Inspection Status: Passed
Inspection History: PDSD Engineering Division Pre-Construction SITE
| Date |
Description |
Inspector |
Results |
Comments |
| 12/09/2021 |
PDSD Engineering Division Pre-Construction SITE |
BBENEDON |
Approved |
Entered by RSALDAT1 - Approved. Greg Anderson with Division II phone number 240-0544
Kevin with Magnum number 704-0274
Please schedule Stormwater follow up inspections on a biweekly basis. Please schedule intermediate inspections anytime dirt is moved for utilities or any reason. Schedule intermediate and rebar inspections for trashenclosure , seven football is required Rebar required center. Photo documentation May be acceptable.
|
| 08/06/2021 |
PDSD Engineering Division Pre-Construction SITE |
BBENEDON |
Continued |
Entered by RSALDAT1 - 09150, 09152, 09154. Continued |
| 08/06/2021 |
PDSD Engineering Division Pre-Construction SITE |
BBENEDON |
Partial Approval |
Entered by RSALDAT1 - Partially approved. Rick with division 2. Magnum paving on site however no supervision. Installing site entrance on East side 5th Street. Will re-schedule inspection once signage and Stormwater protections are in place |