Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Details

Status:
Issued
Type:
Development Package
Address:
340 N 6TH AV
Apply Date:
06/11/2020
Applicant:
CHRIS HODGSON
Description:
Site/Grading/SWPPP / IID - Corbett Block, new entertainment and food service.

Permit Reviews

Permit Number - DP20-0125
Permit Status: Issued
Permit Description: Site/Grading/SWPPP / IID - Corbett Block, new entertainment and food service.
Start Date Submittal Complete Date Status  
01/06/2022 REVISION - - 1ST 03/18/2022 COMPLETED Review Details
03/16/2021 DEV PKG - RESUBMITTAL 04/23/2021 COMPLETED Review Details
05/12/2020 DEV PKG - OK TO SUBMIT 06/15/2020 COMPLETED Review Details
06/15/2020 DEV PKG 07/29/2020 COMPLETED Review Details
06/27/2022 REVISION - - 1ST 08/18/2022 COMPLETED Review Details
07/19/2021 DEV PKG - RESUBMITTAL 07/27/2021 COMPLETED Review Details
11/18/2020 DEV PKG - RESUBMITTAL 01/26/2021 COMPLETED Review Details
12/24/2021 DEV PKG - OK TO SUBMIT 01/06/2022 COMPLETED Review Details
04/17/2023 DEVELOPMENT PACKAGE REVIEW v.1 06/30/2023 APPROVED Review Details

Outstanding Inspections

Permit Status: Issued
Permit Number: DP20-0125
Permite Description: Site/Grading/SWPPP / IID - Corbett Block, new entertainment and food service.
Total Outstanding Inspections - 6
Last Inspection Date Description Inspector Results Comments
09/16/2022 SITE - Stormwater Setup and Controls N/A Complete (Recurring) {Activity date: 09/16/2022; Status: Continued; Inspector: BBENEDON; Comment: Entered by VVERA1 - Continued. Track out Protection installed} ; {Activity date: 02/01/2022; Status: Continued; Inspector: BBENEDON; Comment: Entered by VVERA1 - Continued. SWPPP, NOI , posted at East site entrance.

} ; {Activity date: 10/27/2021; Status: Continued; Inspector: BBENEDON; Comment: Entered by VVERA1 - Continued. Installation of waddle

} ; {Activity date: 10/19/2021; Status: Continued; Inspector: BBENEDON; Comment: Entered by NGARCIA3 - . Continued. Waddle installed along east site perimeter. Large material piles and debris on site.
320 N 6th Ave,
} ; {Activity date: 08/19/2021; Status: Partial Approval; Inspector: BBENEDON; Comment: Entered by NGARCIA3 - . Partially approved. Track out protection and Waddell} ; {Activity date: 08/10/2021; Status: Not ready for Inspection; Inspector: BBENEDON; Comment: Entered by RSALDAT1 - Not ready. Waddle on site, however not installed. Filter fabric laid on the ground at east entrance and needs to be installed a lower elevation to allow for a thicker patch of track out protection rock.
} ; {Activity date: 08/06/2021; Status: Continued; Inspector: BBENEDON; Comment: Entered by RSALDAT1 - 09150, 09152, 09154. Continued}
10/04/2022 SITE - Stormwater Follow-up N/A Complete (Recurring) {Activity date: 10/04/2022; Status: Continued; Inspector: BBENEDON; Comment: Entered by RSALDAT1 - Continued.} ; {Activity date: 09/29/2022; Status: Continued; Inspector: BBENEDON; Comment: Entered by NGARCIA3 - Continued. Minor track out noted after last rain event.
320 N 6th Ave,} ; {Activity date: 09/16/2022; Status: Continued; Inspector: BBENEDON; Comment: Entered by VVERA1 - Continued. No issues or concerns at this time. This was a courtesy unscheduled inspection. Please schedule inspections biweekly as requested
} ; {Activity date: 08/10/2022; Status: Continued; Inspector: BBENEDON; Comment: Entered by VVERA1 - Continued. Minor track out noted} ; {Activity date: 06/23/2022; Status: Continued; Inspector: BBENEDON; Comment: Entered by NGARCIA3 - continued
320 N 6th Ave,} ; {Activity date: 06/15/2022; Status: Continued; Inspector: BBENEDON; Comment: Entered by VVERA1 - Continued} ; {Activity date: 06/09/2022; Status: Continued; Inspector: BBENEDON; Comment: Entered by NGARCIA3 - Continued
320 N 6th Ave} ; {Activity date: 05/24/2022; Status: Continued; Inspector: BBENEDON; Comment: Entered by NGARCIA3 - Continued
320 N 6th Ave,} ; {Activity date: 05/11/2022; Status: Continued; Inspector: BBENEDON; Comment: Entered by VVERA1 - Continued} ; {Activity date: 04/26/2022; Status: Continued; Inspector: BBENEDON; Comment: Entered by NGARCIA3 - Continued
320 N 6th Ave} ; {Activity date: 04/21/2022; Status: Continued; Inspector: BBENEDON; Comment: Entered by NGARCIA3 - Continued. No issues at this time.
320 N 6th Ave} ; {Activity date: 04/01/2022; Status: Continued; Inspector: BBENEDON; Comment: Entered by VVERA1 - Continued} ; {Activity date: 03/30/2022; Status: Continued; Inspector: BBENEDON; Comment: Entered by VVERA1 - Continued} ; {Activity date: 03/17/2022; Status: Continued; Inspector: BBENEDON; Comment: Entered by NGARCIA3 - Continued

320N N 6th Ave,} ; {Activity date: 03/02/2022; Status: Continued; Inspector: BBENEDON; Comment: Entered by VVERA1 - Continued} ; {Activity date: 02/25/2022; Status: Continued; Inspector: BBENEDON; Comment: Entered by NGARCIA3 - Continued. No issues or concerns at this time

320 N 6th Ave} ; {Activity date: 12/09/2021; Status: Continued; Inspector: BBENEDON; Comment: Entered by RSALDAT1 - Continued. Kevin with Magnum and Craig with division two. I’m sure no offsite discharge occurs and is responsible to remove any offsite discharge as needed.} ; {Activity date: 10/13/2021; Status: Continued; Inspector: BBENEDON; Comment: Entered by NGARCIA3 - Continued. Large material and debris piles on site.
320N N 6th Ave,} ; {Activity date: 10/08/2021; Status: Continued; Inspector: BBENEDON; Comment: Entered by VVERA1 - 09154. Continued

} ; {Activity date: 08/31/2021; Status: Continued; Inspector: BBENEDON; Comment: Entered by NGARCIA3 - Continued} ; {Activity date: 08/10/2021; Status: Continued; Inspector: BBENEDON; Comment: Entered by RSALDAT1 - Continued. No issues at this time. Installation of controls in progress. Demolition in progress

} ; {Activity date: 08/06/2021; Status: Continued; Inspector: BBENEDON; Comment: Entered by RSALDAT1 - 09150, 09152, 09154. Continued}
08/23/2023 SITE - Stormwater Final Inspection N/A Not Ready construction fencing still surrounds site and construction debris in parking lot
08/24/2023 PDSD Site/Engineering Division - Landscaping N/A Partial Pass solid waste container still present, scheduled removal august 25 am, per job supervisor Josh with Sundt
08/23/2023 SITE - Engineering Final N/A Not Ready construction fencing still surrounds site and construction debris in parking lot
08/24/2023 COT - ENGR - Sign Final N/A Partial Pass solid waste container still present, scheduled removal august 25 am, per job supervisor Josh with Sundt

Completed Inspections

Permit Status: Issued
Permit Number: DP20-0125
Permit Description: Site/Grading/SWPPP / IID - Corbett Block, new entertainment and food service.
Total Completed Inspections - 6
Date Description Inspector Results Comments
12/09/2021 PDSD Engineering Division Pre-Construction Passed {Activity date: 12/09/2021; Status: Approved; Inspector: BBENEDON; Comment: Entered by RSALDAT1 - Approved. Greg Anderson with Division II phone number 240-0544

Kevin with Magnum number 704-0274

Please schedule Stormwater follow up inspections on a biweekly basis. Please schedule intermediate inspections anytime dirt is moved for utilities or any reason. Schedule intermediate and rebar inspections for trashenclosure , seven football is required Rebar required center. Photo documentation May be acceptable.
} ; {Activity date: 08/06/2021; Status: Continued; Inspector: BBENEDON; Comment: Entered by RSALDAT1 - 09150, 09152, 09154. Continued} ; {Activity date: 08/06/2021; Status: Partial Approval; Inspector: BBENEDON; Comment: Entered by RSALDAT1 - Partially approved. Rick with division 2. Magnum paving on site however no supervision. Installing site entrance on East side 5th Street. Will re-schedule inspection once signage and Stormwater protections are in place}
04/28/2023 PDSD Site/Engineering Division - NPPO Passed
07/10/2023 PDSD Site/Engineering Division - Grading Passed
08/25/2023 SITE - Stormwater Final Inspection Passed
08/31/2023 PDSD Site/Engineering Division - Landscaping Passed
08/31/2023 SITE - Engineering Final Passed

Documents

File Name Document Type  
APPROVED REV2_1_PLAN SET - CORBETT BLOCK - DP REV 2 - 2023-04-13_V1.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
PIMA CO DUST PERMIT - 2023_V1.PDF DOCUMENTS VIEW
APPROVED DEVELOPMENT PACKAGE.PDF DEVELOPMENT PACKAGE VIEW
CONTRACTOR IDENTIFICATION LETTER - CORBETT PROJECTS.PDF DOCUMENTS VIEW
NOTICE OF CONTRACTOR CHANGE TO SUNDT.PDF DOCUMENTS VIEW
COMMENT RESPONSE LETTER, 06.17.22.PDF DOCUMENTS VIEW
LANDSCAPE REVISION LETTER.PDF DOCUMENTS VIEW
REVISION LETTER.PDF DOCUMENTS VIEW
DEQ_FUGITIVEDUSTPERMIT.PDF DOCUMENTS VIEW
LETTER OF INTENT.PDF DOCUMENTS VIEW
PERMIT.PDF DOCUMENTS VIEW
PRE CON E-MAIL REQUEST TO SCHEDULE MEETING.PDF DOCUMENTS VIEW
SCOTT_W._TRANSP_ENGINEER_MEMO, CITY OF TUCSON.PDF DOCUMENTS VIEW
LOT_COMBO_APPROVAL_LETTER, PIMA COUNTY ASSESSOR.PDF DOCUMENTS VIEW
TEP FACILITIES MAP, 01.12.21.PDF DOCUMENTS VIEW
TEP POLE LOCATION MAP, 01.12.21.PDF DOCUMENTS VIEW
TEP APPROVAL LETTER, 01.12.21.PDF DOCUMENTS VIEW
GEOTECHNICAL STUDY.PDF DOCUMENTS VIEW
HYDROLOGY REPORT.PDF DOCUMENTS VIEW
PIMA COUNTY CONSOLIDATION REQUEST FORM.PDF DOCUMENTS VIEW
SWPPP.PDF DOCUMENTS VIEW
FUP APPLICATION.PDF DOCUMENTS VIEW
RES APPLICATION-REAL ESTATE SERVICES FORM.PDF DOCUMENTS VIEW
TUCSON ELECTRIC POWER, FACILITY MAP, 07.10.20.PDF DOCUMENTS VIEW
APPLICATION, 06.15.2020.PDF DOCUMENTS VIEW
NPPP_EXEMPTION_LETTER, NORRIS DESIGN.PDF DOCUMENTS VIEW