Permit: T05CM04557
Permit Details
Apply Date:
09/01/2005
Applicant:
METRO PERMIT EXPRESS
Description:
SITE IMPROVEMENTS:ADDITION:CANOPY
Contractors:
- CHESTNUT CONSTRUCTION CORPORATIO
Permit Reviews
Permit Number - T05CM04557
Permit Status: Final
Permit Description: SITE IMPROVEMENTS:ADDITION:CANOPY
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/23/2006 | RESUBMITTAL | 02/14/2006 | COMPLETED |
| 01/23/2006 | RESUBMITTAL - SITE | 02/14/2006 | COMPLETED |
| 02/14/2006 | RESUBMITTAL | 02/21/2006 | COMPLETED |
| 09/01/2005 | PLANS OK TO SUBMIT - SITE | 09/06/2005 | COMPLETED |
| 09/01/2005 | PLANS OK TO SUBMIT - COMM | 09/07/2005 | COMPLETED |
| 09/07/2005 | SITE | 10/20/2005 | COMPLETED |
| 09/07/2005 | COMMERCIAL NEW | 10/20/2005 | COMPLETED |
| 11/30/2005 | RESUBMITTAL | 12/29/2005 | COMPLETED |
| 11/30/2005 | RESUBMITTAL - SITE ALL | 12/29/2005 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T05CM04557
Permit Status: Final
Permit Description: SITE IMPROVEMENTS:ADDITION:CANOPY
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 09/01/2005 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T05CM04557
Permit Description: SITE IMPROVEMENTS:ADDITION:CANOPY
Total Completed Inspections - 19
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/05/2006 | EXCAVATION/LAYOUT REBAR & ZON | LHANLY | Approved | IVRS - Inspection :* |
| 05/17/2006 | PLUMBING - ROUGH, SOIL | BBENEDON | Approved | IVRS - Inspection :* |
| 05/17/2006 | PLUMBING - YARD WTR LINE/TEST | BBENEDON | Approved | IVRS - Inspection :* |
| 05/19/2006 | BUILDING PRE-SLAB | LHANLY | Approved | IVRS - Inspection :* |
| 06/01/2006 | ELECTRIC - INTERMEDIATE | DSANTACR | Approved | IVRS - Inspection :* |
| 06/01/2006 | PLUMBING - FINAL | BBENEDON | Approved | IVRS - Inspection :* |
| 06/01/2006 | PLUMBING - PROGRESS | BBENEDON | Approved | IVRS - Inspection :* |
| 06/02/2006 | SIGN - FINAL | JSONKIN | Approved | IVRS - Inspection :* |
| 06/05/2006 | RIGHT OF WAY - FINAL | LLOPEZ | Approved | PER EMAIL |
| 11/08/2006 | ELECTRIC - OUTDOOR LIGHTING | DSANTACR | Approved | IVRS - Inspection :* |
| 11/08/2006 | ELECTRIC - UNDERGROUND | DSANTACR | Approved | IVRS - Inspection :* |
| 11/08/2006 | ELECTRIC - UFER | DSANTACR | Approved | IVRS - Inspection :* |
| 11/08/2006 | ELECTRIC - FINAL | DSANTACR | Approved | IVRS - Inspection :* |
| 11/09/2006 | FRAMING | LHANLY | Approved | IVRS - Inspection :* |
| 11/09/2006 | BUILDING - FINAL | LHANLY | Approved | IVRS - Inspection :* |
| 11/09/2006 | BUILDING - FINAL | AALEGRIA | Approved | IVRS - Inspection :* |
| 12/13/2006 | ENGINEERING - FINAL | MAVERY | Approved | Contractor needs to supply approved reviesed drawing. Contractor provided new perk test info. |
| 12/13/2006 | NPPO - FINAL | ACONNOR | Approved | |
| 12/13/2006 | LANDSCAPE - FINAL | ACONNOR | Approved |