Inspection Status: Not Ready
Inspection History: PDSD Site/Engineering Division - Landscaping
Permit Number - DP20-0125
Inspection Description - PDSD Site/Engineering Division - Landscaping
Inspection Status - Not Ready
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/27/2022 | PDSD Site/Engineering Division - Landscaping | Not Ready | ||
10/27/2022 | PDSD Site/Engineering Division - Landscaping | Not Ready | ||
10/18/2022 | PDSD Site/Engineering Division - Landscaping | BBENEDON | Partial Approval | Entered by NGARCIA3 - Partially approved. Irrigation 320 N 6th Ave |
07/26/2022 | PDSD Site/Engineering Division - Landscaping | BBENEDON | Not ready for Inspection | Entered by NGARCIA3 - Not ready 320 N 6th Ave, |
07/03/2023 | PDSD Site/Engineering Division - Landscaping | Not Ready | No one on site at this time site is locked. Inspection will be rescheduled at a later date. | |
07/03/2023 | PDSD Site/Engineering Division - Landscaping | Not Ready | No one outside at this time inspection rescheduled for a later date | |
07/10/2023 | PDSD Site/Engineering Division - Landscaping | Not Ready | Contractor needs to replace some of the trees that were installed because they’re dead and some fencing in the front area and in the back area. And take a good look at the handicap parking area. | |
07/10/2023 | PDSD Site/Engineering Division - Landscaping | Not Ready | Contractor needs to replace the trees that are dead, and some fencing on the south end and on the north end | |
08/21/2023 | PDSD Site/Engineering Division - Landscaping | Partial Pass | Complete all work on the Approved Plans prior to rescheduling this Inspection | |
08/21/2023 | PDSD Site/Engineering Division - Landscaping | Partial Pass | Complete all work on the Approved Plans prior to rescheduling this Inspection | |
08/24/2023 | PDSD Site/Engineering Division - Landscaping | Partial Pass | solid waste container still present, scheduled removal august 25 am, per job supervisor Josh with Sundt | |
08/24/2023 | PDSD Site/Engineering Division - Landscaping | Partial Pass | solid waste container still present, scheduled removal august 25 am, per job supervisor Josh with Sundt | |
08/31/2023 | PDSD Site/Engineering Division - Landscaping | Passed | ||
08/31/2023 | PDSD Site/Engineering Division - Landscaping | Passed |