Inspection History Details
Inspection Status: Approved
Inspection History: PLUMBING - ROUGH, SOIL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/17/2006 | PLUMBING - ROUGH, SOIL | Approved | IVRS - Inspection :* INSTALL 4" CLEANOUT AT W.C RM 115 CALL FOR PLUMBING PRE-SLAB INSP. PRIOR TO CONCRETE. |
|
| 10/13/2006 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* SWEEP OK 2 1/2" K COPPER W/BRAZED 90 AND 100 PSI TEST PROTECT COPPER FROM CONCRETE - INSTALL BRANCH FOR 3" P-7 114 NO PIPING SHALL BE DIRECTLY EMBEDDED IN CONCRETE OK THRU COL. F TOILET RM. SOUTH OF F CORRECT SLOPE |
|
| 09/28/2006 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* - POST ADDRESS - SWEEP REQUIRED AT VERTICAL TO HORIZONTAL CHANGES OF DIRECTION. - SEC. D OUT THROUGH TWO WAY CO, MAIN LINE ONLY W/RISERS CAPPED OFF, OK TO COVER EXCEPT FOR UPPER TERMINAL CLEANOUT SHALL BE A WYE PATTERN FITTING OR SWEEP OF EQUIVALENT RADIUS. |