Permit: T05CM02246
Permit Details
Apply Date:
05/17/2005
Applicant:
APRIL ORTIZ
Description:
NEW: CONDOS: 100-105, 200-205
Contractors:
- PATHWAY DEVELOPMENTS INC ,
Permit Reviews
Permit Number - T05CM02246
Permit Status: C of o
Permit Description: NEW: CONDOS: 100-105, 200-205
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 05/17/2005 | PLANS OK TO SUBMIT - COMM | 05/18/2005 | COMPLETED |
| 05/18/2005 | 3RD PARTY REVIEW-COMMERCIAL | 06/14/2005 | COMPLETED |
| 06/14/2005 | POST 3RD PARTY REVIEW | 06/30/2005 | COMPLETED |
| 06/21/2006 | 3RD PARTY REVIEW-REVISION/OTHER | 06/21/2006 | COMPLETED |
| 06/30/2005 | REVISION | 06/30/2005 | COMPLETED |
| 06/30/2005 | POST 3RD PARTY REVIEW | 05/22/2006 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T05CM02246
Permit Status: C of o
Permit Description: NEW: CONDOS: 100-105, 200-205
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 05/17/2005 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T05CM02246
Permit Description: NEW: CONDOS: 100-105, 200-205
Total Completed Inspections - 42
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/30/2006 | ELECTRIC - UNDERGROUND | CCLEMENS | Approved | IVRS - Inspection :* OK TO COVER FEEDER RACEWAYS *NOTE: NEED TO STUB RACEWAYS ABOVE SLAB AND NO UFER AT THIS INSPECTION. |
| 07/03/2006 | PLUMBING - SEWER HCS CONNECT | RMYERS | Approved | IVRS - Inspection :* 1. PEX INSTALLED UNDERGROUND OK OK TO COVER SUBJECT TO REVISED PLAN SEWER INSTALLED OK OK TO COVER |
| 07/03/2006 | PLUMBING - ROUGH, SOIL | RMYERS | Approved | IVRS - Inspection :* |
| 07/21/2006 | BUILDING PRE-SLAB | AQUIROZ | Approved | IVRS - Inspection :* |
| 07/21/2006 | EXCAVATION/LAYOUT REBAR & ZON | AQUIROZ | Approved | IVRS - Inspection :* |
| 07/24/2006 | ELECTRIC - UFER | CCLEMENS | Approved | IVRS - Inspection :* |
| 08/10/2006 | BUILDING - PROGRESS | AQUIROZ | Approved | 2ND FLOOR DECKING OK |
| 09/14/2006 | ROOF NAILING | AQUIROZ | Approved | IVRS - Inspection :* |
| 10/24/2006 | EXT METAL CLIPS/EXT SHEATHING | AQUIROZ | Approved | IVRS - Inspection :* |
| 10/25/2006 | REINFORCED MASONRY PRE-GROUT | AQUIROZ | Approved | IVRS - Inspection :* |
| 11/13/2006 | STUCCO MESH | AQUIROZ | Approved | IVRS - Inspection :* |
| 11/29/2006 | PLUMBING - INTERMEDIATE | RMYERS | Approved | IVRS - Inspection :* CORRECTIONS MADE OK OK TO COVER ALL AREAS |
| 11/30/2006 | ELECTRIC - INTERMEDIATE | RHOLLAND | Approved | IVRS - Inspection :* 1. SUPPORT NM CABLES WITHIN 12" OF CANS 2. MISSING EXHAUST FANS OK SOFFITS EXCEPT FANS 1ST FLOOR |
| 12/01/2006 | FRAMING | AQUIROZ | Approved | IVRS - Inspection :* FIRE WALL ABOVE CEILING 2ND FLOOR OK |
| 12/27/2006 | MECHANICAL - INTERMEDIATE | JMILITEL | Approved | IVRS - Inspection :* PROVIDE PLATE STRAPS INSULATE & SEAL ALL SHEET METAL FITTINGS |
| 02/09/2007 | SHEET ROCK NAILING | JBURGE | Approved | 2ND FLOOR OK TO TAPE & TEXTURE |
| 02/12/2007 | FIRE SPKLR - OH PIPING & HYDRO | LTHOMAS | Approved | |
| 03/13/2007 | ELECTRIC - CABLE DROP | CCLEMENS | Approved | IVRS - Inspection :* 1) IDENTIFY SERVICE DISCONNECTS NEC 230.70 2) DO A BETTER JOB OF SECURING SERVICE TO STRUCTURE NEC 110.3 |
| 03/14/2007 | TEP CLEARANCE - AM | JWEATHER | Approved | TEC CLEARED FOR ALL METERS PER C. CLEMENS |
| 03/15/2007 | U VALUE FOR WINDOW | AQUIROZ | Approved | IVRS - Inspection :* |
| 03/21/2007 | SITE - SEWER | BBENEDON | Approved | IVRS - Inspection :* |
| 03/21/2007 | PLUMBING - YARD WTR LINE/TEST | BBENEDON | Approved | IVRS - Inspection :* |
| 03/27/2007 | FIRE - FINAL | LTHOMAS | Approved | |
| 03/27/2007 | FIRE SPKLR - FINAL | LTHOMAS | Approved | |
| 03/27/2007 | PLUMBING - ABOVE CEILING | RMYERS | Approved | IVRS - Inspection :* |
| 03/27/2007 | MECHANICAL - HOODS | CCLEMENS | Approved | IVRS - Inspection :* |
| 03/27/2007 | MECHANICAL - ABOVE CEILING | CCLEMENS | Approved | IVRS - Inspection :* |
| 03/27/2007 | ELECTRIC - OUTDOOR LIGHTING | CCLEMENS | Approved | IVRS - Inspection :* |
| 03/27/2007 | ELECTRIC - CONSTRUCTION POWER | CCLEMENS | Approved | IVRS - Inspection :* |
| 03/27/2007 | ELECTRIC - ABOVE CEILING | CCLEMENS | Approved | IVRS - Inspection :* |
| 03/27/2007 | SIGN - FINAL | JYBARRA | Approved | IVRS - Inspection :* |
| 03/28/2007 | PLUMBING - FINAL | RMYERS | Approved | IVRS - Inspection :* PLUMBING FINAL OK OK FOR C OF O S.T.O.I |
| 03/28/2007 | ELECTRIC - FINAL | CCLEMENS | Approved | IVRS - Inspection :* |
| 03/28/2007 | OUTDOOR LIGHTING FINAL | CCLEMENS | Approved | IVRS - Inspection :* |
| 03/28/2007 | MECHANICAL - FINAL | CCLEMENS | Approved | IVRS - Inspection :* |
| 03/28/2007 | LANDSCAPE - FINAL | ACONNOR | Approved | |
| 03/28/2007 | NPPO - FINAL | ACONNOR | Approved | |
| 03/29/2007 | RIGHT OF WAY - FINAL | DLEE | Approved | |
| 03/29/2007 | BUILDING - FINAL | AQUIROZ | Approved | IVRS - Inspection :* OK C OF O |
| 03/29/2007 | BUILDING ABOVE CEILING | AQUIROZ | Approved | IVRS - Inspection :* |
| 03/29/2007 | ENGINEERING - FINAL | MRUSSO | Approved | |
| 03/30/2007 | PERMIT FINALED | LJACKSON | Approved |