Permit: T06CM02975
Permit Details
Status:
C of o
Type:
SINGLE FAMILY NEW
Address:
3007 W VIA DE SUENOS
Address NEW:
3007 W VIA DE SUENOS
Apply Date:
05/18/2006
Applicant:
GARCIA RODULFO
Description:
NEW: SFR
Contractors:
- D M G CO
Permit Reviews
Permit Number - T06CM02975
Permit Status: C of o
Permit Description: NEW: SFR
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/07/2010 | REVISION - - 2ND | 01/07/2010 | COMPLETED |
| 02/22/2010 | REVISION - - 3RD | 02/22/2010 | COMPLETED |
| 03/11/2010 | REVISION - - 4TH | 03/11/2010 | COMPLETED |
| 05/02/2008 | RESUBMITTAL | 05/14/2008 | COMPLETED |
| 05/18/2006 | PLANS OK TO SUBMIT - RES | 11/13/2006 | COMPLETED |
| 05/30/2008 | RESUBMITTAL | 06/25/2008 | COMPLETED |
| 07/16/2008 | RESUBMITTAL | 08/05/2008 | COMPLETED |
| 07/25/2008 | RESUBMITTAL | 08/12/2008 | COMPLETED |
| 11/13/2006 | RESIDENTIAL BLDG/ZONING/ENGINE/WWM | 02/06/2007 | COMPLETED |
| 11/18/2008 | RESUBMITTAL | 11/19/2008 | COMPLETED |
| 11/19/2008 | RESUBMITTAL | 06/12/2009 | COMPLETED |
| 12/20/2007 | RESUBMITTAL | 03/11/2008 | COMPLETED |
| 12/31/2009 | REVISION - - 1ST | 12/31/2009 | COMPLETED |
| 12/31/2009 | REVISION - - 1ST | 01/07/2010 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T06CM02975
Permit Status: C of o
Permit Description: NEW: SFR
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 05/18/2006 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T06CM02975
Permit Description: NEW: SFR
Total Completed Inspections - 29
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/14/2009 | ELECTRIC - UNDERGROUND | RCAMACHO | Approved | IVRS - Inspection :* 1) 2" NON METALLIC RIGID UNDER ROAD OK TO BURY ONLY |
| 09/30/2009 | PLUMBING - YARD WTR LINE/TEST | RCAMACHO | Approved | IVRS - Inspection :* 1) NOT CONNECTED TO HOUSE ONLY 2) OK TO BURY |
| 10/23/2009 | ELECTRIC - UFER | MHENSON | Approved | IVRS - Inspection :* |
| 12/01/2009 | PLUMBING - ROUGH, SOIL | RCAMACHO | Approved | IVRS - Inspection :* 1) PROVIDE AS BUILT NEW LOCATION OF SEPTIC AND SEWER LINES |
| 12/08/2009 | BUILDING PRE-SLAB | MHENSON | Approved | IVRS - Inspection :* 1) UPPER LEVEL HOUSE SLAB PLUMBING WRAPPED MESH AND REBAR OK DETAIL 3-14 ON 10 2) EPOXY REBAR SPECIAL INSPECTED |
| 12/21/2009 | EXCAVATION/LAYOUT REBAR & ZON | RCAMACHO | Approved | IVRS - Inspection :* 1) CANCELLED |
| 12/29/2009 | ELECTRIC - CABLE DROP | MHENSON | Approved | |
| 12/29/2009 | ELECTRIC - TEMPORARY SERVICE | MHENSON | Approved | IVRS - Inspection :* |
| 12/30/2009 | TEP CLEARANCE - AM | JWEATHER | Approved | ECO CLEARED PER M. HENSON |
| 01/13/2010 | REINFORCED MASONRY PRE-GROUT | RCAMACHO | Approved | |
| 03/15/2010 | GRADING - TIER REV | Eleibol1 | Approved | PDSD Engineering has no issue with revising septic system equipment to the south. |
| 03/22/2010 | U VALUE FOR WINDOW | RCAMACHO | Approved | IVRS - Inspection :* |
| 03/30/2010 | ROOF NAILING | RCAMACHO | Approved | IVRS - Inspection :* |
| 03/30/2010 | EXT METAL CLIPS/EXT SHEATHING | RCAMACHO | Approved | IVRS - Inspection :* |
| 04/21/2010 | STUCCO MESH | RCAMACHO | Approved | IVRS - Inspection :* |
| 04/21/2010 | MECHANICAL - INTERMEDIATE | RCAMACHO | Approved | IVRS - Inspection :* |
| 04/27/2010 | ELECTRIC - INTERMEDIATE | RCAMACHO | Approved | IVRS - Inspection :* |
| 04/28/2010 | PLUMBING - INTERMEDIATE | RCAMACHO | Approved | IVRS - Inspection :* |
| 04/29/2010 | FRAMING | RCAMACHO | Approved | IVRS - Inspection :* |
| 05/13/2010 | SHEET ROCK NAILING | RCAMACHO | Approved | IVRS - Inspection :* |
| 07/26/2010 | PLUMBING - SEWER HCS CONNECT | RCAMACHO | Approved | IVRS - Inspection :* |
| 08/20/2010 | NPPO PRE PERMIT INSPECTION | JFEMLING | Approved | Approved |
| 08/20/2010 | LANDSCAPE - FINAL | JFEMLING | Approved | Approved |
| 08/23/2010 | FIRE SPKLR - FINAL | LTHOMAS | Approved | |
| 08/26/2010 | MECHANICAL - FINAL | RCAMACHO | Approved | IVRS - Inspection :* |
| 08/26/2010 | PLUMBING - FINAL | RCAMACHO | Approved | IVRS - Inspection :* |
| 08/26/2010 | ELECTRIC - FINAL | RCAMACHO | Approved | IVRS - Inspection :* |
| 08/31/2010 | BUILDING - FINAL | RCAMACHO | Approved | IVRS - Inspection :* 1) PROVIDE CERTS |
| 09/01/2010 | PERMIT FINALED | JWEATHER | Approved |