Permit: T02CM05314
Permit Details
Apply Date:
11/15/2002
Applicant:
N/A
Description:
TI:RETAIL
Architects:
- WOBKEN, TERRY GEORGE
Contractors:
- ADOLFSON AND PETERSON INC ,
Permit Reviews
Permit Number - T02CM05314
Permit Status: C of o
Permit Description: TI:RETAIL
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/17/2003 | RESUBMITTAL | 03/03/2003 | COMPLETED |
| 03/03/2003 | RESUBMITTAL | 04/16/2003 | COMPLETED |
| 07/02/2003 | REVISION | 07/02/2003 | COMPLETED |
| 10/29/2007 | REVISION - - 2ND | 12/06/2007 | COMPLETED |
| 11/15/2002 | COMMERCIAL TI | 12/27/2002 | COMPLETED |
| 12/06/2007 | REVISION - - 2ND | 12/21/2007 | COMPLETED |
| 12/21/2007 | REVISION - - 2ND | 12/21/2007 | ACTIVE |
Outstanding Activity Conditions
Permit Number - T02CM05314
Permit Status: C of o
Permit Description: TI:RETAIL
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 11/15/2002 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T02CM05314
Permit Description: TI:RETAIL
Total Completed Inspections - 27
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/25/2003 | MECHANICAL - ABOVE CEILING | JMILITEL | Approved | IVRS - Inspection 0000*/ 1) INSPECTED DUCT ABOVE PHARMACY 2) OK FOR CEILING TILES |
| 07/10/2003 | FIRE SPKLR - FINAL | JEGAN | Approved | IVRS - Inspection 0000* |
| 07/11/2003 | FIRE - FINAL | JEGAN | Approved | IVRS - Inspection 0000*/ 1) OK FOR C OF O |
| 07/11/2003 | FIRE - KITCHEN EXH HOOD FINAL | JEGAN | Approved | IVRS - Inspection 0000*/ 1) OK FOR C OF O |
| 07/11/2003 | STUCCO MESH | RSUBA | Approved | IVRS - Inspection 0000* |
| 07/29/2003 | ELECTRIC - ABOVE CEILING | RHOLLAND | Approved | IVRS - Inspection 0000* |
| 07/29/2003 | ELECTRIC - INTERMEDIATE | RHOLLAND | Approved | IVRS - Inspection 0000* |
| 07/30/2003 | MECHANICAL - FINAL | JMILITEL | Approved | IVRS - Inspection 0000*/ 1) ALL CORRECTIONS HAVE BEEN MADE 2) OK FOR C OF O |
| 07/30/2003 | MECHANICAL - PROGRESS | JMILITEL | Approved | |
| 07/30/2003 | MECHANICAL - INTERMEDIATE | JMILITEL | Approved | |
| 07/30/2003 | PLUMBING - FINAL | JSTANLEY | Approved | |
| 07/30/2003 | PLUMBING - PROGRESS | JSTANLEY | Approved | |
| 07/30/2003 | PLUMBING - GAS PRESS TEST FNL | JSTANLEY | Approved | |
| 07/30/2003 | PLUMBING - GAS PRESSURE TEST | JSTANLEY | Approved | |
| 07/30/2003 | PLUMBING - ABOVE CEILING | JSTANLEY | Approved | |
| 07/30/2003 | PLUMBING - INTERMEDIATE | JSTANLEY | Approved | |
| 07/30/2003 | PLUMBING - ROUGH, SOIL | JSTANLEY | Approved | |
| 08/06/2003 | SHEET ROCK NAILING | RSUBA | Approved | |
| 08/06/2003 | FRAMING | RSUBA | Approved | |
| 08/06/2003 | REINFORCED MASONRY PRE-GROUT | RSUBA | Approved | |
| 08/06/2003 | EXCAVATION/LAYOUT REBAR & ZON | RSUBA | Approved | |
| 12/13/2006 | SIGN - FINAL | JYBARRA | Approved | |
| 12/14/2006 | ENGINEERING - FINAL | JBRUCKME | Approved | NO PLANS AVAILABLE, NO ENGINEERING CONCERNS WERE OBSERVED THIS IS A CLOSE OUT OF A 2002 PERMIT. |
| 12/14/2006 | ENGINEERING - FINAL | JBRUCKME | Approved | PROVIDE DRAWINGS FOR INSPECTION. SITE WORK, DRAINAGE AND R/D BASIN MAY HAVE BEEN INCLUDED ON GRADING PERMIT AND MUST BE APPROVED FOR RELEASE OF CERTIFICATE OF OCCUPANCY. ADOLFSON AND PEDERSON - BRAD 602- 463-5897 |
| 12/15/2006 | RIGHT OF WAY - FINAL | PWHIDDON | Approved | PER EMAIL |
| 12/31/2007 | BUILDING - FINAL | RHOLLAND | Approved | IVRS - Inspection :* CANCELLED THESE GUYS ALSO NEED TO TURN IN ALL SPECIAL INSP. FORMS |
| 12/31/2007 | ELECTRIC - FINAL | RHOLLAND | Approved | IVRS - Inspection :* CANCELLED |