Inspection Status: Passed
Inspection History: PDSD Site/Engineering Division - Landscaping
| Date |
Description |
Inspector |
Results |
Comments |
| 11/18/2019 |
PDSD Site/Engineering Division - Landscaping |
BBENEDON |
Approved |
Entered by DMERANZ1 - |
| 10/09/2019 |
PDSD Site/Engineering Division - Landscaping |
BBENEDON |
Not ready for Inspection |
Entered by DMERANZ1 - Matt and Aparna with MW Morrissey. Provide 6 inch recessed landscaped areas as shown per note number three on your grading plan . Depress landscaping areas 6 inches below curb opening at driveway location. Complete landscaping, stabilization and tree staking. Provide a revision for the deletion of below ground water harvesting. Complete stabilized accessible path, also striping between buildings (cross slope exceeds 2%), We will check for slope after it has been completed. Correct accessible signage, install per detail and in the center of the stall.
Provide documentation for all changes. |
| 09/24/2019 |
PDSD Site/Engineering Division - Landscaping |
BBENEDON |
Not ready for Inspection |
Entered by DMERANZ1 - Contractor has started excavation for trash enclosure pad and on-site walkways. |
| 11/18/2019 |
PDSD Site/Engineering Division - Landscaping |
BBENEDON |
Approved |
Entered by DMERANZ1 - |
| 10/09/2019 |
PDSD Site/Engineering Division - Landscaping |
BBENEDON |
Not ready for Inspection |
Entered by DMERANZ1 - Matt and Aparna with MW Morrissey. Provide 6 inch recessed landscaped areas as shown per note number three on your grading plan . Depress landscaping areas 6 inches below curb opening at driveway location. Complete landscaping, stabilization and tree staking. Provide a revision for the deletion of below ground water harvesting. Complete stabilized accessible path, also striping between buildings (cross slope exceeds 2%), We will check for slope after it has been completed. Correct accessible signage, install per detail and in the center of the stall.
Provide documentation for all changes. |
| 10/07/2019 |
PDSD Site/Engineering Division - Landscaping |
RLEDONNE |
Not ready for Inspection |
Entered by DMERANZ1 - Complete all landscaping for approved plans. |
| 08/16/2019 |
PDSD Site/Engineering Division - Landscaping |
BBENEDON |
Not ready for Inspection |
Entered by DMERANZ1 - Landscaping to be installed within the right way to be inspected by transportation |