Permit Details

Status:
Complete
Type:
Development Package
Address:
1110 N STONE AV
Address NEW:
1110 N STONE AV
Apply Date:
06/27/2017
Applicant:
Lisa Bowers
Description:
SITE/GRADE - POPEYES RESTAURANT

Permit Reviews

Permit Number - DP17-0154
Permit Status: Complete
Permit Description: SITE/GRADE - POPEYES RESTAURANT
Start Date Submittal Complete Date Status  
02/04/2019 REVISION - - 2ND 02/04/2019 COMPLETED Review Details
02/20/2019 REVISION - - 2ND 03/05/2019 COMPLETED Review Details
03/06/2018 RESUB - SITE and/or GRADING 04/06/2018 COMPLETED Review Details
04/06/2018 RESUB - SITE/GRADING ALL 11/08/2018 COMPLETED Review Details
06/27/2017 DEV PKG - OK TO SUBMIT 06/27/2017 COMPLETED Review Details
06/27/2017 SITE and/or GRADING 09/25/2017 COMPLETED Review Details
09/25/2017 RESUB - SITE and/or GRADING 03/06/2018 COMPLETED Review Details
11/08/2018 REVISION - - 1ST 11/08/2018 COMPLETED Review Details

Completed Inspections

Permit Status: Complete
Permit Number: DP17-0154
Permit Description: SITE/GRADE - POPEYES RESTAURANT
Total Completed Inspections - 9
Date Description Inspector Results Comments
01/30/2019 SITE - Stormwater Setup and Controls Passed {Activity date: 01/30/2019; Status: Approved; Inspector: BBENEDON; Comment: Entered by CBELL1 - } ; {Activity date: 01/22/2019; Status: Not ready for Inspection; Inspector: BBENEDON; Comment: Entered by VFLORES1 - There are no controls in place , however no swipe p is required .}
05/15/2019 PDSD Site/Engineering Division - NPPO Passed {Activity date: 05/15/2019; Status: Approved; Inspector: BBENEDON; Comment: Entered by CBELL1 - }
05/15/2019 SITE - Stormwater Follow-up Passed {Activity date: 05/15/2019; Status: Approved; Inspector: BBENEDON; Comment: Entered by CBELL1 - } ; {Activity date: 04/04/2019; Status: Continued; Inspector: BBENEDON; Comment: Entered by CBELL1 - There is some traffic out into the alley, but nine onto Speedway at this time.} ; {Activity date: 03/26/2019; Status: Continued; Inspector: BBENEDON; Comment: Entered by CBELL1 - There is no track out onto Speedway as the gate is closed. There is some track out into the alley. No concerns at this time.} ; {Activity date: 03/12/2019; Status: Continued; Inspector: BBENEDON; Comment: Entered by CBELL1 - There are no issues or concerns at this time} ; {Activity date: 02/19/2019; Status: Continued; Inspector: bbenedo1; Comment: Entered by BBENEDO1 - Minor track out onto the sidewalk on stone.
Protection in place.
No other issues.} ; {Activity date: 02/06/2019; Status: Continued; Inspector: BBENEDON; Comment: Entered by CBELL1 - The site is closed due to a rain event, there are no concerns or issues at this time.} ; {Activity date: 02/05/2019; Status: Continued; Inspector: BBENEDON; Comment: Entered by CBELL1 - There are no issues at this time.} ; {Activity date: 01/30/2019; Status: Continued; Inspector: BBENEDON; Comment: Entered by CBELL1 - Controls are in place as needed.} ; {Activity date: 01/22/2019; Status: Continued; Inspector: BBENEDON; Comment: Entered by VFLORES1 - There is notable track out onto Stone Avenue . Aaron with Boyd Excavating said he will take care of it .}
05/15/2019 SITE - Stormwater Final Inspection Passed {Activity date: 05/15/2019; Status: Approved; Inspector: BBENEDON; Comment: Entered by CBELL1 - }
05/16/2019 PDSD Engineering Division Pre-Construction SITE Passed {Activity date: 05/16/2019; Status: Approved; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - } ; {Activity date: 01/22/2019; Status: Partial Approval; Inspector: BBENEDON; Comment: Entered by VFLORES1 - Rick with McManus construction 269 - 9783 and Erin Boyd with Boyd Excavating. No swipp required however contractor is required to clean up any track out onto public streets as needed. Inspector suggest controls to help mitigate track out. Call for inspections of your trash enclosure when you are ready and please call in for inspections of stormwater control periodically.}
05/16/2019 COT - ENGR - Signage Final Passed {Activity date: 05/16/2019; Status: Approved; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - }
05/21/2019 PDSD Site/Engineering Division - Landscaping Passed {Activity date: 05/21/2019; Status: Approved; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - Provide galvanized tie wire and braided hose at tree staking.} ; {Activity date: 05/16/2019; Status: Not ready for Inspection; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - Complete the landscaping, stake the trees, complete the riprap, install the ground cover as shown. Complete the work in the right of way, sidewalk at the south entrance.} ; {Activity date: 05/15/2019; Status: Not ready for Inspection; Inspector: BBENEDON; Comment: Entered by CBELL1 - Landscaper needs to remove small shrubs in water harvesting areas on the south side of the building and lower the grade to the six -9Inches specified on the plans. Stake trees for the detail}
05/21/2019 ENGR Engineering Final Passed {Activity date: 05/21/2019; Status: Approved; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - Provide galvanized tie wire and braided hose at tree staking.} ; {Activity date: 05/16/2019; Status: Not ready for Inspection; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - Complete the landscaping, stake the trees, complete the riprap, install the ground cover as shown. Complete the work in the right of way, sidewalk at the south entrance.} ; {Activity date: 05/15/2019; Status: Denied; Inspector: BBENEDON; Comment: Entered by CBELL1 - Harvesting areas on the south side of the site need to be dug down substantially.} ; {Activity date: 05/14/2019; Status: Not ready for Inspection; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - I walk the site with Pete and we discussed which areas still need to come down. Plan calls for 6-9 She has depression in landscaped areas.}
05/21/2019 ENGR Grading Final Passed {Activity date: 05/21/2019; Status: Approved; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - Provide galvanized tie wire and braided hose at tree staking.}

Documents

File Name Document Type  
001_SHEET 1 OF 9.TIF DEVELOPMENT PACKAGE VIEW
002_SHEET 2 OF 9.TIF DEVELOPMENT PACKAGE VIEW
003_SHEET 3 OF 9.TIF DEVELOPMENT PACKAGE VIEW
004_SHEET 4 OF 9.TIF DEVELOPMENT PACKAGE VIEW
005_SHEET 5 OF 9.TIF DEVELOPMENT PACKAGE VIEW
006_L-1.TIF DEVELOPMENT PACKAGE VIEW
007_L-2.TIF DEVELOPMENT PACKAGE VIEW
008_L-3.TIF DEVELOPMENT PACKAGE VIEW
009_L-4.TIF DEVELOPMENT PACKAGE VIEW
None DOCUMENTS VIEW
GEOTECH ENGINEERING EVALUATION.PDF DOCUMENTS VIEW
None DOCUMENTS VIEW