Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: TR-PIA-0824-00011
Permit Details
Status:
Inspections
Type:
Private Improvement Agreement (PIA)
Address:
9210 E VALENCIA RD
Address NEW:
9210 E VALENCIA RD
Apply Date:
08/23/2024
Applicant:
Description:
Private Improvement Agreement for the Chase Bank Valencia project - DP TD-DEV-0424-00110. ROW Improvements include curbing, sidewalk, curb access ramps, asphalt pavement repair/patch and and asphalt driveways. Water improvements to be done under plans permitted by Tucson Water, sewer improvements to be don under plans permitted by PCRWRD.
Permit Reviews
Permit Number - TR-PIA-0824-00011
Permit Status: Inspections
Permit Description: Private Improvement Agreement for the Chase Bank Valencia project - DP TD-DEV-0424-00110. ROW Improvements include curbing, sidewalk, curb access ramps, asphalt pavement repair/patch and and asphalt driveways. Water improvements to be done under plans permitted by Tucson Water, sewer improvements to be don under plans permitted by PCRWRD.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 08/23/2024 | PRIVATE IMPROVEMENT AGREEMENT REVIEW v.1 | 09/19/2024 | REQUIRES RESUBMIT |
| 05/15/2025 | PRIVATE IMPROVEMENT AGREEMENT REVIEW v.3 | 05/22/2025 | REQUIRES RESUBMIT |
| 05/22/2025 | PRIVATE IMPROVEMENT AGREEMENT REVIEW v.4 | 05/23/2025 | APPROVED |
| 04/24/2025 | PRIVATE IMPROVEMENT AGREEMENT REVIEW v.2 | 05/14/2025 | REQUIRES RESUBMIT |
Conditions
Permit Number - TR-PIA-0824-00011
Permit Status: Inspections
Permit Description: Private Improvement Agreement for the Chase Bank Valencia project - DP TD-DEV-0424-00110. ROW Improvements include curbing, sidewalk, curb access ramps, asphalt pavement repair/patch and and asphalt driveways. Water improvements to be done under plans permitted by Tucson Water, sewer improvements to be don under plans permitted by PCRWRD.
| Date | Description | Comments |
|---|---|---|
| 05/21/2025 |
Completed Inspections
Permit Status: Inspections
Permit Number: TR-PIA-0824-00011
Permit Description: Private Improvement Agreement for the Chase Bank Valencia project - DP TD-DEV-0424-00110. ROW Improvements include curbing, sidewalk, curb access ramps, asphalt pavement repair/patch and and asphalt driveways. Water improvements to be done under plans permitted by Tucson Water, sewer improvements to be don under plans permitted by PCRWRD.
Total Completed Inspections - 8
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/10/2025 | TRSP - PIA - Pre-Construction Meeting | Passed | ||
| 07/17/2025 | TRSP - PIA - AB Placement | Passed | This is temporary AB with a hot mix of asphalt that will be placed afterward. It will not last more than a couple of weeks due to Valencia widening project. |
|
| 06/27/2025 | TRSP - PIA - Barricade - Setup/Takedown/Routine | Passed | I called Southwest Barricade to have them remove the 40mph sign on the E bound traffic on Valencia. It has been an ongoing issue with the traffic control. | |
| 07/10/2025 | TRSP – PIA – Demo/Clearing and Grubbing/Grading/Earthwork | Passed | Utility sleeves for fiber optic and electricity still needs to be trenched and installed. After speaking with the super, Bradley, the work is supposed to be done today or tomorrow. No PIA work being done today. | |
| 07/09/2025 | TRSP - PIA - Curb Placement | Passed | Concrete curb return was poured at the most east end of the project. Same mix used for ADA ramp was used. | |
| 07/14/2025 | TRSP - PIA - Sidewalk Placement | Passed | ADA ramp was poured utilizing approved mix from CEMEX. ADA slope percentages met standards and specs utilizing a smart level. Truncated domes were installed according to plans. Area was prepared by Day's Excavation; base was AB brought up on lifts using moisture and tamp vibrating plate. | |
| 07/18/2025 | TRSP - PIA - Roadway Subgrade | Passed | Temporary gravel and AB has been placed along Valencia roadway and the E driveway entry. On-site asphalt paving took place, and about a foot and a half spilled on to off-site in order for a clean cut to be made by Borderland when they pave Valencia. | |
| 10/21/2025 | TRSP - PIA - Engineering Final - Completion of PIA Work (Final Lot Release/Acceptance) | Passed | Final Re-inspection was done for broken sidewalk panels. They were re-poured, inspected, and passed. |