Permit Reviews

Permit Number - T06CM03052
Permit Status: C of o
Permit Description: NEW CLASSROOM BLDG
Start Date Submittal Complete Date Status  
05/22/2006 PLANS OK TO SUBMIT - 3RD PARTY 05/24/2006 COMPLETED Review Details
05/22/2006 PLANS OK TO SUBMIT - SITE 08/16/2006 COMPLETED Review Details
05/24/2006 3RD PARTY REVIEW-COMMERCIAL 08/15/2006 COMPLETED Review Details
08/15/2006 POST 3RD PARTY REVIEW 08/31/2006 COMPLETED Review Details
08/16/2006 SITE 11/27/2006 COMPLETED Review Details
08/31/2006 RESUBMITTAL 11/08/2006 COMPLETED Review Details
11/08/2006 3RD PARTY REVIEW-REVISION/OTHER 11/27/2006 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T06CM03052
Permit Status: C of o
Permit Description: NEW CLASSROOM BLDG
Total Outstanding Activity Conditions - 1
Date Name
05/22/2006 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: C of o
Permit Number: T06CM03052
Permit Description: NEW CLASSROOM BLDG
Total Completed Inspections - 41
Date Description Inspector Results Comments
09/21/2006 ELECTRIC - UFER RHOLLAND Approved IVRS - Inspection :*
OK UFER -- 3/0 & CLAMP TO REBAR
10/03/2006 STEM WALL/RETAINING WALL JBURGE Approved IVRS - Inspection :*
N. STAIRWELL & ELEVATOR AREAS COMPLETE
10/13/2006 PLUMBING - YARD WTR LINE/TEST BBENEDON Approved IVRS - Inspection :*
3" TYPE K COPPER W/7.5 PSI TEST, STUBBED INTO BUILDING.
10/13/2006 PLUMBING - ROUGH, SOIL BBENEDON Approved IVRS - Inspection :*
10/18/2006 PLUMBING - PRE SLAB BBENEDON Approved IVRS - Inspection :*
PROTECT COUPLING IN NE STEM WALL, THEN OK TO POUR
10/19/2006 ELECTRIC - UNDERGROUND RMAJUTA Approved IVRS - Inspection :*
ELEVATOR CONDUITS -- CLASSROOM BLDG. TO MECH. ROOM
10/20/2006 EXCAVATION/LAYOUT REBAR & ZON JBURGE Approved MECHANICAL ROOM (RE-OPENED)
10/20/2006 PLUMBING - INTERMEDIATE BBENEDON Approved IVRS - Inspection :*
FD AND FCO OK FOR CONCRETE
3" BLK STEEL SLEEVED AND UNDER TEST 100 PSI
11/20/2006 MECHANICAL - ABOVE CEILING JMILITEL Approved 100 PSI TEST ON CHILLER PIPE OK TO INSULATE
11/21/2006 MECHANICAL - INTERMEDIATE JMILITEL Approved IVRS - Inspection :*
INSULATION ON CHILLER PIPE OK TO COVER
12/06/2006 BUILDING PRE-SLAB JBURGE Approved 2ND FLOOR OK TO POUR
12/19/2006 FRAMING JBURGE Approved IVRS - Inspection :*
2ND FLOOR EXTERIOR WALLS OK TO COVER
12/19/2006 REINFORCED MASONRY PRE-GROUT JBURGE Approved IVRS - Inspection :*
ELEVATOR MECHANICAL ROOM @ 14'8" TOPPED OUT
12/28/2006 ROOF NAILING JBURGE Approved IVRS - Inspection :*
1) CONTRACTOR CANCELLED-RAINED OUT
01/03/2007 SITE - SEWER BBENEDON Approved IVRS - Inspection :*
01/22/2007 EXT METAL CLIPS/EXT SHEATHING JBURGE Approved OK TO STUCCO
02/27/2007 STUCCO MESH JBURGE Approved IVRS - Inspection :*
1ST FLOOR OVERHANG - EAST ENTRY CEILINGS OK TO STUCCO
03/13/2007 SHEET ROCK NAILING JBURGE Approved IVRS - Inspection :*
STAIRWELLS COMPLETE
03/30/2007 BUILDING ABOVE CEILING JBURGE Approved IVRS - Inspection :*
OK TO SET TILES
05/10/2007 PLUMBING - FINAL BBENEDON Approved IVRS - Inspection :*
05/10/2007 PLUMBING - ABOVE CEILING BBENEDON Approved IVRS - Inspection :*
05/10/2007 PLUMBING - ROOF DRAINS BBENEDON Approved IVRS - Inspection :*
05/10/2007 PLUMBING - PROGRESS BBENEDON Approved IVRS - Inspection :*
05/15/2007 ENGINEERING - FINAL JBRUCKME Approved
05/15/2007 NPPO - FINAL ACONNOR Approved N/A
05/15/2007 LANDSCAPE - FINAL ACONNOR Approved N/A
05/15/2007 SIGN - FINAL JYBARRA Approved
05/16/2007 RIGHT OF WAY - FINAL PWHIDDON Approved PER EMAIL
05/18/2007 ELECTRIC - FINAL RHOLLAND Approved IVRS - Inspection :*
OK FINAL
CONTRACTOR TO FIRE SEAL RACEWAY SLEEVES AT BOTH ENDS
05/18/2007 OUTDOOR LIGHTING FINAL RHOLLAND Approved IVRS - Inspection :*
05/18/2007 ELECTRIC - OUTDOOR LIGHTING RHOLLAND Approved IVRS - Inspection :*
05/18/2007 ELECTRIC - SERVICE UPGRADE RHOLLAND Approved IVRS - Inspection :*
05/18/2007 ELECTRIC - PROGRESS RHOLLAND Approved IVRS - Inspection :*
05/18/2007 ELECTRIC - ABOVE CEILING RHOLLAND Approved IVRS - Inspection :*
05/18/2007 ELECTRIC - INTERMEDIATE RHOLLAND Approved IVRS - Inspection :*
06/18/2007 MECHANICAL - FINAL JMILITEL Approved IVRS - Inspection :*
OK FOR FINAL
AIR BALANCE OK
06/18/2007 MECHANICAL - HOODS JMILITEL Approved IVRS - Inspection :*
06/18/2007 BUILDING - PROGRESS JBURGE Approved IVRS - Inspection :*
06/18/2007 U VALUE FOR WINDOW JBURGE Approved IVRS - Inspection :*
06/18/2007 BUILDING - FINAL JBURGE Approved IVRS - Inspection :*
06/19/2007 FIRE - FINAL LTHOMAS Approved