
| 12/03/2008 | EXCAVATION/LAYOUT REBAR & ZON | MHENSON | Approved | IVRS - Inspection :* 1. FRONT ENTRY AND ELECTRIC ROOM, SLAB & SIDEWALK 2. DETAIL 104 SHOWS SLAB OVER STEM WALL - SLAB POURING TO STEM WALL |
| 02/12/2009 | SHEET ROCK NAILING | GDABBS | Approved | IVRS - Inspection :* 1) ELECTRICAL ROOM AND FIRE RISER ROOM |
| 03/30/2009 | ELECTRIC - TEMP POWER FOR TEST | DSANTACR | Approved | IVRS - Inspection :* 1) CALL FOR INSPECTION FOR INSIDE WIRING 2) FINAL INSPECTION AFTER POWER CHECK 3) ROOF NEEDS INSPECTION |
| 03/31/2009 | TEP CLEARANCE - AM | JWEATHER | Approved | TEC CLEARED FOR "HP METER ONLY" PER D. SANTACRUZ |
| 05/15/2009 | ELECTRIC - FINAL | RHOLLAND | Approved | IVRS - Inspection :* |
| 05/15/2009 | ELECTRIC - OUTDOOR LIGHTING | RHOLLAND | Approved | IVRS - Inspection :* |
| 05/15/2009 | ELECTRIC - CABLE DROP | RHOLLAND | Approved | IVRS - Inspection :* |
| 05/15/2009 | ELECTRIC - INTERMEDIATE | RHOLLAND | Approved | IVRS - Inspection :* |
| 05/15/2009 | PLUMBING - INTERMEDIATE | RLEDONNE | Approved | IVRS - Inspection :* |
| 07/07/2009 | MECHANICAL - INTERMEDIATE | MRAMBER | Approved | IVRS - Inspection :* 1) DUCT SMOKE DETECTORS OMITTED PER ENGINEER |
| 07/07/2009 | MECHANICAL - FINAL | MRAMBER | Approved | IVRS - Inspection :* |
| 07/08/2009 | PLUMBING - YARD WTR LINE/TEST | RLEDONNE | Approved | IVRS - Inspection :* 1) PROVIDE LETTER ? BLDG WATER MAIN 3" VALVE 2) REPAIR LEAK 3) PROVIDE CAPS ON ALL OPEN VALVES |
| 07/08/2009 | PLUMBING - PROGRESS | RLEDONNE | Approved | IVRS - Inspection :* |
| 07/14/2009 | PLUMBING - FINAL | RLEDONNE | Approved | IVRS - Inspection :* |
| 10/21/2009 | SIGN - FINAL | JYBARRA | Approved | |
| 10/21/2009 | RIGHT OF WAY - FINAL | LLOPEZ | Approved | PER EMAIL |
| 10/26/2009 | U VALUE FOR WINDOW | MHENSON | Approved | IVRS - Inspection :* |
| 10/26/2009 | BUILDING PRE-SLAB | MHENSON | Approved | IVRS - Inspection :* |
| 11/13/2009 | FIRE - FINAL | LTHOMAS | Approved | Approved |
| 11/20/2009 | NPPO - FINAL | CGROSS | Approved | |
| 11/20/2009 | LANDSCAPE - FINAL | CGROSS | Approved | |
| 11/20/2009 | LANDSCAPE - FINAL | JLINVILLE | Approved | 1. Water Harvesting is required per Note 7 2. Adjust irrigation appropriately to stop over watering. |
| 11/24/2009 | FIRE SPKLR - FINAL | LTHOMAS | Approved | Approved |
| 12/07/2009 | ENGINEERING - FINAL | MCARREON | Approved | ALL PUNCH LIST ITEMS HAVE BEEN SATISFIED. |
| 12/08/2009 | BUILDING - FINAL | MHENSON | Approved | IVRS - Inspection :* 1) LETTER OF COMPLETION ONLY |
| 12/08/2009 | EXT METAL CLIPS/EXT SHEATHING | MHENSON | Approved | |
| 12/09/2009 | PERMIT FINALED | JWEATHER | Approved |