Permit: DP16-0238
Permit Details
Apply Date:
12/29/2016
Applicant:
Brandy Burke
Description:
SITE/GRADING - Downtown Clifton Motel expansion.
Permit Reviews
Permit Number - DP16-0238
Permit Status: Complete
Permit Description: SITE/GRADING - Downtown Clifton Motel expansion.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 04/20/2017 | DEV PKG - RESUBMITTAL | 05/16/2017 | COMPLETED |
| 05/16/2017 | DEV PKG - RESUBMITTAL | 09/28/2018 | COMPLETED |
| 09/24/2019 | DEV PKG - OK TO SUBMIT | 10/25/2019 | COMPLETED |
| 10/25/2019 | REVISION - - 2ND | 12/04/2019 | COMPLETED |
| 11/13/2018 | DEV PKG - REVISION | 11/16/2018 | COMPLETED |
| 12/29/2016 | DEV PKG - OK TO SUBMIT | 12/29/2016 | COMPLETED |
| 12/29/2016 | DEV PKG | 04/20/2017 | COMPLETED |
Completed Inspections
Permit Status: Complete
Permit Number: DP16-0238
Permit Description: SITE/GRADING - Downtown Clifton Motel expansion.
Total Completed Inspections - 10
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/01/2018 | PDSD Engineering Division Pre-Construction SITE | Passed | {Activity date: 10/01/2018; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - MET WITH THE CONTRACTOR AND DISCUSSED WHAT WILL BE NEEDED FOR THIS SITE ONCE IT GETS UNDERWAY NEXT WEEK. FIRST THEY WILL BE WORKING ON THE REMOVAL OF THE EXISTING STEM WALLS FROM AROUND THE SITE AND THEN PROCEED TO BUILD ALL OF THE PADS FOR THE BUILDINGS(4). I HAVE ASKED THAT THEY SCHEDULE THIS SITE FOR INSPECTIONS EVRY TWO WEEKS DURING THE DEMO AND THE MATERIAL IMPORT FOR THE BUILDING OF THE PADS, AFTER THAT THEY CAN SCHEDULE THIS SITE FOR A ONCE A MONTH INSPECTION OR AS NEEDED ON A REGULAR BASIS. ALSO THE CONTRACTOR WILL BE PLACING WADDLE MATERIAL AROUND THE SITE TO ENSURE THAT THERE ARE NO ISSUES WITH THE STORMWATER FOR THIS SITE.} | |
| 10/07/2019 | PDSD Site/Engineering Division - NPPO | Passed | {Activity date: 10/07/2019; Status: Approved; Inspector: RLEDONNE; Comment: Entered by DMERANZ1 - } | |
| 10/07/2019 | SITE - Stormwater Follow-up | Passed | {Activity date: 10/07/2019; Status: Approved; Inspector: RLEDONNE; Comment: Entered by DMERANZ1 - } ; {Activity date: 08/16/2019; Status: Continued; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - I met with Mike on site and reminded him to keep the sidewalk and street clear of construction materials and dirt. And to schedule storm water inspections by weekly.} ; {Activity date: 08/15/2019; Status: Continued; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - sidewalk along stone av is blocked with no signage. A right of way permit is required, or keep sidewalk clear of temp fencing and rocks. Trackout Controls are needed at the east entrance to the site.} |
|
| 10/07/2019 | SITE - Stormwater Setup and Controls | Passed | {Activity date: 10/07/2019; Status: Approved; Inspector: RLEDONNE; Comment: Entered by DMERANZ1 - } | |
| 10/07/2019 | COT - ENGR - Signage Final | Passed | {Activity date: 10/07/2019; Status: Approved; Inspector: RLEDONNE; Comment: Entered by DMERANZ1 - } ; {Activity date: 09/24/2019; Status: Not ready for Inspection; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - Contractor has started excavation for trash enclosure pad and on-site walkways.} | |
| 10/09/2019 | SITE - Stormwater Final Inspection | Passed | {Activity date: 10/09/2019; Status: Approved; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - } ; {Activity date: 10/07/2019; Status: Not ready for Inspection; Inspector: RLEDONNE; Comment: Entered by DMERANZ1 - } | |
| 11/18/2019 | PDSD Site/Engineering Division - Landscaping | Passed | {Activity date: 11/18/2019; Status: Approved; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - } ; {Activity date: 10/09/2019; Status: Not ready for Inspection; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - Matt and Aparna with MW Morrissey. Provide 6 inch recessed landscaped areas as shown per note number three on your grading plan . Depress landscaping areas 6 inches below curb opening at driveway location. Complete landscaping, stabilization and tree staking. Provide a revision for the deletion of below ground water harvesting. Complete stabilized accessible path, also striping between buildings (cross slope exceeds 2%), We will check for slope after it has been completed. Correct accessible signage, install per detail and in the center of the stall. Provide documentation for all changes.} ; {Activity date: 10/07/2019; Status: Not ready for Inspection; Inspector: RLEDONNE; Comment: Entered by DMERANZ1 - Complete all landscaping for approved plans.} ; {Activity date: 08/16/2019; Status: Not ready for Inspection; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - Landscaping to be installed within the right way to be inspected by transportation} |
|
| 11/18/2019 | ENGR Grading Final | Passed | {Activity date: 11/18/2019; Status: Approved; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - } ; {Activity date: 10/09/2019; Status: Not ready for Inspection; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - Matt and Aparna with MW Morrissey. Provide 6 inch recessed landscaped areas as shown per note number three on your grading plan . Depress landscaping areas 6 inches below curb opening at driveway location. Complete landscaping, stabilization and tree staking. Provide a revision for the deletion of below ground water harvesting. Complete stabilized accessible path, also striping between buildings (cross slope exceeds 2%), We will check for slope after it has been completed. Correct accessible signage, install per detail and in the center of the stall. Provide documentation for all changes.} ; {Activity date: 10/07/2019; Status: Not ready for Inspection; Inspector: RLEDONNE; Comment: Entered by DMERANZ1 - } |
|
| 12/12/2019 | SITE - Zoning Final | Passed | {Activity date: 12/12/2019; Status: Approved; Inspector: RSALDAT1; Comment: Entered by RSALDAT1 - Inspection of exterior of abutting historic structure, located on the most northern side of the property and is addressed as 475 S. Stone. Inspection was conducted Post construction of the permitted building and a walk around the perimeter of historic structure found no signs of movement. Report generated and meeting with associated Planners found that the Zoning Final met all criteria, will close this Zoning Final as compliance.} ; {Activity date: 12/05/2019; Status: Not ready for Inspection; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - Contractor could show no documentation confirming vibration study.} ; {Activity date: 11/18/2019; Status: Not ready for Inspection; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - Comply with the previously noted requirements. Provide a copy of the city approved revised plan. Complete all work shown. Correct cross slopes where required.} ; {Activity date: 10/09/2019; Status: Not ready for Inspection; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - Complete vibration study and demo permit.} ; {Activity date: 10/07/2019; Status: Not ready for Inspection; Inspector: RLEDONNE; Comment: Entered by DMERANZ1 - } | |
| 12/20/2019 | ENGR Engineering Final | Passed | {Activity date: 12/20/2019; Status: Approved; Inspector: BBENEDON; Comment: Entered by PMARTIN1 - } ; {Activity date: 12/05/2019; Status: Partial Approval; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - Pending approval of zoning requirements; vibration study} ; {Activity date: 11/18/2019; Status: Not ready for Inspection; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - Comply with the previously noted requirements. Provide a copy of the city approved revised plan. Complete all work shown. Correct cross slopes where required.} ; {Activity date: 10/09/2019; Status: Not ready for Inspection; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - Matt and Aparna with MW Morrissey. Provide 6 inch recessed landscaped areas as shown per note number three on your grading plan . Depress landscaping areas 6 inches below curb opening at driveway location. Complete landscaping, stabilization and tree staking. Provide a revision for the deletion of below ground water harvesting. Complete stabilized accessible path, also striping between buildings (cross slope exceeds 2%), We will check for slope after it has been completed. Correct accessible signage, install per detail and in the center of the stall. Provide documentation for all changes.} |