Permit Details

Status:
C of o
Type:
COMMERCIAL ADDITION
Apply Date:
04/24/2006
Applicant:
N/A
Description:
ADD: 2 STORY 16 CLASSROOM BUILDING
Architects:
  • BROOKS, ROGER WILLIAM
Contractors:
  • CORONA SIERRA INC ,
  • TUCSON UNIFIED SCHOOL DIST #1

Permit Reviews

Permit Number - T06CM02334
Permit Status: C of o
Permit Description: ADD: 2 STORY 16 CLASSROOM BUILDING
Start Date Submittal Complete Date Status  
04/24/2006 PLANS OK TO SUBMIT - 3RD PARTY 04/24/2006 COMPLETED Review Details
04/24/2006 PLANS OK TO SUBMIT - SITE 04/24/2006 COMPLETED Review Details
04/24/2006 3RD PARTY REVIEW-COMMERCIAL 06/05/2006 COMPLETED Review Details
04/24/2006 SITE 08/29/2006 COMPLETED Review Details
06/05/2006 POST 3RD PARTY REVIEW 06/12/2006 COMPLETED Review Details
07/27/2006 RESUBMITTAL 08/11/2006 COMPLETED Review Details
08/11/2006 RESUBMITTAL 09/01/2006 COMPLETED Review Details
09/22/2006 3RD PARTY REVIEW-REVISION/OTHER 09/22/2006 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T06CM02334
Permit Status: C of o
Permit Description: ADD: 2 STORY 16 CLASSROOM BUILDING
Total Outstanding Activity Conditions - 1
Date Name
04/24/2006 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: C of o
Permit Number: T06CM02334
Permit Description: ADD: 2 STORY 16 CLASSROOM BUILDING
Total Completed Inspections - 50
Date Description Inspector Results Comments
10/05/2006 ELECTRIC - UNDERGROUND RHOLLAND Approved IVRS - Inspection :*
APPROX 50' OF 2 - 4" PVC'S FRONT OF MAIN
1 - 2" PVC
3 - 1" PVC
OK TO COVER
10/05/2006 ELECTRIC - UFER RHOLLAND Approved IVRS - Inspection :*
10/17/2006 PLUMBING - ROUGH, SOIL BBENEDON Approved IVRS - Inspection :*
INSTALL 4" CLEANOUT AT W.C RM 115
CALL FOR PLUMBING PRE-SLAB INSP. PRIOR TO CONCRETE.
10/19/2006 ELECTRIC - INTERMEDIATE CCLEMENS Approved IVRS - Inspection :*
OK FIRST LIFT IN GROUTED WALLS -- OK TO CONTINUE ON
10/26/2006 STEM WALL/RETAINING WALL JBURGE Approved IVRS - Inspection :*
STEM WALLS @ 24"
LINES D/1 TO H/1 OK TO POUR
COLUMN FOOTINGS @ F/3, G/3, H/3 -- OK TO POUR
12/05/2006 EXCAVATION/LAYOUT REBAR & ZON GDABBS Approved IVRS - Inspection :*
COLUMN FOOTING D-3 & E-3
12/22/2006 BUILDING PRE-SLAB JBURGE Approved IVRS - Inspection :*
A TO D & #1 TO #4 OK TO POUR
12/29/2006 REINFORCED MASONRY PRE-GROUT GDABBS Approved IVRS - Inspection :*
1) EAST SIDE CMUN COLUMNS TO 13/4 AT GRID D-E-F
03/06/2007 ROOF NAILING JBURGE Approved IVRS - Inspection :*
OK TO DRY IN ROOF AREA
03/26/2007 EXT METAL CLIPS/EXT SHEATHING JBURGE Approved IVRS - Inspection :*
04/06/2007 SITE - SEWER BBENEDON Approved IVRS - Inspection :*
1) AFTER HRS INSPECTION REQUESTED BY PAT-PAID WITH MONEY ORDER 56186674896
04/25/2007 STUCCO MESH JBURGE Approved IVRS - Inspection :*
OK TO STUCCO ALL EXTERIOR WALLS
05/04/2007 FRAMING JBURGE Approved IVRS - Inspection :*
ALL RESTROOMS COMPLETED
05/09/2007 PLUMBING - ABOVE CEILING BBENEDON Approved IVRS - Inspection :*
05/09/2007 PLUMBING - PRE SLAB BBENEDON Approved IVRS - Inspection :*
05/09/2007 PLUMBING - GAS PRESSURE TEST BBENEDON Approved IVRS - Inspection :*
05/09/2007 PLUMBING - INTERMEDIATE BBENEDON Approved IVRS - Inspection :*
05/10/2007 MECHANICAL - ABOVE CEILING CWILLIAM Approved IVRS - Inspection :*
05/15/2007 SHEET ROCK NAILING JBURGE Approved IVRS - Inspection :*
RESTROOMS & MECHANICAL ROOMS OK TO TAPE
05/22/2007 MECHANICAL - PROGRESS JMILITEL Approved IVRS - Inspection :*
05/22/2007 BUILDING ABOVE CEILING JBURGE Approved IVRS - Inspection :*
OK TO SET TILES
1ST & 2ND FLOORS
05/23/2007 MECHANICAL - INTERMEDIATE CWILLIAM Approved 100 PSI TEST ON UNDERGROUND CHILLER PIPING OK TO BACKFILL TRENCH.
06/25/2007 PLUMBING - PROGRESS BBENEDON Approved IVRS - Inspection :*
CLOSET FLANGES OK
06/25/2007 PLUMBING - YARD WTR LINE/TEST BBENEDON Approved IVRS - Inspection :*
06/26/2007 FIRE SPKLR - UG, PIPING, HYDRO LTHOMAS Approved
06/26/2007 FIRE SPKLR - UG PIPING FLUSH LTHOMAS Approved
06/26/2007 FIRE SPKLR - OH PIPING & HYDRO LTHOMAS Approved
06/26/2007 FIRE SPKLR - FINAL LTHOMAS Approved
06/28/2007 FIRE - ALARM FINAL LTHOMAS Approved
06/28/2007 FIRE - FINAL LTHOMAS Approved
07/02/2007 PLUMBING - GAS PRESS TEST FNL BBENEDON Approved IVRS - Inspection :*
07/11/2007 MECHANICAL - FINAL JMILITEL Approved IVRS - Inspection :*
OK FOR FINAL
AIR BALANCE OK
07/11/2007 U VALUE FOR WINDOW JBURGE Approved IVRS - Inspection :*
07/13/2007 ELECTRIC - FINAL CCLEMENS Approved IVRS - Inspection :*
10, 05, 35, 36, 61, 62, 75, 85, 99
07/13/2007 OUTDOOR LIGHTING FINAL CCLEMENS Approved IVRS - Inspection :*
07/13/2007 ELECTRIC - OUTDOOR LIGHTING CCLEMENS Approved IVRS - Inspection :*
07/13/2007 ELECTRIC - PROGRESS CCLEMENS Approved IVRS - Inspection :*
07/13/2007 ELECTRIC - TEMP POWER FOR TEST CCLEMENS Approved IVRS - Inspection :*
07/13/2007 ELECTRIC - CONSTRUCTION POWER CCLEMENS Approved IVRS - Inspection :*
07/13/2007 ELECTRIC - ABOVE CEILING CCLEMENS Approved IVRS - Inspection :*
07/19/2007 PLUMBING - FINAL BBENEDON Approved IVRS - Inspection :*
07/20/2007 PLUMBING - ROOF DRAINS BBENEDON Approved
07/27/2007 BUILDING - FINAL JBURGE Approved IVRS - Inspection :*
07/27/2007 BUILDING - PROGRESS JBURGE Approved IVRS - Inspection :*
08/03/2007 NPPO - FINAL ACONNOR Approved N/A
08/03/2007 LANDSCAPE - FINAL ACONNOR Approved N/A
08/03/2007 SIGN - FINAL JYBARRA Approved IVRS - Inspection :*
08/06/2007 RIGHT OF WAY - FINAL MOTERO Approved PER EMAIL
09/05/2007 ENGINEERING - FINAL MRUSSO Approved
09/07/2007 PERMIT FINALED LJACKSON Approved

Documents

File Name Document Type  
C OF O_08-13-2007.TIF CERT OF OCC VIEW
DRAINAGESTATEMENT.TIF DOCUMENTS VIEW
None DOCUMENTS VIEW
ORIGINAL CONSTRPLANS VIEW
None CONSTRPLANS VIEW